Mann, Berens & Wisner, LLP, Attorneys

Follow MBW on Facebook

Jay M. Mann, Esq.

Quia Timet: A Remedy for the Fearful Surety

American Bar Association, 20 Forum 685, Summer 1985

Please note that this web-formatted version of the article does not include citations and other footnotes. To view the original footnoted article with related appendices, please view the PDF version.

I. Introduction

According to Black’s Law Dictionary, quia timet is a Latin phrase meaning “because he fears or apprehends.” In fact, quia timet is the technical name of an equitable remedy which can be extremely valuable to the surety practitioner. Although bills quia timet date back to ancient Common Law, their modem applications have not been generally known or sufficiently used by the surety industry.

Quia timet has been the subject of discussion by numerous legal scholars. In particular, several articles of recent vintage have treated limited aspects of the broad quia timet remedies which are available to sureties. However, no article known to the author has made a comprehensive study of quia timet since the article of Walter W. Downs, entitled “Quia timet as a Preventer of Anticipated Mischief,” presented to the 1956 Annual Convention of the American Bar Association.

There have been significant developments in the case law of quia timet in the years since the Downs article. This writing is intended to provide an update of the law of quia timet, and also to furnish the reader with practical suggestions for use of this valuable weapon in the surety’s modem-day arsenal of remedies.

II. HISTORICAL BACKGROUND

A bill quia timet is a bill in equity to protect a party against the occurrence of some future injury which he fears he may suffer, and which he cannot avoid by a present action at law. It is a remedy of particular importance to the surety of a construction contractor because it may be utilized, under appropriate circumstances, prior to the time that the surety’s liability has become fixed. Quia timet is not, however, restricted to use by sureties. For example, quia timet may properly be used to seek cancellation of a negotiable instrument which is voidable while in the hands of a present holder, but which may be enforced against the maker if it is transferred to a bona fide purchaser for value.

Quia timet was originally enforced as a writ of prevention. There were six writs at ancient Common Law (all of which are now obsolete) that could be maintained quia timet before “molestation, distress or impleading.” These were called Brevia Anticipantia – anticipatory relief to accomplish the ends of precautionary justice. The common thread underlying these six ancient writs was that quia timet should be applied so as to prevent wrongs or anticipated mischiefs, and not merely to redress wrongs after they were done.

Many courts have taken the Latin phrase literally and applied bills quia timet in unexpected "fearful" contexts. These include the following:

  1. Suit to determine plaintiff’s status as the wife of defendant;

  2. Suit by wife to declare that Mexican divorce decree was invalid;

  3. Suit for cancellation of execution upon judgment;

  4. Suit to determine title to shares of stock;

  5. Suit to determine liability insurer’s duty to defend;

  6. Suit to remove cloud on title;

  7. Suit to establish upon real property;

  8. Suit to quiet title to vessel;

  9. Suit by property owner to determine that he had never been the owner of a supper club and therefore not liable for cabaret taxes;

  10. Suit to determine patent infringement;

  11. Suit to perpetuate testimony of severely injured person in action thereafter commenced;

  12. Suit to set aside antenuptial agreement due to fraud and misrepresentation.

These cases are representative of the many factual situations to which quia timet may be applicable. All of these cases involved an absence of actual present injury, a reasonable apprehension of future injury, and danger that irreparable harm would result if the relief prayed for was not granted. The combination of these essential elements made quia timet appropriate relief under the disparate factual circumstances of the above cases.

III. CONSTRUCTION SURETY’S USE OF QUIA TIMET

It has been said that ‘no principle in equity is more familiar or more firmly established than that a surety, after the debt for which he is liable has become due, without paying or even being called on to pay a debt, may me a bill in equity in the nature of a bill quia timet to compel the principal to exonerate him by its payment, provided no rights of creditors are prejudiced thereby.’

This oft-repeated statement demonstrates the importance of quia timet in surety law. Nevertheless, the courts and legal scholars have frequently confused the exoneration and quia timet rights of the surety. An understanding of the distinction between exoneration and quia timet is essential to proper representation of the surety.

In the context of a bonded construction contractor, exoneration is the surety’s right to require that contract proceeds be used to pay contract obligations of its principal which, if unpaid, shall become the obligation of the surety. Also, exoneration includes the surety’s right to require its principal to use his own funds to discharge the primary obligation for payment, even in the absence of the surety having made any payment itself in discharge of its secondary bond obligation.

Quia timet is the surety’s right to relief when it justifiably fears that contract proceeds may be diverted from contract obligations. Also, quia timet includes the surety’s right to require its principal to post security for discharge of his principal obligation for payment under appropriate circumstances of anticipated liability by the surety. A surety is under no obligation to seek quia timet relief. On the other hand, the surety’s failure to act promptly at the time of anticipated liability may result in substantially increased liability at a later date. This article will next explore the two areas of quia timet relief that most frequently arise in surety practice: (a) preventing the diversion of contract funds, and (b) requiring the principal and indemnitors to post security for anticipated bond losses.

A. Preventing the Diversion of Contract Funds

1. Surety’s Rights in Contract Funds

Upon the principal contractor’s default of the bonded construction contract (including default in obligations to laborers and materialmen), the surety is entitled to have contract proceeds applied to contract obligations. Alternatively, the surety is entitled to be reimbursed from contract proceeds to the extent of payments made in discharge of bond obligations. The practical problem facing the surety is how to preserve the contract funds until its obligations are clearly defined.

In Prairie State Bank v. United States, the United States Supreme Court first addressed the surety’s subrogated interest in unpaid contract funds. It was held that a completing surety on a public works project was entitled to receive the contract funds because it was legally subrogated to the owner’s position. Such common law subrogation allowed the surety to prevail over a bank-assignee of the contractor who made a two-fold argument to the contract funds, i.e., the bank asserted a contractual claim arising from a written assignment executed by the contractor and also an equitable claim because its money had been used by the contractor to finance performance at the bonded project. The Court rejected both claims by the bank, on the rationale that the contract proceeds constituted the security which the owner held to guarantee performance by the contractor. When the surety performed in lieu of the contractor, it became subrogated to all rights of the owner, including the owner’s right to hold contract proceeds as security and backcharge to the extent of losses.

Twelve years later, the Supreme Court expanded the Prairie State ruling in Henningson v. United States Fidelity & Guaranty Company. In addition to the surety’s subrogated interest for completion of construction, the Court held that the surety also had a subrogated interest in contract proceeds for reimbursement of claims that the surety was required to pay laborers and materialmen under the payment bond for the project.

The Prairie State and Henningson cases were decided at the time of the Heard Act, the predecessor of the Miller Act. Any doubt as to the continuing validity of the surety’s rights in unpaid contract proceeds under the Miller Act was resolved in the 1962 United States Supreme Court case of Pearlman v. Reliance Insurance Company. In this contest between the surety (who had paid claims pursuant to its Miller Act payment bond obligations) and the trustee for the bankrupt contractor, the Court ruled that the surety was entitled to the contract balances. Mr. Justice Black, writing for the majority, stated:

We therefore hold in accord with the established legal principles stated above that the Government had a right to use the retained fund to pay laborers and materialmen; that the laborers and materialmen had a right to be paid out of the fund; that the contractor, had he completed his job and paid his laborers and materialmen, would have become entitled to the fund; and that the surety, having paid the laborers and materialmen, is entitled to the benefit of all these rights to the extent necessary to reimburse it. Consequently, since the surety in this case has paid out more than the amount of the existing fund, it has a right to all of it. (Emphasis added.)

A new challenge is now being asserted to the surety’s subrogated right to contract proceeds, in the situation when the principal contractor is a chapter 11 (reorganization) debtor in a pending bankruptcy proceeding. Similar to the argument rejected in the Pearlman case regarding the effect of the Miller Act, it has been argued that enactment of the 1978 Bankruptcy Code impliedly overruled earlier Supreme Court cases dealing with the subrogation rights of a surety. At least one bankruptcy court, in a published opinion, accepted the argument that the surety’s subrogation rights were modified by the new bankruptcy law, while another bankruptcy court has ruled in favor of the surety on this issue. Particularly due to the prevalence of chapter 11 bankruptcy filings, this is an important issue that will probably have to be decided ultimately by the United States Supreme Court. It is a subject which is beyond the scope of this article, and so it will be assumed in this article that the surety’s subrogation right to contract proceeds continues intact in the bankruptcy context, and all other situations of default by the principal contractor.

2. Requirements for Quia Timet relief to Protect Contract Funds

The right to have contract proceeds applied to contract obligations is meaningless unless the surety may take protective actions to prevent dissipation of the proceeds. Before actually making any bond payments, the surety does not technically have subrogation rights in the interest proceeds. If, however, it has a reasonable basis for fearing dissipation, then the surety may bring a quia timet suit to compel exoneration by the principal contractor.

The surety practitioner should be aware that the concept of quia timet is not always readily accepted by the courts. For example, in Morley Construction Co. v. Maryland Casualty Co., the Eighth Circuit originally ruled that the surety of an insolvent contractor was not entitled to exoneration because its bond liability had not matured. After reversal and remand by the Supreme Court, the Eighth Circuit then decided that the surety had made out a valid claim for quia timet relief. Although the record failed to disclose any indication that the contractor intended to voluntarily divert contract funds, the Morley court ruled in the latter opinion that the contractor’s insolvency provided the surety with a reasonable apprehension of diversion. Accordingly, the surety’s request for exoneration was granted.

Other cases which have granted quia timet relief to sureties in similar circumstances include National Surety Corp. v. Barth, (right of surety to have contract funds paid to payment bond claimants was held superior to right of contractor to such funds, and superior to right of United States to which contractor owed income taxes), Western Casualty and Surety Company v. Biggs  (court seized contract funds due to contractor who had failed to pay subcontractors at the bonded project), and Lambert v. Maryland Cas. Co. (surety of an insolvent contractor entitled to take action to ‘freeze’ contract funds for subsequent payment of bond claims).

In Western Casualty and Surety Company v. Biggs, the court set forth the following prerequisite elements for a quia timet suit to compel exoneration:

The plaintiff originally brought a suit in equity in the nature of a bill quia timet to enforce its equity of exoneration from appellant. It is well settled that a court of equity will, at the request of a surety, seize funds due its principal and apply them to the principal’s debts if the surety can show that: the debts are currently due, the principal is unable or refuses to pay them, and if they are not paid the surety will become liable. (Emphasis added.)

The remedy of quia timet is not unlimited, as shown by the case of Fireman’s Fund Insurance Co. v. S.E.K. Construction Co. This case involved a dispute between a surety and contractor’s assignee-bank to a progress payment owed on a bonded highway project. The contractor had admitted to the surety that it owed $140,000 in outstanding bills, many of which were past due, but maintained that it was not insolvent because credit arrangements had been made with its creditors. No claims had been made against bonds issued by the surety, and the contractor was not in default in its work at the bonded project. The court ruled that the surety should not have in court ruled that the surety should not have instructed the State Highway Department to withhold the progress payment which the contractor intended to endorse to the assignee-bank. The court’s reasoning for refusing the surety’s quia timet request was that the surety’s rights to exoneration and subrogation could not be asserted unless and until a default by the contractor occurred; only when the contractor was in default under the bonded contract, according to the court, would the surety prevail over the contractor and the contractor’s bank. The Morley Construction case was distinguished as follows:

The Morley case applied the identical rules we have heretofore set out, and reached the decision that a bill in the nature of quia timet permitted the surety’s exoneration, only because of facts which do not exist in the instant suit. First, the construction company was insolvent when the bill of complaint was filed. Second, the creditors were demanding payment on past due bills. Third, an agreement had been entered into between surety and principal whereby the former loaned the latter large sums of money to keep the company operational, in exchange for which the principal agreed to first apply the construction contract proceeds to bills for labor and materials furnished.

The S.E.K. Construction case illustrates the danger of a surety being overanxious in seeking to enforce its quia timet rights. Reading between the lines of the court’s opinion, the contractor was in serious financial difficult that, with more time, probably would have resulted in a default situation. For this purpose, the contractor’s failure in either performance of construction work or in payment of laborers and materialmen would have been sufficient for the surety to take protective action. While the S.E.K. Construction court case may be criticized for adopting an overly restrictive view of when a contractor is in default, the surety should definitely have waited to file suit until it had a better factual foundation upon which to seek quia timet relief.

Indeed, the courts generally adopt a broad view of when a contractor is in default at a bonded project. Default is a factual question, and its determination often requires careful review of the bonded contract. Also, the terms of the surety’s bond are read into the contract, and so there is a default under the contract whenever there is a default under the bond. As explained by the court in U.S. Fidelity and Guaranty Company v. A&A Machine Shop, Inc.:

There is authority for the principle that all contractual instruments between the prime contractor and the government be construed together in ascertaining the obligations which run thereunder. Thus, it has been held that government projects require payment of subcontractors, failure to pay constituting a failure to perform and a breach of the contract.

3. Procedural Considerations

In Martin v. National Surety Co., the United States Supreme Court granted quia timet relief, in the form of an injunction, to prevent the diversion of contract proceeds before paying valid claims of laborers and materialmen. The Court based its injunctive relief on two grounds. One, an assignment in the indemnity agreement with the surety, effective upon default by the contractor, to the extent needed to pay bond claimants. Two, under common law, the failure to pay laborers and materialmen was a sufficient default to require the contractor to turn over payments to the surety upon appropriate demand. The progress payments were turned into the court for the benefit of unpaid laborers and materialmen.

Other courts have followed Martin and required deposit of contract funds into court for distribution to laborers and materialmen, with the surplus (if any) distributed to the principal contractor, contractor’s assignee bank and others according to a priority formula established by the court. In many ways, these cases resemble interpleader suits in which the surety’s superior right to the contested fund is recognized by the court.

The problem with this procedure is that it is too cumbersome for an ongoing construction project. Dynamics of keeping laborers and material suppliers paid and the work going forward according to schedule do not permit the time-consuming deliberation often required by the judicial process. These authors suggest that a joint control trust account be established to which progress payments are deposited and, after verification by the surety, from which project bills are paid.

Court approval for establishment of a trust account will be needed unless the contractor will agree to share control of project receipts and payments with the surety. Even if the contractor will so agree, court approval must be obtained if the contractor is a debtor-in-possession in a pending chapter 11 bankruptcy proceeding. Precious time can slip away while court approval is being obtained. Accordingly, it is suggested that surety immediately place the bond obligee on written notice of its claim to unpaid contract proceeds upon learning of the default, and thereby freeze the funds until a trust account can be judicially approved.

The surety’s rights will be prejudiced if the notice to the bond obligee is not promptly sent. Such notice may be in the form of a simple letter which advises the obligee of the principal’s default under the bond, of the surety’s known bond obligations due to the default (e.g., known debts owed to laborers or material suppliers at the project), and of the surety’s equitable right of subrogation to the unpaid contract proceeds. The letter should conclude with a demand that no contract funds be paid to any party, in the absence of the surety’s approval, until a court order is obtained. This letter should preserve the status quo until a court can determine the priority rights of the various parties to the unpaid contract funds.

Included in Appendix A to this article is a form trust account agreement, which is adapted from an actual agreement approved by the Bankruptcy Court for completion of a project by a debtor-in-possession contractor. When this trust agreement was executed, the contractor was behind in payments to project creditors, but the surety had not yet paid any claims and the extent of its bond obligations were not known. Court approval was obtained for the trust agreement on the basis of the surety’s reasonable fear of bond losses, under the doctrine of quia timet, unless project funds were strictly applied to project expenses incurred by the debtor in the course of its bonded contract. Hopefully, it will be a useful form for other situations that may be encountered when a trust agreement is needed, particularly when the bonded project is being completed by a chapter 11 debtor-in-possession.

B. Requiring Collateral to Cover Anticipated Bond Losses

1. Surety’s Right to Have Collateral Posted by Indemnitors

All too often, the remaining contract proceeds at a project are insufficient for the surety to complete performance and pay the bills of the bonded contractor. Due to practices of underbidding, frontloading, using project funds for unrelated purposes, and a myriad of other reasons, the surety may be faced with tremendous losses unless its indemnitors will provide funding from their personal assets.

Theoretically, the surety should never incur any loss, as its principal and indemnitors are fully liable to the surety for the amount of damages and expenses which may be suffered in connection with issued bonds. The written indemnity agreement, underlying issuance of bonds, typically provides that the principal (contractor) and indemnitors (individuals or companies, including the principal, who have agreed to be responsible for obligations owed to the surety) shall ‘indemnify and keep indemnified, and hold and save harmless the surety against all demands, claims, loss, costs, damages, expenses and attorneys’ fees whatever, and any and all liability therefore sustained or incurred by the surety by reason of executing or procuring the execution or procuring the execution of any bonds.’ Although the terminology changes in indemnity agreements of different sureties, the purpose of all such agreements is to include every conceivable type of damage and expense within the scope of the indemnity obligation to the surety.

The written indemnity agreement also typically provides that the surety may take action against its indemnitors in anticipation of losses. The following type of provision is probably the most common within the industry:

That if Surety shall be required or shall deem it necessary to set up a reserve in any amount to cover any claim, demand, liability, expense, suit, order, judgment or adjudication under or on any Bond or Bonds or for any other reason whatsoever, the principal and indemnitors shall immediately upon demand deposit with Surety an amount of money sufficient to cover such reserve and any increase thereof, such funds to be held by Surety as collateral, in addition to the indemnity afforded by this instrument, with the right to use such funds or any part thereof, at any time, in payment or compromise of any liability, claims, demands, judgment, damages, fees and disbursements or other expenses.

Note that the surety’s right to have collateral posted in the above provision is conditioned upon the establishment of a liability reserve. Although this is not normally a problem, there may be fast-breaking situations in which the surety requires collateral from indemnitors in advance of establishment of the liability reserve. The following provision (loss frequently found in form indemnity agreements) is more flexible:

In order to exonerate or indemnify Surety, the principal and indemnitors shall upon demand of Surety, place Surety in funds before Surety makes any payment; such funds shall be, at Surety’s option, money or property, or liens or security interests in property. (The amount of such money or property, or the value of the property to become subject to liens or security interests, shall be determined by Surety.)

Obviously, the amount of surety’s demand to be placed in funds (i.e., to be collateralized) under this provision must be reasonably related to the amount of anticipated losses. As this provision is less restrictive upon the surety than the former provision quoted above, it is preferred for a surety’s form indemnity agreement.

2. Requirements for Quia Timet Relief to Obtain Collateral

The contractual right of the surety to be placed in funds or collateralized by its indemnitors is independent of, and in addition to, the common law. Under the doctrine of quia timet, such common law right may be exercised, before the bond obligations become due, under appropriate circumstances of anticipated loss. The following quotation from Corpus Juris Secundum is illustrative of the common law:

In equity and under some statutes, after the maturity of the debt or accrual of liability, a surety who has not paid the debt, even though he has not been troubled by the creditor, has a right to compel the principal to exonerate him from liability, to pay the debt, or to secure him against loss.

Doster v. Continental Casualty Company, involved a contractor, Doster, who declared to his surety, Continental, upon completion of a school construction project that he was unable to pay approximately $24,000 owed for materials used at the project. Doster had $21,000 on hand, the bulk of which consisted of progress payments received from the school, but refused to pay the material suppliers whose accounts were past due. The surety brought a quia timet suit, and prayed that the court order Doster to use all available funds to pay project bills and, if such funds were not sufficient, then that Doster “be required to protect and secure and indemnify Continental by a transfer of all his assets not subject to exemption over to Continenta1.” The trial court granted surety a temporary injunction consistent with its prayer for relief: which injunction was later made permanent.

Although Doster had signed a written indemnity agreement which included a provision for transferring assets to the surety as collateral, the court’s affirmance of the trial court’s injunctive relief was decided on common-law principles. In particular, the court rejected the argument that fraudulent disposition of property, or any other special reason for fearing a loss, had to be shown before a surety could invoke its quia timet rights. The following essential elements were set forth in the Doster opinion for requiring a contractor to transfer assets as collateral to the surety:

The requirements of our cases for a bill of exoneration are more than met in the bill in the instant case in that:

  1. The relationship of surety and principal is alleged.

  2. It is averred that the respondent had, in substance, declared himself in default under his bond by reason of his inability and failure to make payment of the bills of materialmen who had furnished material and supplies for the construction of the North Roebuck School on which the complainant was the contractor’s surety.

  3. It is averred that numerous of the materialmen who had furnished the project had made demand upon the complainant, Continental Casualty Company as surety, for payment under the terms of the performance and labor and material payment bond which the surety had executed on the respondent as principal pursuant to the provisions of § 16 of Title 50 of the Code of Alabama of 1940.

  4. Averments are made concerning the financial status of the respondent, including his possession and control of substantial funds collected as earnings off of the construction of the job bonded by the complainant, and the refusal of the respondent to use same for the payment of the material bills incurred on the project.

  5. The Complainant in the bill offers to do equity and avers that it makes no effort to avoid its secondary liability to the materialmen for the reasonable value of materials and labor furnished for the construction of the North Roebuck School, for which the materialmen would be entitled to recover from the complainant as surety pursuant to the aforesaid public works statute, and further avers that equity, good conscience and simple honesty dictate and require that the respondent be made to fulfill his obligations to the extent that he is reasonably able, and that the complainant, as his surety, be permitted exoneration to the extent that the materialmen and obligee under the bond for the construction of the North Roebuck School will not be prejudiced on any valid and legitimate claims possessed by them.

In theory, the surety should be able to obtain an injunctive lien upon assets whenever it can meet the five essential elements of common law cited in the above passage. However, judges are sometimes reluctant to grant such drastic relief based upon strict application of common law principles. Most judges prefer to couch their decision in the form of specific performance of the written indemnity agreement. For example, in United Bonding Insurance Company v. Stein, the operative provision of the indemnity agreement for collateralization was conditioned upon the surety’s establishment of a liability reserve. The indemnitors refused to comply with surety’s demand for funds equal to its established reserve, and so the surety brought suit to compel security. The court denied the indemnitors’ motion to dismiss in the following passage:

When stripped to its essentials, this action is simply one for the specific performance of a contractual agreement. Unlike the situations with which the cases cited by defendant petitioners were involved, the instant controversy concerns defendants’ promise to place funds in reserve, should the plaintiff deem such precaution necessary. Hence consideration of instances of contracts to indemnify against actual loss is not relevant. ...

In the instant case the only conditions precedent to defendants’ obligation were the plaintiffs estimate that a reserve was necessary and its demand upon defendants for current funds in the amount of such reserve. Once these conditions are fulfilled equity will specifically enforce such a promise where, as in the instant case, a legal remedy for subsequent damages would not suffice, ...

Also in the Ninth Circuit case of Milwaukie Construction Co. v. Glens Falls Insurance Co., the court specifically enforced the provision in an indemnity agreement requiring indemnitors to post adequate security upon establishment of a liability reserve. The argument that such relief could not be given until after payment of bond claims was rejected, on the basis of the surety’s quia timet right to compel exoneration and obtain security against loss upon accrual of the bond liabilities.

An essential element for specific performance of any contract is inadequacy of remedy at law. In the Stein case, the court stated, without discussion of this issue, that a legal remedy for subsequent damages would not suffice when an indemnitor refuses to voluntarily comply with a surety’s demand for collateral. The Milwaukie Construction court also seemed inclined to rule that inadequacy of remedy could be presumed in these circumstances; there was evidence that one of the indemnitors in the Milwaukie Construction case had transferred assets out of the country to avoid creditors, which additionally supported the court’s finding of an inadequate remedy of law. Also in the Doster case discussed above, the court ruled that a showing of fraudulent disposition of property was not a prerequisite to quia timet relief against the indemnitors.

These authors believe that inadequacy of remedy should be presumed upon the indemnitors’ failure to voluntarily post collateral. When the issuance of bonds was first contemplated by the principal and surety, the indemnitors had promised to provide collateral to the surety under appropriately described circumstances in the indemnity agreement. If such promise cannot be enforced when later needed in an equitable action for specific performance, but rather must await determination in a legal action for damages, then the promise to collateralize is meaningless. After all, in another provision of the agreement, the indemnitors have already agreed to fully repay surety for all of its losses and expenses. Unless the surety has recourse to obtain collateral while the lawsuit for damages is pending, then the promise to collateralize adds nothing to the surety’s rights under the agreement.

Nevertheless, the cautious surety practitioner should attempt to learn all facts which will bolster its position that there is not an adequate legal remedy to protect the surety. This is particularly important when the collateral is first pursued in a lawsuit with a request for temporary restraining order or preliminary injunction against the indemnitors. Certainly any evidence of asset transfers, such as in the Milwaukie Construction case, will be most helpful in obtaining the desired relief from the court.

Also, the surety practitioner should be sure that the conditions precedent set forth in the indemnity agreement have been strictly complied with. In Maryland Casualty Co. v. Straubinger, the appellate court reversed the trial court’s award of specific performance under the indemnity agreement. The reason for the reversal was that the indemnity agreement stated that funds had to be immediately deposited by the indemnitors upon the surety setting up a reserve ‘required by the State Insurance Department.’ The appellate court strictly interpreted this provision; as there was no proof that the State had actually required establishment of the liability reserve in that case, the court held that the condition precedent had not been met.

3. Procedural Considerations

Probably even more so than when trying to prevent dissipation of contract funds, there is a great need for the surety to take prompt action when seeking collateralization from indemnitors. Injunctive relief to prevent transfers of assets is required. However, to have any real benefit to the surety, the injunction must be entered at the commencement of the lawsuit against the indemnitors, and must be in effect during the pendency of the litigation. Otherwise, the assets may be gone by the time that the surety can have final judgment entered against the indemnitors.

The case of Doster v. Continental Casualty Company is the strongest authority for the opposition that the surety must have a preliminary injunctive relief to protect his rights. It is suggested this case be closely studied and followed when seeking a preliminary injunction on behalf of a surety against its indemnitors.

Included in Appendix B to this article is a set of pleadings which were used in a case to obtain a temporary restraining order, without notice, from a federal district court. The order specifically provided the surety with a lien upon all assets of indemnitors and prohibited the indemnitors from transferring assets during the pendency of the order. Diversity jurisdiction was invoked to enable the district court to hear the case. The surety preferred to have an order from the federal court, rather than from the state court, because there was the possibility that out-of-state assets were owned by the indemnitors. Enforcement of injunctions, particularly affecting disposition of real property, is more easily accomplished across state lines with orders of the federal court.

Rule 65 of the Federal Rules of Civil Procedure governs issuance of temporary restraining orders by federal district courts. It provides that a temporary restraining order may only be entered if it clearly appears from specific facts shown by affidavit or by verified complaint that immediate and irreparable injury will result before the adverse party can be heard in opposition, and that the applicant’s attorney must certify in writing the reasons why notice to the adverse party should not be required. The order only remains in effect for ten days, unless extended by agreement of the parties or for good cause shown for an additional ten days. The hearing on applicant’s motion for preliminary injunction, after notice to the adverse party, must be scheduled at the earliest possible time and take precedence over other matters before the court. Finally the temporary restraining order must be supported by an injunction bond, in an amount to be determined by the court.

The pleadings included in Appendix B are a complaint for injunctive and other relief, and an application for temporary restraining order. In that case, a hearing on preliminary injunction was held four days after service of the temporary restraining order upon the indemnitors. The court sustained surety’s request for quia timet relief, and a preliminary injunction was entered for the pendency of the litigation.

Obviously, these form pleadings must be adapted to the particular facts of the situation in which they are used. In particular, if the indemnitors are known to have transferred assets or done other things which give the surety special reason to be fearful, these facts should be specified in the pleadings. Even without such special reasons for being apprehensive (as in the case in which the pleadings were actually used) the surety should be able to enforce its quia timet rights with a temporary restraining order, followed shortly thereafter with a preliminary injunction entered after notice and opportunity for hearing to the indemnitors.

4. Procedural Due Process Rights of Indemnitors

The indemnitors may argue that preliminary injunctive relief, and particularly a temporary restraining order issued without notice, violates their procedural due process rights. However, a review of the leading cases on this issue shows that due process rights are not being infringed.

The first United States Supreme Court case on the subject of procedural due process, in a series of cases from 1969 to 1975, was Sniadacb v. Family Finance Corp. In that case, the Court ruled that due process required that garnishment of wages be preceded by notice and opportunity for hearing. Crucial to the Court’s holding was the unique importance of wages to the debtor and the severe deprivation which would be caused by a wrongful garnishment.

The second case was Fuentes v. Sbevin, in which it was held that a state replevin statute was unconstitutional. In extremely broad terms, the Court’s opinion stated that, except in extraordinary circumstances, deprivation of property had to be preceded by notice and an opportunity for hearing in which the debtor could dispute the creditor’s claims. Justice White, in a dissenting opinion, urged a balancing test which weighed the debtor’s due process interest against that of the creditor’s property interest.

Justice White wrote the majority opinion in the third case in the series. In Mitchell v. W. T. Grant Co., the balancing approach was used to uphold a Louisiana sequestration statute which failed to provide for prior notice and hearing for the debtor. Significant to the balancing process were the measures adopted by the state to minimize the risk of a wrongful taking of property. In particular, the statute required the creditor to file an affidavit consisting of specific facts supporting the writ of execution, and declared that only a judge could issue the writ. The importance of judicial control was stressed in the following quotation from the majority opinion:

The Louisiana sequestration statute followed in this case mandates a considerably different procedure. A writ of sequestration is available to a mortgage or lien holder to forestall waste or alienation of the property, but, different from the Florida and Pennsylvania systems, bare, conclusory claims of ownership or lien will not suffice under the Louisiana statute. Article 3501 authorizes the writ ‘only when the nature of the claim and the amount thereof, if any, and the grounds relied upon for the issuance of the writ clearly appear from specific facts’ shown by verified petition or affidavit. Moreover, in the parish where this case arose, the requisite showing must be made to a judge, and judicial authorization obtained. Mitchell was not at the unsupervised mercy of the creditor and court functionaries. The Louisiana law provides for judicial control of the process from beginning to end.

The fourth Supreme Court case in the series was North Georgia Finishing, Inc. v. Di-Chem, Inc. By relying largely on Fuentes to invalidate a Georgia prejudgment garnishment statute it added to, rather than clarified, the confusion arising from the three earlier cases. It is significant that the Georgia statute did not provide the protective measures, particularly judicial participation, which were so important to the balancing process used in the Mitchell case.

Later due process cases of the Supreme Court have employed the balancing test suggested by Justice White in his dissenting opinion to Fuentes and his majority opinion in Mitchell. Lower court cases have also generally followed the balancing approach, giving special consideration to review by a judicial officer and opportunity for early hearing.

If warranted by the circumstances, the surety should seek a temporary restraining order against the indemnitors to enjoin transfer of assets. Although there are no cases directly addressing the question of whether such order will violate the indemnitors’ due process rights, the balancing approach of Mitchell and other above cited cases should uphold the order. As in Mitchell, there are measures in effect to minimize the risk of a wrongful taking of property. The surety’s affidavits and pleadings supporting the temporary restraining order, as required by the Rules of Civil Procedure, must specifically set forth the reasons for the order, and a requisite showing for relief must be approved by a judicial officer. Clearly, the surety has a valid property interest in obtaining collateral, as promised by the indemnitors, upon reasonable apprehension of liability; this property interest may be irreparably prejudiced unless relief is immediately granted. On the other side of the balancing process, the indemnitors will only be deprived of their right to transfer assets for the few days that pass until the indemnitors can be given notice and an opportunity for hearing. Further, an injunction bond protects the indemnitors from damage for the short time that the injunctive order is in effect without notice. Under these circumstances, it appears that the balancing process employed by the Mitchell court would uphold the procedure for the surety to obtain a temporary restraining order under appropriate circumstances discussed above.

IV. CONCLUSION

Quia timet is an extremely useful remedy for the surety. The mere threat of resort to quia timet remedies may result in the requested, but previously declined, cooperation of the principal and indemnitors.

It is, however, a drastic remedy that must be used sparingly in circumstances of justified apprehension of losses. Overzealous use of this remedy in situations where injury is not reasonably anticipated or prior to default of the principal, as in the S.E.K. Construction case, may result in the court’s rejection of the doctrine of quia timet entirely.

Of course, the principal and indemnitors are not without remedy themselves. Bankruptcy, either in the form of a straight liquidation (chapter 7) or a reorganization (chapter 11) is always available to them. If they choose to file a voluntary bankruptcy petition within 90 days following a judicial order giving surety an involuntary lien upon assets, then the lien is subject to avoidance as a preferential transfer under bankruptcy law. Furthermore, other creditors of the principal or indemnitors, with claims exceeding $5,000, may choose to file an involuntary bankruptcy petition, the effect of which will also be to make a voluntary or involuntary lien in favor of the surety, within the preceding 90 days, subject to voidance under bankruptcy law. The surety will then only have the status of an unsecured creditor in the bankruptcy proceeding.

Thus, the ultimate effect of a quia timet suit may be to force the principal and indemnitors into bankruptcy. However, even in a bankruptcy situation, the surety is entitled to have contract proceeds applied to bonded contract obligations. Furthermore, the bankruptcy proceeding will place the assets of the principal and indemnitors under the auspices of the bankruptcy court, which should accomplish the intended result--the prevention of fraudulent diversion of assets from the surety.

Whenever the construction surety is faced with potential bond losses and a recalcitrant principal contractor or indemnitor, the remedy of quia timet should be considered. It is not suitable for all situations, and the surety practitioner must determine, on a case-by-case basis, whether quia timet may properly be invoked and whether it will really be beneficial to the surety. However, under appropriate circumstances of default and reasonable apprehension of liability, quia timet may be the only practical means by which the surety may preserve funds or other assets for subsequent discharge of bond obligations or reimbursement to the surety. In other words, prompt use of available quia timet procedures may be the difference between losses and avoidance of losses to the construction surety. u


APPENDIX A: TRUST AGREEMENT

THIS AGREEMENT made and entered into this _____ day of ,_______, ___, by and between INSOLVENT CONSTRUCTION COMPANY, an Arizona corporation (hereinafter referred to as ‘Principal’), and JOHN

OWNER and MARY OWNER, husband and wife (hereinafter said individuals are collectively referred to as the ‘Indemnitors’), and FEARFUL INSURANCE COMPANY, a Maryland corporation (hereinafter referred to as ‘Surety’).

WITNESSETH: WHEREAS, Surety has heretofore executed bonds from time to time on behalf of Principal at the request of Principal and Indemnitors on certain projects, including the following: __________________ (hereinafter referred to as the ‘Bonded Project’).

WHEREAS, Principal and Indemnitors, to induce Surety to execute the aforesaid bonds on their behalf, agreed to indemnify and save Surety harmless from any claim, loss, cost, or expense by reason of executing said bonds;

WHEREAS, on __________, ___, Principal and Indemnitors executed a General Indemnity Agreement in favor of Surety wherein and whereunder Principal and Indemnitors, jointly and severally, agreed to indemnify Surety against any loss or liability it might incur as a consequence of executing surety bonds on behalf of Principal;

WHEREAS, on __________, ___, Principal filed a voluntary petition under Chapter 11 in the United States Bankruptcy Court for the District of (In re Insolvent Construction Company, Cause No. ). Principal remains in possession of its property and continues to operate its business as a debtor in possession;

WHEREAS, Principal is unable to meet obligations for both performance and payment covered under the above described bonds for the Bonded Project; and

WHEREAS, Principal, Indemnitors and Surety agree that the execution of this Agreement and the performance of its terms, provisions and conditions will be to the mutual benefit of Principal, Indemnitors, Surety and the general creditors of Principal, and in furtherance of the performance and completion of the work at the above described Bonded Project.

NOW, THEREFORE, in consideration of the mutual promises and covenants hereinafter contained, the parties hereto agree as follows:

1. Principal and Indemnitors, and each of them, do hereby reaffirm their General Indemnity Agreement, dated _______________, 20___, in favor of Surety notwithstanding anything contained herein.

2. Surety shall have a first right of priority, superior to all other claims to the unpaid balance of the contract proceeds (including unpaid draws and retention sums) of the bonded contract, to the extent necessary to reimburse Surety for any and all losses, costs, expenses, including attorneys’ fees, and interest on any advances that may be made by Surety at the rate of ten percent (10%) per annum, which it has incurred or any hereafter incur as a result of the execution of the above-described bonds for the Bonded Project.

3. There shall be a bank account established at the Bank. The account shall be known as the ‘Insolvent Construction Company Trust Account’ (hereinafter referred to as ‘Trust Account’).

A.  With regard to the Trust Account:

(1) The Trust Account shall be a general operations account for the Bonded Project.

(2)  The following monies, receipts or payments shall be deposited in said account: (a) all monies, presently in the possession of Principal, representing proceeds or payments received by Principal from the bonded contract; (b) all monies which may be received, after execution of this Agreement, representing proceeds or payments from the bonded contract; and (c) funds that may be advanced by Surety to pay expenses described in subparagraph (3) below.

(3)  The Trust Account shall be used for the following purposes, for which uses and purposes a trust is hereby imposed upon said account: (a) to pay all necessary labor, materials, supplies, equipment, contracts and expenses for the continued performance of the bonded contract, for which Surety would be liable under its abovedescribed bonds for the Bonded Project; and (b) to reimburse Surety to the extent of reimbursement described in paragraph 2 above.

(4)  Withdrawals to be made from the Trust Account shall be only by checks signed either (a) by any two designated representatives of Surety, or (b) by anyone designated representative of Surety and by anyone designated representative of Principal. The designated representative of Surety and Principal are set forth in paragraph (B) below.

(5)  Nothing contained in this paragraph 3 shall obligate Surety to provide funding to Principal. Should the above-described Trust Account be depleted and funding be needed Principal in connection with performance of the bonded contract, the decision to provide or not provide funding shall be at the sole discretion of Surety.

B.  The designed representatives of Surety and Principal, for purposes of withdrawals from the Trust Account, are as follows:

(1) For Surety: _______________ Surety shall have the right at any time to name substitutions in place and instead of these individuals.

(2) For Principal: _______________ Principal shall have the right at any time to name substitutions in place and instead of these individuals.

C.  It is understood that the Trust Account shall remain the property of Surety at all times to the extent necessary for reimbursement described in paragraph 2 above. Surety may, at any time and without prior notice or consent of Principal or Indemnitors, withdraw all or any part of the balance of the Trust Account for the purpose and to the extent of said reimbursement.

D.  Principal shall render periodic accountings, as requested by Surety, of all deposits into and withdrawals from the Trust Account, together with such payroll reports, invoices, billings and other supporting documents requested by Surety.

4.  Principal shall execute an irrevocable Direction of Payment to __, owner of the Bonded Project. Such Direction of Payment shall require the owner to make all payments of the unpaid balance of the bonded contract proceeds (including unpaid draws and retention sums) by checks payable to the order of the ‘Insolvent Construction Company Trust Account,’ and shall further require delivery of such checks to __, counsel for Surety. Upon receipt, counsel for Surety shall promptly deposit each check into the Trust Account.

5. It is agreed that funds in the Trust Account shall be used to reimburse Surety as follows:

First, to the payment of any advances that may be made directly by Surety, with regard to the bonded contract, to bond claimants or deposited into the Trust Account or otherwise. Second, to the payment of all other costs, expenses and attorneys’ fees incurred by Surety as a result of execution of bonds on behalf of Principal for the Bonded Project.

6. Surety shall have the right, through its own employees or by outside auditors, to audit and inspect the books of Principal at such reasonable time or times as it may desire.

7. Principal and Indemnitors agree that Surety may at any time, in its sole discretion and with or without cause or notice, terminate this Agreement; provided, however, such termination shall not in any way lessen Surety’s obligations under the above-described bonds for the project. Principal and Indemnitors agree and fully understand, and have had the advice of counsel, that this provision is for the protection of Surety.

8. Principal agrees to do all things necessary to affirm the bonded contract as soon as such affirmation can reasonably be accomplished.

9. The rights afforded Surety under this Agreement are in addition to any and all other rights which Surety has, may have or acquire against Principal and Indemnitors, whether under the terms of any indemnity agreements or otherwise. This Agreement shall not be deemed to modify or alter any existing indemnity or other agreement. In particular, Surety specifically reserves its right to demand collateral and to be placed in funds by Indemnitors, and further to take over or relet the bonded contract, and further to seek the appointment of a trustee or examiner in the above-described Chapter 11 proceeding.

10. Nothing contained in this Agreement or done pursuant thereto shall be construed to enlarge any obligation of Surety under any bond or undertaking executed on behalf of Principal and it is further agreed that this Agreement is solely for the benefit of the parties hereto and shall not create any rights in or for any other persons, firms, or corporations.

11. Any waiver by Surety of any provisions of this Agreement or any failure on the part of Surety to act or take advantage of its provisions shall not in any way limit, vary, or discharge Principal or Indemnitors under this or any other agreement.

12. Principal and Indemnitors agree to reimburse Surety for any and all reasonable expenses, including any attorneys’ fees which it may have, or may hereafter incur as a result of the execution of the above-described bonds or under the terms of this Agreement.

13. Principal and Indemnitors hereby agree to all of the terms of this Agreement, and to comply therewith and to execute any and all instruments deemed by Surety as necessary or proper to effectuate this Agreement.

14. Time is of the essence of this Agreement.

15. This Agreement shall extend to and be binding upon and inure to the benefit of the parties and their respective successors, heirs and assigns.

16.  This Agreement is expressly conditioned upon formal approval which approval Principal shall seek to obtain promptly upon execution of this Agreement.

17. To the extent that Surety is fully reimbursed for any and all losses, costs, expenses and attorneys’ fees, then remaining proceeds received from the Bonded Project and any remaining balances in the Trust Account described in paragraph 3 above shall be promptly paid to Principal.

IN WITNESS WHEREOF, this Agreement has been duly executed by the parties hereto on the day and year first hereinabove written.


APPENDIX B

UNITED STATES DISTRICT COURT DISTRICT OF ARIZONA

TABULAR OR GRAPHIC MATERIAL SET FORTH AT THIS POINT IS NOT DISPLAYABLE

For its complaint against defendants, plaintiff alleges as follows:

Count One

I

Plaintiff is a corporation incorporated under the laws of the State of Maryland and has its principal place of business in the State of Maryland. Defendant Insolvent Construction Company (‘Insolvent’) is a corporation incorporated under the laws of the State of Arizona. Defendants John Owner and Mary Owner, husband and wife, are citizens of the State of Arizona. The matter in controversy exceeds, exclusive of interest and costs, the sum of Ten Thousand Dollars ($10,000.00). Accordingly, this Court has diversity jurisdiction over this action pursuant to 28 U.S.C. § 1332.

II

On or about ______________, ________, Insolvent (as principal) and defendants John Owner and Mary Owner (as indemnitors) executed a General Indemnity Agreement with plaintiff. By the terms of such General Indemnity Agreement, defendants agreed, among other things, to exonerate, indemnify and keep indemnified the surety plaintiff from and against any and all liabilities, losses and expenses of whatsoever kind or nature (including but not limited to, interest, court costs and counsel fees) imposed upon, sustained, or incurred by surety plaintiff by reason of: (1) surety plaintiff having executed bonds in behalf of principal Insolvent, or (2) defendants’ failure to perform or comply with any of the provisions of the General Indemnity Agreement. Further by the terms of the General Indemnity Agreement, defendants agreed that in order to exonerate or indemnify surety plaintiff, defendants shall upon demand of surety plaintiff, place surety plaintiff in funds before surety plaintiff makes any payment; such funds to be, at the surety plaintiffs option, money or property, or liens or security interests in property, the amount of such money or property or the value of the property to become subject to liens or security interests as determined by the surety plaintiff. A copy of the said General Indemnity Agreement is attached hereto as Exhibit ‘A’ and incorporated by reference herein.

III

At the request of defendants and pursuant to the terms of the said General Indemnity Agreement, plaintiff, as surety, and Insolvent, as principal, executed payment and performance bonds, in connection with construction projects in which Insolvent had agreed to be the general contractor thereon. There are presently outstanding ___ such payment and performance bonds issued by plaintiff for Insolvent, in the total sum of $ ______.

IV

Defendant Insolvent does not have the financial resources to pay its obligations on the bonded construction projects and is therefore in default to its material suppliers and subcontractors at such projects. Further with regard to Insolvent’s uncompleted construction contracts, defendant Insolvent does not have the resources to finance completion of same.

V

Plaintiff justifiably fears that it will sustain a loss in the completion of the bonded projects. Further, plaintiff justifiably fears that it will be required to pay claims of unpaid material suppliers and subcontractors at the bonded projects. To date, plaintiff has paid, pursuant to its bond obligations, the sum of $ to unpaid material suppliers and subcontractors of Insolvent. However, based upon a review of Insolvent’s books and records, and further based upon numerous notices of claims received from material suppliers and subcontractors, it is estimated that the losses to plaintiff in connection with the bonds issued for Insolvent will actually exceed $____________.

VI

In accordance with the General Indemnity Agreement, plaintiff made demand upon defendants to be placed in funds prior to making any payment, such funds to be money, property, or liens or security interests in property as determined by plaintiff. By virtue of the said General Indemnity Agreement and by virtue of the equitable doctrines of exoneration and quia timet, plaintiff is entitled to have defendants place funds or other security with plaintiff that is sufficient to cover the above-described bond losses.

VII

Defendants have failed and refused to meet their obligations under the General Indemnity Agreement. In particular, defendants have refused to place plaintiff in funds, both in the amount and according to the procedure set forth in the Agreement.

VIII

Upon information and belief, the assets of the defendant Insolvent are insufficient to adequately secure plaintiff for its obligations under the above-described payment and performance bonds. Unless the personal assets of the individual defendants, as well as the corporate assets of Insolvent, are collateralized, plaintiff will not be adequately secured for its obligations on the bonded projects.

IX

Plaintiff is entitled to be fully collateralized by defendants prior to making any further payments in discharge of its bond obligations. Unless the injunctive relief requested below is granted, plaintiff will not be adequately secured for its obligations prior to making such further payments. Further unless the injunctive relief requested below is granted, defendants are likely to sell, transfer, dispose, lien, secure, or otherwise divert their assets from being used to discharge defendants’ obligations to exonerate and indemnify plaintiff, all to plaintiffs irreparable harm.

X

Plaintiff is without a plain, speedy or adequate remedy at law, and will be irreparably and permanently injured unless this Court grants the injunctive and equitable relief as prayed herein.

XI

Plaintiff has been forced to retain legal counsel and incur other expenses in pursuit of its rightful interests in this matter, and is entitled to recompense therefore, pursuant to the terms of the General Indemnity Agreement.

WHEREFORE, plaintiff demands judgment against defendants, jointly and severally, as follows:

A.  For an order requiring defendants to render to plaintiff a full and complete accounting of all assets owned by them or in which they have an interest.

B.  For an order requiring defendants to allow plaintiff full and complete access to all financial books, records and accounts maintained by them.

C.  For an order requiring defendants to place plaintiff in funds by money, property, or liens or security interests in property, as determined by plaintiff to be ample security for its obligations on the bonded projects.

D.  For an order permanently enjoining and restraining defendants from selling, transferring or disposing or liening their assets and property, and further enjoining and retraining defendants from allowing their assets and property to be liened, unless and until plaintiff shall be placed in funds as prayed for in paragraph (C) above.

E.  For an order granting a lien upon all assets and property, including realty, personally and mixed, owned by defendants and property in which defendants have an interest. Such lien shall secure plaintiff against any loss that it may sustain or incur by virtue of its having executed bonds for Insolvent. Such lien shall remain in effect unless and until plaintiff shall be placed in funds as prayed for in paragraph (C) above.

F.  For an order requiring defendants to indemnify and exonerate plaintiff for all liabilities, losses and expenses incurred by plaintiff as a result of plaintiff having executed bonds for Insolvent.

G.  For plaintiff’s costs, including reasonable attorneys’ fees, incurred herein.

H.  For such other and further relief as this Court deems just and equitable.

Count Two

XII

By this reference, plaintiff incorporates the allegations contained in paragraphs I through XI, inclusive, of the complaint.

XIII

By the express provisions of the General Indemnity Agreement and by virtue of the equitable doctrines of exoneration and quia timet, plaintiff is entitled to be placed in funds, upon demand, prior to making further payments upon its bonds issued for Insolvent. Unless preliminary injunctive relief is granted, plaintiff will not be adequately secured for its obligations prior to making further payment thereon. Further unless the preliminary injunctive relief is granted, defendants are likely to sell, transfer, dispose, lien, secrete, or otherwise divert their assets from being used to discharge defendants’ obligations to exonerate and indemnify plaintiff, all to plaintiffs irreparable harm.

WHEREFORE, plaintiff prays that the Court grant the following preliminary relief:

A.  Issue its order to defendants to show cause at the earliest possible date why the relief demanded herein should not be granted.

B.  Schedule a hearing at which evidence will be taken.

C.  Thereafter issue a Preliminary Injunction which includes the following:

(1)  Requires defendants to render to plaintiff a full and complete accounting of all assets owned by them or in which they have an interest.

(2)  Requires defendants to allow plaintiff full and complete access to all financial books, records and accounts maintained by them.

(3)  Requires defendants to place plaintiff in funds by money, property, or liens or security interests in property, as determined by plaintiff to be ample security for its obligations on the bonded projects.

(4)  Permanently enjoins and restrains defendants from selling, transferring or disposing or liening their assets and property, and further enjoins and restrains defendants from allowing their assets and property to be liened, unless and until plaintiff shall be placed in funds as prayed for in paragraph (3) above.

(5)  Grants a lien upon all assets and property, including realty, personally and mixed, owned by defendants and property in which defendants have an interest. Such lien shall secure plaintiff against any loss that it may sustain or incur by virtue of its having executed bonds for Insolvent. Such lien shall remain in effect unless and until plaintiff shall be placed in funds as prayed for in paragraph (3) above.

(6)  Requires defendants to indemnify and exonerate plaintiff for all liabilities, losses and expenses incurred by plaintiff as a result of plaintiff having executed bonds for Insolvent.

D.  For plaintiffs costs, including reasonable attorneys’ fees incurred herein.

E.  For such other and further relief as this Court deems just and equitable.

 


APPENDIX C

UNITED STATES DISTRICT COURT DISTRICT OF ARIZONA

TABULAR OR GRAPHIC MATERIAL SET FORTH AT THIS POINT IS NOT DISPLAYABLE

Plaintiff hereby applies to this Court for a Temporary Restraining Order, and in support thereof alleges as follows:

I

By this reference, plaintiff hereby incorporates the allegations contained in its Complaint for Injunctive and Other relief filed concurrently herewith.

II

To date, plaintiff had advanced, pursuant to its bond obligations, the sum of $ to unpaid material suppliers and subcontractors of Insolvent Construction Company (‘Insolvent’). Based upon a review of Insolvent’s books and records, and further based upon numerous notices of claims received from material suppliers and subcontractors, plaintiff justifiably fears that further substantial advances will be required and, accordingly, estimates its losses, upon bonds issued for Insolvent, in the sum of $

III

By virtue of the General Indemnity Agreement executed by plaintiff and defendants on or about ___________, ______, a copy of which was attached to the complaint as Exhibit ‘A,’ and by virtue of the equitable doctrines of exoneration and quia timet, plaintiff is entitled to be fully collateralized by defendants prior to making further payments upon its bonds issued for Insolvent.

IV

Unless restrained and enjoined therefrom, defendants are likely to sell, transfer, dispose, lien, secrete or otherwise divert their assets from being used to discharge defendants’ obligations to exonerate and indemnify plaintiff, all to plaintiffs irreparable harm.

V

Should notice of the pending issuance hereof be given to defendants, there exists a strong likelihood that they will commit one or more of the above acts before this order could be entered and served upon them, and immediate and irreparable loss, damage and harm would thereby result to plaintiff.

WHEREFORE, plaintiff requests that this Court issue an ex parte temporary restraining order which includes the following:

A.  Enjoins and restrains defendants from selling, transferring, disposing or liening their assets and property and further enjoins and restrains defendants from allowing their assets and property to be liened during the pendency of this order;

B.  Grants a lien in favor of plaintiff upon all assets and property of defendants, including realty, personally and mixed, owned by defendants and property in which defendants have an interest. Such lien shall secure plaintiff against any loss that it may sustain or incur by virtue of its having executed bonds for Insolvent. Such lien shall remain in effect during the pendency of this order; and

C.  Requires defendants to appear within 10 days and show cause why said temporary restraining order should not remain in effect as a preliminary injunction pending disposition of this lawsuit.

Respectfully submitted this ____ day of ___________, 19 ____.

Attorneys  |  Practice Areas  |  Jurisdictions  |  Articles  |  Disclaimer  |  Contact Us  |  Home  |  Sitemap

© 2005-2011. Mann, Berens & Wisner, LLP

3300 N. Central Ave., Suite 2400 | Phoenix, AZ 85012 | 602-258-6200

The act of visiting or communicating with Mann, Berens & Wisner, LLP, via this website or by email does not constitute an attorney-client relationship. Communications from non-clients via this website are not subject to client confidentiality or attorney-client privilege. Further, the written contents this website are offered as general guidance only and are not to be relied upon as specific legal advice. For legal advice on a specific matter, please consult with an attorney who is knowledgeable and experienced in that area. Full disclaimer