|
Jay M. Mann, Esq.
Recoverability
of Delay Damages
A. COMMON LAW THEORIES FOR RECOVERY
A delay claim is basically
a claim for breach of contract. From the owner’s point of view, the project was
supposed to be finished in a certain number of days if completion is delayed due
to the fault of the contractor, the contractor has breached the contract. From
the contractor’s point of view, it estimated a certain number of days on the
project and, in fact, the contract specified the number of days for performance
– if the project takes more than the specified number of days due to actions of
the owner or its architect, the owner has breached the contract.
However, because a
construction project requires that a number of disciplines work closely together
to achieve a complex goal, identifying the causes of delay, and the damages that
flow therefrom, goes well beyond a typical breach of contract action. An
oft-quoted passage from the District of Columbia Court of Appeals echoes this
problem:
We note
parenthetically and at the outset that, except in the middle of a
battlefield, nowhere must men coordinate the movement of other men and all
materials in the midst of such chaos and with such limited certainty of
present facts and future occurrences as in a huge construction project . . .
Even the most painstaking planning frequently turns out to be mere
conjecture and accommodation to changes must necessarily be of the rough,
quick and ad hoc sort, analogous to ever-changing commands on the
battlefield.
Blake Construction Co. v.
C.T. Coakley Co., Inc., 431 A.2d 569 (D.C. 1981).
There are three characteristics of delay: first,
the “nature” of the delay; second, the “extent” of the delay; and third, the
“cost” of the delay. For example, if an owner requests numerous changes in the
plans and specifications, the project may be completed on time or the project
may be delayed, depending upon the number and the substance of these changes.
Waiting on the architect’s approval for these changes goes to the “nature” of
the delay. How long the contractor must wait before the changes are approved
goes to the “extent” of the delay. The damages incurred while waiting for the
changes goes to the “cost.”
In the above example, waiting a reasonable time
for the architect’s approval on changed shop drawings is generally within the
contemplation of the parties at the time of the contracting and, indeed, is
often specified in the contract. If the time for architect approval is longer
than that contemplated by the parties at the time of contracting, a court will
most likely allow recovery for delay. See, e.g., Anthony P. Miller, Inc. v.
U.S., 111 Ct.Cl. 252, 77 F.Supp. 209 (1948)(three month delay beyond that
contemplated by the parties; recovery allowed).
Delay damages can be grouped broadly into two
categories: “direct” damages and “indirect” damages. Direct damages are all
those costs which can be traced directly to a delay, such as equipment rental
costs, field office expenses, increased labor costs, and increased material
costs. Indirect damages are the indirect costs arising from changes or delays in
the schedule, such as lost profits, lost use of equipment at the site,
impairment of capital, and increased interest payments on borrowed money because
progress payments were delayed.
The most easily proved direct damage is field
office expense. The contractor can determine the cost of a field office and,
once the length of the delay caused by the owner is proved, the contractor can
simply multiply his weekly or monthly expenses by the length of the delay.
Other types of damages in the category of direct
damages are harder to prove. Suppose Subcontractor A was to have finished before
Subcontractor B began his job, but subcontractor A is delayed for some reason.
If Subcontractor B continues his work, Subcontractor A may have to expend twice
the labor that was budgeted to work around Subcontractor B’s finished work. Such
additional labor may result in additional costs termed “disruption damages” and
may delay the subsequent subcontractor as well. For a representative case
discussing both delay damages and disruption damages, see U.S. Industries,
Inc. v. Blake Construction Co., 671 F.2d 539 (D.C.Cir. 1982).
A delay may cause increased material costs for
materials purchased as scheduled but, because of the delay, needed to be stored.
On the other hand, if the materials were not purchased, during the delay period,
the cost may have increased. These expenses may be easily documented, but
tracing these extra expenses directly back to a certain delay can be difficult.
Loss of productivity and labor inefficiencies can
be caused by delay. Employing labor under adverse weather conditions, bringing
untrained laborers onto the work-site who require extended training, keeping
laborers over an eight-hour day, forcing one shift of workers to explain the
status of the project to a new shift, or forcing different groups of workers
onto the jobsite at one time may result in a claim for damages resulting from
delay.
Increased interest on borrowed money is one of
the most easily proved yet often disallowed indirect damage. See, e.g., Dravo
Corp. v. U.S., 219 Ct.Cl. 416, 594 F.2d 842 (1979); Framlau Corp. v.
U.S., 215 Ct.Cl. 185,568 F.2d 687 (1977). A contractor must often borrow
substantial sums to purchase materials and pay his laborers. The contractor
depends upon progress payments from the owner to make payments on these loans.
Where a project is substantially delayed and progress payments not made, the
interest costs on the borrowed money may be substantial.
The hardest indirect damage to prove is lost
profits. Where a contractor has committed all his resources to one job, he
cannot bid for new jobs. However, the difficulty of proving that he would have
bid for, would have received, and, most important, would have made a profit on
any prospective project often prevents recovery of this speculative damage
claim. See, e.g., TechDyn Systems Corp. v. Whittaker Corp., 245 Va.
291,427 S.E.2d 334 (1993).
An indirect cost related to lost profits is
impairment of capital. Where the contractor has substantial sums tied up in a
project that is delayed, the contractor may exceed his bonding capacity, he may
fail to bid on new jobs, and worst of all, may be forced into bankruptcy. The
courts usually deny recovery for impairment of capital. See, e.g., Lewis v.
Mobil Oil Corp., 438 F.2d 500 (8th Cir. 1971); Parmet Homes, Inc. v.
Republic Insurance Co., 111 Mich.App. 140, 314 N.W.2d 453 (1981).
The remainder of this paper will address the
parties responsible for delay, the legal theories on which to premise liability,
contract clauses affecting recoverability of delay damages (such as “no damage
for delay” and liquidated damages clauses), and, finally, whether delay damages
can be recovered from either performance or payment bonds issued by a surety.
B. THE PARTIES RESPONSIBLE FOR DELAY
1. Owner Caused Delay
Implied contractual responsibilities of the owner
to the contractor can include the following: to provide access to the jobsite;
to cooperate with the contractor; and not to unreasonably interfere, hinder, or
delay the work of the contractor. If the owner employs multiple contractors, it
must coordinate the jobsite to ensure that all prior work that is allocated to a
prior contractor is finished so that any subsequent contractor is not delayed
and to ensure that one contractor’s work does not interfere with another
contractor’s work. If the owner breaches any of these implied duties, and the
breach delays the contractor, the owner can be held responsible to the
contractor. Delays resulting from actions by the owner or its representatives
are known as compensable delays. The other two .types of delay, non-excusable
and excusable, will be discussed in subsequent sections.
If the contract specifies a starting date, the
owner impliedly warrants that the site will be available for the contractor to
start work. See, e.g., Blinderman Construction Co., Inc. v. U.S., 695
F.2d 552 (Fed. Cir. 1982); Moorehead Construction Co. v. City of Grand Forks,
508 F.2d 1008 (8th Cir. 1975); Higgins v. City of Fillmore, 639 P.2d 192
(Utah 1981). If the owner fails to provide access to the jobsite, the contractor
most likely will be delayed. Any delay in the start date of the work should be
documented by the contractor, especially where the contract specifies a start
date and allows only a specified number of days to finish the project.
Access to the jobsite involves more than simply
allowing the contractor onto the land. The failure to remove utility poles from
a roadway right of way constituted failure to provide site access in Grant
Construction Co. v. Burns, 92 Idaho 408, 443 P.2d 1005 (1968). Failure to
provide site access can include a prior contractor, hired by the owner, who
fails to complete work precedent to the start of a project. Moorehead
Construction Co. v. City of Grand Forks, 508 F.2d 1008 (8th Cir. 1975);
see also In re Roberts Construction Co., 172 Neb. 819, 111 N.W.2d 767
(1961). An owner who allows an earlier work force to delay the contractor’s
access to the job site can be liable for delay. Head Construction Co.,
77-1 B.C.A. (CCH) ¶ 12,226 (1977)(ENGBCA No. 3537). However, an Illinois court
denied a general contractor’s claim for damages due to a delay in site
availability because the court found that a specific start date was not implied
in the contract and the contractor accepted the risk of prior contractors not
finishing the work required before the general contractor could start. J.F.
Edwards Construction Co. v. Illinois State Toll Highway Authority, 34
Ill.App.3d 929, 340 N.E.2d 572 (1975). For more complete discussion of
“owner-caused” delays see, generally, 2 S. Stein, Construction Law, ¶
6.11 (1988).
Constantly making changes in the contract
drawings is one of the most common ways that an owner can interfere or hinder
the general contractor. Although most contracts allow minor changes in the work,
constant changes can escalate into major delay on the project. Federal
government contracts have specific clauses allowing changes in drawings and
specifications, provided those changes are within the scope of the contract. The
contractor may get direct costs for these changes, but not consequential damages
which include damage for delay. However, if such changes are “cardinal”, i.e.,
beyond the scope of the original contract, the contractor can recover
consequential damages for delay. For a case illustrating what is and what is not
a cardinal change, see McDaniel v. Ashton-Mardian Company, 357 F.2d 511
(9th Cir. 1966)(subcontractor could not recover consequential damages because
changes were not cardinal).
An owner can also delay the contractor by failing
to coordinate the work of various other contractors at the jobsite. ¶ 6.1.3 of
the 1987 version of the General Conditions of the Contract for Construction, AIA
Document A201, expressly provides that the owner “shall provide for coordination
of the activities of the Owner’s own forces and of each separate contractor with
the work of the Contractor, who shall cooperate with them.” Some courts have
held an owner’s duties go beyond merely assuring that the different contractors
are not frustrated. These courts have held that the owner has an affirmative
duty to coordinate the work at the project site. See e.g., Gaspirini
Excavating Co. v. Penn. Turnpike Comm’n, 409 Pa. 465, 187 A.2d 157
(1963). The owner may be able to shift this burden onto the contractors
themselves, however, by including a clause in each of the contracts that places
each prime contractor in privity with the others. See Edwin J. Dobson v.
Rutgers State University, 157 N.J.5uper. 357, 384 A.2d 1121 (1978), aff'd
sub nom. Broadway Maintenance Corp. v. Rutgers, 180 N.J.Super. 350, 434 A.2d
1125 (App. 1981), reaff’d, 90 N.J. 253,447 A.2d 906 (1982).
An owner can be liable for interference with a
contractor’s ability to complete a project early. See, e.g., Sun Shipbuilding
& Drydock Co. v. United States Lines, Inc., 439 F.Supp. 671 (E.D.Pa. 1977),
aff'd without opinion, 582 F.2d 1276 (3rd Cir. 1978), cert.
denied 439 U.S. 1073 (1979); Housing Authority v. E.W. Johnson
Construction Co., 264 Ark. 523, 573 S.W.2d 316 (1978). In such a case, the
contractor must be able to show that it would have completed the work prior to
the scheduled completion date but for the delays attributable to the
owner. Id. It should be noted that the federal courts were very skeptical
about allowing a contractor to recover from the United States for delay to an
early completion. See, e.g., United States v. Blair, 321 U.S. 730, 64
S.Ct. 820, 88 L.Ed. 1039 (1944). However, more recent cases recognize the right
to recover, albeit with strict requirements as to proof. See, e.g.,
Weaver-Bailey Contractors, Inc. v. U.S., 19 Cl.Ct. 474 (1990);
Metropolitan Paving Co. v. United States, 163 Ct.Cl. 420, 325 F.2d 241
(1963); In re ACS Construction Co.. Inc., ASBCA No. 35872 (October 18,
1988).
An owner can interfere with the contractor in
other ways, including: stopping the work repeatedly to discuss the job with the
workmen, Natkin & Co. v. George A. Fuller Co., 347 F.Supp. 17 (W.O. Mo.
1972); directing the contractor to perform work in a sequence materially
different from that called out in the contract, Turnbull, Inc. v. U.S.,
180 Ct.Cl. 1010 389 F.2d 1007 (1967); and insisting on stricter tolerances than
that called for in the contract specifications, Kenneth Reed Construction Co.
v. U.S., 201 Ct.Cl. 282, 475 F.2d 583 (1973). However, it is not
interference for an owner to issue stop work notices to correct apparently
non-conforming work, even though the work actually was conforming. Stammel
Const. Co., 75-1 BCA (CCH) ¶ 11,078 (1974); Stallings & McCorvey, Inc.,
83-2 BCA (CCH) ¶ 16,718 (1983).
An owner can interfere with the contractor by
failing to disclose conditions at the jobsite which the owner knew would likely
cause delays to the contractor. Warner Construction Co. v. City of Los
Angeles, 2 Cal.3d 285, 466 P.2d 996, 85 Cal.Rptr. 444 (1970);
Metropolitan Paving Co. v. U.S., 163 Ct.Cl. 420, 325 F.2d 241 (1963). Also,
the failure to make timely progress payments can delay the contractor if it must
pull off the job. An unwarranted refusal by the owner to make progress payments
justifies abandonment of the project by the contractor. See General
Conditions of the Contract for Construction, AIA Document A201, 1987 ed., ¶
9.7.1.
The owner can be held liable for errors in the
plans and specifications. If the owner supplies the specifications and the
drawings, it impliedly warrants their suitability for the intended purpose and
the contractor can recover delay damages resulting from errors in the plans or
specifications. U.S. v. Spearin, 248 U.S. 132,39 S.Ct. 59, 63 L.Ed. 166
(1918); Laburnum Const. Corp. v. U.S., 163 Ct.Cl. 339, 325 F.2d 451
(1963). Also, the contractor can recover for time spent correcting defects in
the plans and specifications that result in delays. Carl M. Halvorson, Inc.
v. U.S., 198 Ct.Cl. 882, 461 F.2d 1337 (1972). The owner can cause delay by
failing to approve changes in the shop drawings. Unless the contract
specifically mentions a time for approval, the review and return by the owner
should be within a “reasonable” time. Grow Construction Co. v. State, 56
A.D. 2d 95, 391 N.Y.S.2d 726 (1977); Continental Consolidated Corp., 67-2
BCA (CCH) ¶ 6624 (1967).
Finally, if the owner delays the project, or
issues change orders affecting the completion date, but at the same time
requires the contractor to meet the project schedule without extension, the
owner can be held liable for acceleration damages. See, e.g., Norair
Engineering Corp. v. U.S., 229 Ct.Cl. 160, 666 F.2d 546 (1981); Nat
Harrison Assoc., Inc. v. Gulf States Utilities Co., 491 F.2d 578 (5th Cir.
1974); Siefford v. Housing Authority of City of Humboldt, 192 Neb. 643,
223 N.W.2d 816 (1974); Walter Kidde Constructors, Inc. v. State, 37
Conn.Supp. 50, 434 A.2d 962 (Conn.Super.Ct. 1981). To recover acceleration
damages under federal law, the contractor must show that the delay forcing the
acceleration was excusable. See, e.g., Envirotech Corp. v. Tennessee Valley
Auth., 715 F.Supp. 190 (W.D.Ky. 1988)(contractor denied recovery for
acceleration efforts geared toward award for early completion, not at direction
of owner).
2. Delays Caused by Third Parties
If the owner employs multiple prime contractors,
pinpointing the cause of delay may be as difficult as apportioning the cost.
Some courts have allowed a contractor to sue other prime contractors under a
third-party beneficiary theory. See, e.g.,., Hanbery Corp. v. State Bldg.
Comm., 390 So.2d 277 (Miss. 1980); Barth Electric Co. v. Traylor Bros.,
Inc., 553 N.E.2d 504 (Ind.App 1990)(AIA General Conditions made co-prime
contractors into third-party beneficiaries of separate prime contracts).
However, where the jurisdiction follows strict third-part beneficiary
principles, the court may not allow such cross-contractor suits. See, e.g.,
Norton v. First Federal Savings, 128 Ariz 176, 624 P.2d 854 (1981)(for a
person to recover as a third-party beneficiary of a contract, an intention to
benefit that person must be indicated in the contract itself, the contemplated
benefit must be both intentional and direct, and it must definitely appear that
the parties intended to recognize the third party as the primary party to be
benefitted).
When dealing with the federal government, the
contractor should be aware of the U.S. Supreme Court cases of U.S. v. Rice,
317 U.S. 61, 63 S.Ct. 120, 87 L.Ed. 53 (1942) and U.S. v. Blair, 321 U.S.
730,64 S.Ct. 820, 88 L.Ed. 1039 (1944) that place the cost of delays caused by
other contractors onto the prime contractor. These cases were dependent on the
standard “extension of time only” or “no damage for delay” clause in government
contracts. This may result in the cost of delay being placed on the least
responsible party --the delayed· prime contractor.
The better reasoned theory is to place liability
for multiple-prime contractor delay on the owner under an implied covenant to
coordinate the work or an implied duty to facilitate the work of the various
primes. See, e.g., Shalman v. Board of Education, 31 A.D.2d 338, 297
N.Y.S.2d 1000 (l969)(owner has implied duty not to interfere and impliedly
agrees that contractor will not be unreasonably delayed by failures of others to
perform their work); J.A. Jones Construction Co. v. City of Dover, 372
A.2d 540 (Del.Super. 1977)(owner must make reasonable efforts to assure that
other contractors perform their contracts); Shea-S&M Ball v.
Mossman-Kiewit-Early, 606 F.2d 1245 (D.C.Cir. 1979)(implied duty to exercise
authority to ensure cooperation among multiple prime contractors); United
States Steel Corp. v. Missouri Pacific Railroad Co., 668 F.2d 435 (8th Cir.
1982), cert. denied 459 U.S. 836, 103 S.Ct. 80, 74 L.Ed.2d 77
(l982)(owner liable for delay to bridge superstructure contractor for
substructure contractor’s failure to complete). Notwithstanding these cases, the
contractor who wishes to recover for delay caused by another contractor must
comply with any and all provisions regarding notice to the owner of delay.
See, e.g., Cove Creek Development Corp. v. APAC-Alabama, Inc., 588 So.2d 458
(Ala. 1991)(where contractor failed to provide required twenty-day notice, delay
caused by prior contractor did not prevent assessment of liquidated damages).
In the absence of exculpatory clauses, courts
will find that the owner impliedly covenants not to hinder or delay the
contract. See, e.g., George A. Fuller Co. v. U.S., 69 F.Supp. 409 (Ct.Cl.
1947). However, in the case of Edwin T. Dobson v. Rutgers State University,
157 N.J.Super. 357, 384 A.2d 1121 (1978), aff'd sub nom. Broadway
Maintenance Corp. v. Rutgers, 180 N.J.Super. 350, 434 A.2d 1125 (App. 1981),
reaff’d, 90 N.J. 253, 447 A.2d 906 (1982), the owner (a state
university) negotiated contract clauses that placed each prime contractor on the
job in privity with the others, thereby putting the responsibility of
coordinating the work on the prime contractors themselves.
A few courts have allowed a cause of action
directly against an architect for failure to coordinate efforts on a jobsite by
multiple prime contractors. See, e.g., E.C. Ernst v. Manhattan Construction
Company, 551 F.2d 1026 (5th Cir. 1977), reh’g denied in part,
granted in part, 559 F.2d 268 (5th Cir.1977), cert. denied, Providence
Hospital v. Manhattan Construction Co. of Texas, 434 U.S. 1067, 98 S.Ct.
1246, 55 L.Ed.2d 769 (1978).
Claims by contractors for delay damages caused by
an architect or engineer normally should be brought against the owner as part of
the contractor’s breach of contract claim, based on the legal position of these
design professionals as agents of the owner. In early cases, the courts held
that a contractor had no cause of action against an architect or an engineer
because there was no privity of contract between the parties. See, e.g.,
Geare v. Sturgis, 14 F.2d 256 (D.C.Cir. 1926), overruled, Hannah v.
Fletcher, 231 F.2d 469 (D.C.Cir. 1956); Gherardi v. Bd. of Education,
53 N.J.Super. 349, 147 A.2d 535 (1958). In other early cases, the courts held
that the architect or engineer was immune from suit based on the design
professional’s “quasi-judicial” function in the construction process. See,
e.g., Craviolini v. Scholer & Fuller Associated Architects, 89 Ariz. 24, 357
P.2d 611 (1960); Wilder v. Crook, 250 Ala. 254, 34 So.2d 832 (1948).
Courts are increasingly recognizing architects’ and engineers’ liability
directly to the contractor, notwithstanding the lack of privity, albeit on a
tort theory.
For example, California courts recognized early
that privity is not required for third-parties to sue professionals for
negligence. See, e.g., Gagne v. Bertram, 43 Ca1.2d 481, 275 P.2d 15
(1954)(soils engineer liable to third-party landowner for negligence). In
Huber, Hunt & Nichols, Inc. v. Moore, 67 Cal.App.3d 278, 136 Cal.Rptr. 603
(1977), California extended this reasoning to architects:
The general rule in California is
that a professional person may be held liable to third persons who suffer
damage proximately caused by the negligence of the professional person as an
independent contractor in the performance of his professional duties even
though there is no privity of contract between the third person and the
professional person and even though the client does not complain about the
quality of the professional service. ... The reason for the rule is that the
action is ex delicto, not ex contractu.
Id., 136 Cal. Rptr. at 617 (citations
omitted). The court concluded that “[f]oreseeability and proximate cause now
supplant the former requirement of privity of contract.” Id.; see also
Donnelly Construction Co. v. O’Berg/Hunt/Gilleland, 139 Ariz. 184,
677 P.2d 1292 (l984)(preparation of plans and specifications not quasi-judicial
in nature; contractor allowed to proceed against the architect for negligence
claims despite the lack of privity); Robert & Co. Associates v.
Rhodes-Haverty Partnership, 250 Ga. 680, 300 S.E.2d 503 (l983)(lack of
privity does not shield engineer from liability to purchasers that foreseeably
relied on engineer’s report); American Fidelity Fire Ins. Co. v. Pavia Byrne
Engineering, 393 So.2d 830 (La.Ct.App.1981), cert. denied, 397 So.2d
1362 (La. 1981)(engineer liable to performance bond surety for overpayments
based on negligent issuance of percent complete certificates). However, the lack
of privity defense may still be viable in some jurisdictions. See, e.g.,
Bryant Electric Co. v. City of Fredericksburg, 762 F.2d 1192 (4th Cir.
1985)(under Virginia law, subcontractor cannot recover for delay from architect
absent privity).
To recover damages for delays caused by a
supplier, the contractor must be able to prove that the supplier knew of the
time constraints and the specific costs that would be incurred if the supplier
delayed shipment. This follows the often stated rule of Hadley v. Baxendale,
156 Eng.Rep. 145 (1854) that a party to a contract is not responsible for
consequential damages of which he was not aware. See, e.g., U. S. ex rel.
Pioneer Steel Co. v. Ellis Construction Co., 398 F.5upp. 719 (E.D.Tenn.
1975); District Concrete Co. v. Bernstein Concrete Corp., 418 A.2d 1030
(D.C.App. 1980); Robberson Steel, Inc. v. T. D. Abrams, Inc., 582 S.W.2d
558 (Tex.Ct.App. 1979); Capital Steel Co., Inc. v. Foster and Creighton Co.,
264 Ark. 683, 574 S.W.2d 256 (1978).
3. Concurrent Delay
In the past, most courts followed the rule that
neither party could collect from the other where each has contributed to the
delay. The courts basically washed their hands of any attempt to apportion delay
damages in a situation where both parties were at fault. See, e.g., Gogo v.
Los Angeles County Flood Control District, 45 Cal.App.2d 334, 114 P.2d 65
(1941); S.O.G. v. Missouri Pacific Railroad, 658 F.2d 562 (8th Cir.
1981); J.A. Jones Construction Co. v. Greenbriar Shopping Ctr., 332
F.Supp. 1336 (N.D. Ga. 1971), aff'd 461 F.2d 1269 (5th Cir. 1972);
Broome Construction, Inc. v. U.S., 203 Ct.CI. 521, 492 F.2d 829 (1974).
In each of these cases, the court refused to apportion liquidated damages where
the owner and the contractor had each contributed to the overall delay. However,
in recent decisions, some courts have attempted to apportion damage claims when
either the owner or the contractor can give clear proof that it was not
responsible for certain aspects of the overall delay at the project. See,
U.S. v. William Klingensmith, Inc., 670 F.2d 1227 (D.C. Cir. 1982);
Blinderman Construction Co., Inc. v. U.S., 695 F.2d 552 (Fed. Cir. 1982).
California courts have allowed apportionment where the contract contains a “no
damage for delay” or “extension of time only” clause. See, e.g., Nomellini
Construction Co. v. Department of Water Resources, 19 Ca1.App.3d 240, 96
Cal.Rptr. 682 (1971) and Jasper Construction, Inc. v. Foothill Junior College
District, 91 Cal.App.3d 1, 153 Ca1.Rptr. 767 (1979)(statute expressly
authorizing liquidated damages provisions in public contracts; apportionment
allowed). However, where neither party can separate the concurrent delay, the
liquidated damages provision will not be enforced. See, e.g., In re C.D.
Murray Co., ENG BCA No. 5018 (October 31, 1988).
4. Contractor Caused Delay
a. Non-Excusable/Excusable Delays
Non-excusable delays are those caused by factors
within the control of the contractor, including delays caused by its
subcontractors or suppliers. The contractor is not entitled to either time
extension or additional compensation for non-excusable delays. Excusable delays
are delays for which neither the contractor nor the owner bear responsibility.
These include acts of God (such as unusually severe weather), acts of the
government, and labor strikes arising from unforeseen causes beyond the control
of the contractor. Severe weather alone is not an act of God which will excuse
performance because every contractor must contemplate that weather will at times
disrupt performance and may delay the project. To be an excusable delay, the
frequency, duration, or intensity of the severe weather must be unusual and
therefore unforeseeable by the general contractor. See, e.g., Broome
Construction, Inc. v. U.S., 203 Ct.Cl. 521, 492 F.2d 829 (974)(unusually
severe weather is adverse weather which at the time of the year that it had
occurred was unusual for the place in which it had occurred). For a case where a
general contractor was excused from delay caused by unusually severe weather,
called a “hundred-year flood”, see New Pueblo Construction, Inc. v. State of
Arizona, 144 Ariz. 95,696 P.2d 185 (1985).
Typically, the contractor is granted an extension
of time to complete that is mutually agreed upon by the owner and the
contractor. The contract may contain a clause which allows the architect to
arbitrate and to set the time allowed for completion if the two parties cannot
agree. See General Conditions of the Contract for Construction, AIA
Document A201, 1987 ed., ¶¶ 4.3.8.2 and 4.4. The amount of time allowed for
completion should reflect the total time lost and not just the number of days
the work was stopped. A delay of two months, for example, might cause a delay of
five months if completion is pushed into the winter season.
The general contractor is responsible for delays
caused by its subcontractors and suppliers. The contractor should make sure that
all subcontracts incorporate the provisions of the prime contract that call for
liquidated damages or other damages to be assessed against the contractor in
case of delay. If held liable to the owner, the contractor should be able to
recover from its subcontractors for any delay damages that resulted directly
from the subcontractor’s own delay. The contractor should be wary, however, of
blanket incorporation or “flow down” clauses which are discussed below.
b. Subcontractor Delay Claims
The general rule is that the general contractor
is liable to the subcontractor for all delay caused by the general contractor
that damages the subcontractor. See, e.g., Frank T. Hickey, Inc. v. Los
Angeles Jewish Community Council, 128 Cal.App.2d 676, 276 P.2d 52
(Cal.App.1954)(ordinarily, contractor in control of the work is under obligation
to make good all losses resulting from delays in the progress of the work not
attributable to the subcontractor). The contractor has an implied duty, much the
same as the owner has, to cooperate with the subcontractor and to not hinder the
subcontractor’s performance. See, e.g., Johnson v. Fenestra, 305 F.2d 179
(3d Cir. 1962)(implied obligation on contractor to facilitate work of
subcontractors); Unis v. ITS Constructors/Managers, Inc., 541 So.2d 278
(La.App. 1989)(contractor must schedule and arrange work in a manner that avoids
delaying the work of any subcontractor); see also H.H. Robertson Co. v. V.S.
DiCarlo General Contractors, Inc., 950 F.2d 572 (8th Cir. 1991)(contractor
has implied duty to provide timely access and coordinate its work and the work
of the subcontractors). However, the contractor may be able to avoid
coordination responsibilities to its subcontractors by a carefully worded
disclaimer. See, e.g., L.K. Comstock & Co., Inc. v. United Engineers &
Constructors, Inc., 880 F.2d 219 (9th Cir. 1989); see also High Point
Sprinkler Co. v. George Hyman Construction Co., 297 S.E.2d 757 (Ga.App.
1982)(contractor successfully delegated duty to coordinate shop drawings among
subcontractors).
In the absence of a specific subcontract clause,
it has been held that subcontractors do have an implied duty to coordinate the
work among each other. At least one court has held that subcontractors do not
owe a duty to coordinate with each other and cannot be responsible for another
subcontractor’s delay. Morse/Diesel, Inc. v. Trinity Industries, Inc.,
859 F.2d 242 (2d Cir. 1988).
To recover for delay, the subcontractor must
prove that the contractor caused substantial delay, that the subcontract terms
forbid such delay, and that the subcontractor was damaged as a result of the
delay. See, e.g., U.S. ex rel. Gray-Bar Electric Co., Inc. v. I.H. Copeland &
Sons Construction, Inc., 568 F.2d 1159 (5th Cir. 1978). In other words, the
contractor must have breached some term of the subcontract. In most states, the
courts state the proposition broadly: “Absent a contractual commitment
contra, a general contractor is not liable to its subcontractor for damages
flowing from delays incurred by the subcontractor unless the delays were caused
by the general contractor or some agency or circumstance under his direction or
control.” Doyle & Russell, Inc. v. Welch Pile Driving Corp., 213 Va. 698,
194 S.E.2d 719 (1973); see also, McGrath v. Electrical Construction Co.,
230 Or. 295, 364 P.2d 604 (1961)(general rule that the contractor must answer to
subcontractor for delays does not apply to delays caused by the owner or its
agents); W. Wright, Inc. v. Korshoj Corp., 197 Neb. 692, 250 N.W.2d 894
(1977)(absent contractual commitment, contractor is not liable to subcontractor
for delays unless caused by contractor or some agency or circumstance under its
control); Loughman Cabinet Co. v. C. Iber & Sons, Inc., 46 Ill.App.3d
873, 361 N.E.2d 379 (Ill.App. 1977)(general conditions of the prime contract,
incorporated by reference into the subcontract, permitted extension of the
construction period under certain circumstances; contractor not liable to
subcontractor).
However, the law in California is “[o]rdinarily,
as between a subcontractor and the contractor who is in control of the work
being performed, the law places the latter under an obligation to make good all
losses consequent on delays in the progress of the work not attributable to the
subcontractor.” Frank T. Hickey, Inc. v. Los Angeles Jewish Community
Council, 128 Cal.App.2d 676, 276 P.2d 52, 59 (App. 1954). “However, this
rule may be made inapplicable by the express provisions of the subcontract.” 276
P.2d at 59. No subsequent California decisions have abrogated this statement of
the law. One other California decision that dealt with subcontractor delay did
not discuss the rule because the general contractor was clearly liable for the
delay. Western Concrete Structures Co. v. Tames 1. Barnes Construction Co.,
206 Cal.App.2d 1, 23 Cal.Rptr. 506 (l962)(contractor delayed preparing
prestressed concrete slabs that subcontractor was to place; subcontractor
allowed to recover for delay from contractor and its surety).
C. CONTRACTUAL CAUSES AFFECTING RECOVERY OF
DELAY DAMAGES
Each party to the construction process attempts
to put its stamp on the contract to deal with the issues of completion, delay
claims, time extensions, and liquidated damages. However, the parties’
expectations as to the effect of these clauses are often dashed by the courts.
Asked to interpret or apply such contract clauses, courts often stray from a
strict interpretation to justify an intended result. Such actions lead to
confusing judicial precedents. This paper will now discuss clauses that affect
delay and court interpretations thereof, including standard contract clauses and
often-used clauses found in non-standard contracts.
1. Standard Contract Form Clauses
a. American Institute of Architects (AIA)
The 1987 edition of the General Conditions of the
Contract for Construction, AIA Document A201, is perhaps the most widely used
contract form. ¶ 3.10 requires the Contractor to provide a “construction
schedule” to the Architect and Owner that complies with the “time limits current
under the Contract Documents.” Most often, the schedule provided is a bar chart
showing beginning and end dates. However, given that almost any project may be
subject to delay of one type or another, showing how any given delay: may have
affected the overall project schedule will be difficult, if not impossible, with
a simple bar chart.
In hindsight, many contractors wish they would
have taken the time and effort to provide a more detailed schedule, such as a
network-based schedule or critical path method (CPM) chart. Developing such a
chart or schedule requires a detailed analysis of the project, its fundamental
parts, and the inter-relationships of each activity. Providing and maintaining a
CPM chart throughout the project can reap rewards if the contractor must show,
after the fact, how a delay by the owner or its architect affected the project.
However, even if such a chart is utilized, that is no guarantee of a successful
delay claim.
Although the CPM analysis is a
well-respected tool and may be useful to a trier of facts for ascertaining
the impact and interrelationship of Government [owner]-caused delays in
project scheduling, its usefulness as a barometer for measuring time
extensions and delay damages is necessarily circumscribed by the extent to
which it is employed in an accurate and consistent manner to comport with
the events actually occurring on the job .... [T]his is the single most
important factor in determining the acceptability of a contractor’s delay
analysis.
Ballenger Corp., 84-1 B.CA. (CCH)
¶ 16,973 (l983)(DOT CAB No. 74-32)(citations omitted).
Paragraph 8.1 et seq. defines time and all
related aspects thereof. 8.2.1. expressly states that time is of the essence.
The contractor must “proceed expeditiously with adequate forces and shall
achieve Substantial Completion within the Contract Time.” ¶ 8.2.3. Paragraph
8.3.2 states that all claims for delay shall be made in accordance with the
applicable provisions of ¶ 4.3. “Substantial Completion” is defined by ¶ 9.8
et seq.
Paragraph 4.3, et seq., governs claims for
delay by defining a “claim” as “a demand or assertion by one of the parties
seeking, as a matter of right, ... extension of time or other relief with
respect to the terms of the Contract.” (¶ 4.3.1). Claims must be made by written
notice. (¶ 4.3.1). Paragraph 4.3.8.1 provides that if the contractor wishes to
make a claim for an increase in completion time, written notice must be
given. The written notice must contain an estimate of the cost and the probable
effect of delay on the progress of the work in general. However, the paragraph
does not specify to whom the notice must be given.
Paragraph 4.3.3 sets specific time limits on
claims: twenty-one days after the occurrence of the events giving rise to the
claim or within twenty-one days after the claimant first recognizes the
condition giving rise to the claim, whichever is later. The contractor may lose
any chance of recovering for delay if the notice provisions are not met.
Similarly, ¶ 4.2.11 states that delay caused by the failure of the architect to
provide interpretations of the contract documents as required shall not be
recognized “until 15 days after written request is made for them.”
If the contractor has failed to comply with the
writing requirement, it can attempt to show that the owner was responsible for
or had actual or constructive knowledge of the delay, and its impact on the
contractor. See, e.g., Peter Kiewit Sons’ Co. v. Pasadena City Junior
College Dist., 59 Cal. 2d 241, 379 P.2d 18, 28 Cal. Rptr. 714
(1963)(requirement that requests for extension be in writing not enforceable
where owner responsible for delay); Vanderlinde Electric Corp. v. City of
Rochester, 54 A.D.2d 155, 158, 388 N.Y.S.2d 388, 391 (1976)(when an owner is
fully and continuously aware of project delays, even without notice from the
contractor, owner has “a continuing duty to inquire into the causes of such
delay and to minimize potential damages”); GB&E Electric Contractors,
87-3 RC.A. (CCH) ¶ 20,119 (1987)(ASBCA No. 34026)(oral notice sufficient);
Steve Nanna, Inc., 83-2 B.C.A. (CCH) ¶ 16,692 (1983)(DOT CAB No.
1343)(actual knowledge); Leiden Corp., 83-2 B.C.A. (CCH) ¶ 16,612 (ASBCA
No. 26136)(constructive knowledge); contra, Central Penn Industries, Inc. v.
Department of Transportation, 25 Pa.Commw. 25, 358 A.2d 445 (Pa.Commw.Ct.
1976)(contractor that encountered unexpected soil conditions not allowed
recovery due to failure to comply with requirement to supply written notice to
owner of potential delay); Blankenship Construction Co. v. North Carolina
State Highway Comm’n, 28 N.C.App. 593,222 S.E.2d 452 (N.C.App. 1976),
review denied, 290 N.C. 550, 230 S.E.2d 765 (1976)(no recovery for delay
due to unexpected rock where contractor failed to comply with contract
requirements of written notice and contemporaneous cost accounts).
b. Association of General Contractors (AGC)
The Standard General Conditions of the AGC
Construction Contract drafted by the Engineers Joint Contract Documents
Committee addresses claims for delay in Articles 10, 11 and 12. Written notice
to the owner and engineer must be made “promptly (but in no event later than
thirty days) after occurrence of the event giving rise to the claim ... .” ¶
12.1 Notice of the “extent of the claim and supporting data shall be delivered
within sixty days after such occurrence ... .” ¶ 12.1.
Paragraph 12.2 defines the types of delays for
which the contractor may apply for an extension of contract time: “acts of
neglect by OWNER or other performing additional work as contemplated by Article
7, or to fires, floods, labors disputes, epidemics, abnormal weather conditions
or acts of God:’ Finally, ¶ 12.3 states that time is of the essence.
c. Federal Government Contracts
For the most part, federal contracts contain “no
damage for delay” clauses. That is, the contractor is allowed only an extension
of completion time for delay caused by the government. To the extent that a
subcontract incorporates the prime contract, the subcontractor is bound by such
a clause as is the contractor. A representative decision in which the court
denied recovery by a subcontractor for delay damages is McDaniel v.
Ashton-Mardian Co., 357 F.2d 511 (9th Cir. 1966).
In McDaniel, the subcontractor filed suit
against the general and its Miller Act surety for delay damages. The subcontract
incorporated the terms of the prime contract which allowed the government to
make changes in the work. The subcontract required the subcontractor to
“complete this contract within the time herein limited for that purpose or
within said term as it may be extended. by reason of delay, changes, additions,
or other reasons called for or allowed by the Contractor and Architect and/or
Engineer.” Id. at 513. The prime contract allowed 450 days, but the work
actually took an additional 196 days. The delay was caused, in part, by
thirty-nine change orders. No delay was attributed to the subcontractor. Three
of the change orders granted the contractor additional time covering the delay
period. The contractor finished within the time allowed by the extension. When
the subcontractor filed its action, the contractor pursued its administrative
remedies against the government. After losing before several administrative
boards, the parties returned to the district court which denied relief to the
subcontractor.
The subcontractor based its claim in the district
court on two grounds: tort and contract. As to the tort claim, the Ninth Circuit
noted that the prime contract allowed the government to make changes without
additional liability for delay and, therefore, the contractor was required to
accept the changes with only an extension of time for performance. Therefore,
there was no wrongful act on which the subcontractor could base a tort claim.
Id. at 515.
As to the contract claim, the subcontractor
claimed it would be unfair to keep subcontractors on the project during periods
of delay without compensation. The Ninth Circuit noted that it was equally
problematic if “[contractor] could recover nothing for delays caused by change
orders it was obligated to carry out, yet would be liable to each of its
subcontractors whose work was delayed by changes.” Id. at 516.
Resolving this dilemma, the court adopted the
district court’s opinion:
[The] provisions of the subcontract
and the General Contract make it clear that both [subcontractor] and
[contractor] knew when they entered into the subcontract that it could ...
happen that the work under the subcontract would not be completed within the
450 days specified in the General Contract; that changes might be made by
the United States which would necessarily extend the performance period of
the General Contract and, subsequently, the performance period of the
subcontract. Both ... knew, also, that if any changes authorized by Section
3 and ordered by United States should result in delay damages to
[contractor], no compensation ... could be recovered ... from the United’
States. Hence, it is reasonable to conclude that [they] did not intend their
subcontract to mean that [subcontractor] could recover from [contractor] for
delays occasioned by proper change orders of the United States.
Id. at 516. The Ninth Circuit finished its
opinion with this general statement:
Potential damage from delay is
inherent in any construction contract. If the delay results from action
which the party causing the delay was authorized by the contract to take, it
would be difficult, in any case, to justify the award of delay damages to
another party to the contract. When the party causing the delay is the
United States Government, and the contract is the standard government
contract, it is impossible, in the face of the precedents which we have
cited, to find an equitable reason why a prime contractor, without fault and
without option and without right of reimbursement from the Government,
should have to compensate his subcontractor for damages resulting from
delayed performance.
Id. at 517.
Subsequent federal cases have distinguished the
McDaniel decision on its facts. In Havens Steel Co. v. Randolph
Engineering Co., 613 F.Supp. 514 (W.D. Mo. 1985), the court also was faced
with a subcontractor claiming for delay, some of which was caused by the
architect, some by the general contractor. The subcontract did not contain a “no
damage for delay” clause. In allowing recovery, the court reasoned:
While it is true (absent a contrary
contractual provision) that a general contractor will ordinarily not be
liable to its subcontractor for damages resulting from delay, unless the
delay is in fact caused by the general contractor or some agency or
circumstance under its control, [citing McDaniel, McGrath, Doyle &
Russell, Frank T. Hickey, Inc.], that principle does not require, in
cases of multiple causation involving the general contractor and others,
that the subcontractor show the proportional part played by the general
contractor and segregate the loss accordingly. ... The rule to be applied in
that situation is instead the ordinary contracts rule applicable to damages
involving multiple causes: that if the defendant’s breach or fault was a
“substantial factor” in causing the injury, the defendant will bear full
responsibility for it even though there were other, contributing causes.
[Contractor’s] delays were clearly a “substantial factor” in causing the
damages here. The fact that [the architect] or other parties may have also
played some part in connection with the problem is immaterial.
Id. at 532.
Subcontractors should be aware that even where
the contractor may have failed to disclose changes to the project’s schedule,
allegedly delaying and disrupting a subcontractor, recovery for delay may not be
clear cut if there is a no damage for delay clause in the subcontract. See,
e.g., Crawford Painting and Drywall Co. v. I.W. Bateson Co., 857 F.2d 981
(5th Cir. 1988).
d. State Contracts
Unlike the federal government, some states
disfavor “no damage for delay” clauses in their contracts. In California, the
Public Contracts Code § 7102 states:
Contract-provisions in
construction-contracts of public agencies and subcontracts thereunder which
limit the contractee’s liability to an extension of time for delay for which
the contractee is responsible and which delay is unreasonable under the
circumstances involved, and not within the contemplation of the parties,
shall not be construed to . preclude the recovery of damages by the
contractor or subcontractor.
No public agency may require the waiver,
alteration, or limitation of the applicability of this section. Any such waiver,
alteration, or limitation is void.
Cal.Pub.Cont. Code§ 7102.
Therefore, in California or any other state with
similar laws, it may be argued that federal cases involving no damage for delay
clauses are distinguishable and should not be followed in those jurisdictions.
2. Non-Standard Contract Causes
a. Exculpatory Clauses
A typical clause found in a subcontract may be
written as follows:
No claims for additional
compensation or damages for delays, whether caused in whole or in part by
any conduct on the part of the Contractor, including, but not limited to,
conduct amounting to a breach of this Agreement, or delays by other
subcontractors or Owner, shall be recoverable from Contractor, and the above
mentioned extension of time for completion shall be the sole remedy of
Subcontractor, provided, however, that ... .
Such a clause is sometimes referred to as an
“exculpatory clause.” See, e.g., Atlantic States Construction, Inc. v. Hand,
Arendall, Bedsole, Greaves and Johnson, 892 F.2d 1530 (11th Cir.
1990)(exculpatory clause serves the purpose of insulating the general contractor
itself from the possibility of being (1) liable to the subcontractor for delay
caused by the government, yet (2) unable to recover from the government).
Subcontractors must be aware that the effect of any such clause in their
subcontracts may prevent recovery for any delay.
b. “Flow-Down” Clauses
Subcontractors also should be aware that their
subcontracts may contain so-called “flow-down” clauses that effectively
incorporate every delay damage-related clause from the prime contract into the
subcontract. The typical flow-down clause states that the subcontractor assumes
towards the contractor all the duties, obligations, and liabilities the
contractor has assumed toward the project owner. However, there must be some
limit on the application of these clauses because if enforced as written, the
subcontractor would be liable to build the entire project.
The general position taken by federal courts has
been that broad flow-down clauses incorporate only the applicable work
requirements of the prime contract, not the procedural or administrative
provisions. See, e.g., U.S. ex rel. N.U., Inc. v. Gulf Ins. Co., 650
F.Supp. 557 (S.D.Fla. 1986)(“disputes” provision of federal prime contract not
imposed on subcontractors by virtue of broad flow-down provision); Wollf &
Munier, Inc. v. Whiting-Turner Contracting Co., 946 F.2d 1003 (2d Cir.
1991)(general flow-down clause does not incorporate “no damage for delay” clause
in prime contract). Other federal courts have denied the application of a
flow-down clause where the effect would be to deny the subcontractor its Miller
Act rights. See, e.g., Fanderlik-Locke Co. v. U.S. ex rel. M.B. Morgan,
285 F.2d 939 (l0th Cir. 1960), cert. denied, 365 U.S. 860
(l961)(notwithstanding flow-down clause as to arbitration, subcontractor could
proceed on Miller Act claim while arbitration pending).
State courts appear to be less forgiving and, in
general, enforce broad flow-down clauses. See, e.g., Air Cooling & Energy,
Inc. v. Midwestern Construction Co., 602 S.W.2d 926 (Mo.App. 1980)(owner’s
site condition disclaimer in prime contract enforced via flow-down clause in
subcontract) c.f., Sanders Co. Plumbing and Heating, Inc. v. City of
Independence, 694 S.W.2d 841 (Mo.App. 1985)(owner’s site condition
disclaimer not effective to place burden on contractor); Sime Construction
Co. v. Washington Public Power Supply System, 28 Wash.App. 10, 621 P.2d 1299
(1980), review denied, 95 Wash.2d 1012 (1981)(fifteen day notice of claim
provision in prime contract incorporated into subcontract via flow-down clause
enforced to deny subcontractor’s claim beyond fifteen day limit).
In summary, subcontractors must be aware of all
terms and provisions in the prime contract dealing with delay claims, whether
such provisions are in their subcontracts or not. A broad flow-down clause may
require the subcontractor to give notice of a delay within a certain number of
days as required by the prime contract. Further, given a broad flow-down clause,
the contractor may be able to enforce a “no damage for delay” clause in the
prime contract against the subcontractor although the subcontract does not
contain a “no damage for delay” clause.
3. Enforceability of “No Damage for
Delay” Clauses
The most common type of clause that will prevent
a contractor’s delay claim is the “no damage for delay” clause. Courts generally
uphold this type of clause as long as it is free from ambiguity and reflects the
intent of the parties as reasonably interpreted. See, e.g., Blake
Construction Co. v. C.T. Coakley Co., 431 A.2d 569 (D.C. 1981)(courts will
uphold the clause unless the contractor can show delays not contemplated by the
parties, delay amounting to abandonment of the contract, bad faith, or active
interference); see also M.A. Lombard & Son Co. v. Public Building Commission
of Chicago, 101 Ill.App.3d 514, 428 N.E.2d 889 (1981)(intent of the parties
clear by inserting clause that no damage for delay was contemplated; clause
upheld); accord John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.,
147 Wis.2d 298, 432 N.W.2d 584 (1988).
Because of the often harsh effect of a no damage
for delay clause, the courts will typically construe ambiguous clauses against
the drafter/owner. See, e.g., Ace Stone, Inc. v. Township of Wayne, 47
N.J. 431, 221 A.2d 515 (1966); Giametta Assoc., Inc. v. T.T. White, Inc.,
573 F. Supp. 112 (E.D. Pa. 1983). Because the clause may cause a contractor to
forfeit its claim, some jurisdictions hold that the owner bears the burden of
proving that the particular delay damage claim falls within the scope of the no
damage for delay clause. See, e.g., Hawley v. Orange County Flood Control
Dist., 211 Cal. App. 2d 108, 27 Cal. Rptr. 478 (1963); F.D. Rich Co. v.
Wilmington Housing Authority, 392 F.2d 841 (3d Cir. 1e.g.,68).
The courts make two inquiries into no damage for
delay clauses. First, the court determines what the scope of the clause is as
evidenced by its express language. Does the clause mention both excusable and
unexcusable delays? Does it distinguish between unexcusable delay and
interference? Second, the court determines whether the specific type and source
of the delay were within the contemplation of the parties to the agreement. For
example, was “active interference” by the owner contemplated?
To avoid the effect of a no damage for delay
clause, the contractor must show that the delay encountered falls within one of
the well-recognized exceptions: (1) that the delay encountered was not
contemplated by the parties; (2) fraud, misrepresentation, or other bad faith;
(3) delay resulting in abandonment; (4) delays not specifically enumerated in
the written contract. See, e.g., City of Houston v. R.F. Ball Construction
Co., 570 S.W.2d 75 (Tex.Civ.App. 1978). For a complete overview of these
exceptions, see the Annotation, Validity and Construction of “No Damage” Clauses
With Respect to Delay in Building or Construction Contracts, 74 A.L.R.3D 187
(1976) (general analysis of the validity of no damages for delay clauses) and
Peter Kiewit Sons’ Co. v. Iowa Southern Utilities Co., 355 F.Supp.
376 (S.D. Iowa 1973). The burden is, of course, on the contractor to prove that
the delay falls within the exception. See, e.g., Dickinson Co. v. Iowa State
Dep’t of Transportation, 300 N.W.2d 112 (Iowa 1981).
For two representative cases discussing no damage
for delay clauses, see City of Seattle v. Dyad Construction Co., 17
Wash.App. 501,565 P.2d 423 (1977) (where a sewer line contractor recovered delay
damages from the City because of demands that the contractor perform beyond the
scope of the contract and the City’s interference with the contractor’s
performance) and Housing Authority of the City of Dallas v. Hubbell, 32
S.W.2d 880 (Tex. Civ.App. 1959) (where the City was precluded from using an
exculpatory no damage for delay clause because it failed to provide master
construction schedules, did not coordinate various prime contractors on the
site, and did not permit work to proceed in on orderly manner).
a. Unforeseen and Uncontemplated Delays
There are a number of decisions holding that a no
damage for delay clause cannot operate as to unforeseen or uncontemplated
delays. See, e.g., E.C. Ernst, Inc. v. Manhattan Construction Co. of Texas,
551 F.2d 1026 (5th Cir. 1977), reh’g denied in part, granted in
part, 559 F.2d 268 (5th Cir.1977), cert. denied, Providence Hospital v.
Manhattan Construction Co. of Texas, 434 U.S. 1067, 98 S.Ct. 1246, 55
L.Ed.2d 769 (1978); John E. Green Plumbing & Heating Co. v. Turner
Construction Co., 500 F.Supp. 149 aff'd 305 F.2d 216 (3d Cir.
1962)(clause did not contemplate hindrance); Hawley v. Orange County Flood
Control Dist., 211 Cal. App. 2d 108, 27 Cal. Rptr. 478 (1963); Department
of Transportation v. Arapaho Construction. Inc., 257 Ga. 269,357 S.E.2d 593
(Ga. 1987); c.f. F.D. Rich Co. v. Wilmington Housing Authority, 392 F.2d
841 (3rd Cir. 1968)(delay clearly foreseen does not fall within recognized
exception).
Other jurisdictions have held the opposite,
however, based on the reasoning that as parties can specifically bargain for
foreseeable delays, it is the unforeseeable delays that such clauses were
intended to address. Note, however, that these decisions reflect what appears to
be the minority position. See. e.g., John E. Gregory & Son, Inc. v. A.
Guenther & Sons, Co., 147 Wis.2d 298, 432 N.W.2d 584 (1988); State
Highway Administration v. Greiner Engineering Sciences, Inc., 83 Md.App.
621,577 A.2d 363 (1990)(no damage for delay clause upheld even as to unforeseen
delay); City of Houston v. R.F. Ball Construction Co., 570 S.W.2d 75
(Tex.Civ.App. 1978)(where clause unambiguous, it will be enforced).
A contractor delayed by a differing site
condition but faced with a no damage for delay clause might argue that the
differing site condition is per se unforeseen and, therefore, the no
damage for delay clause should not operate. However, because most federal and
state contracts contain differing site condition or suspension of work clauses,
it is difficult to argue that the parties did not contemplate a differing site
condition. See, e.g., Calumet Construction Corp. v. Metropolitan Sanitary
Dist. of Greater Chicago, 222 Ill.App.3d 374, 581 N.E.2d 206
(l991)(“suspension of work” clause required in all E.P.A. funded projects
applied to defeat recovery by contractor); P.T. & L. Construction Co. v.
State of N.J. Dep’t of Transp., 108 N.J. 539,531 A.2d 1330
(1987)(excellent overview of differing site condition and no damage for delay
clauses). Of course, if the contractor is in a jurisdiction, such as New York,
wherein no damage for delay clauses are strictly upheld whether the contract
contains a differing site condition clause or not, arguing the site condition
was unforeseen will not void the operation of the clause. See, e.g., Blau
Mechanical Corp. v. City of New York, 158 A.D.2d 373, 551 N.Y.S.2d 228
(1990) and Davis Construction Corp. v. County of Suffolk, 149 A.D.2d
404,539 N.Y.S.2d 757 (1989), appeal denied, 74 N.Y.2d 615,549 N.E.2d
151,549 N.Y.S.2d 960 (1989).
b. Owner Interference Exception
Most jurisdictions require that the owner’s
actions which cause delay must be clear and egregious to find such active
interference as to negate the effect of a no damage for delay clause.
Intentional misconduct of the owner or his agents, including the architect or
other prime contractors, certainly constitutes active interference. But the
contractor usually must prove more than simple mistake, error in judgment, lack
of total effort, or lack of diligence. For example, the New York Court of
Appeals in Kalisch-Jarcho, Inc. v. City of N.Y., 58 N.Y. 2d 377, 448 N.E.
2d 413 (1983) held that even “active interference” was insufficient basis to
avoid a no damage for delay clause. The court required the contractor to
demonstrate the owner’s “bad faith and deliberate intent” to delay the
contractor before recovery of delay damages would be allowed. However, the court
hinted that the owner’s “gross negligence” might be sufficient to allow delay
damage recovery.
The New York Court of Appeals revisited the
Kalisch-Jarcho decision in Corinno Civetta Construction Corp. v. City of
New York, 67 N.Y. 2d 297, 493 N.E.2d 905 (1986). In Corinno Civetta,
the court held that negligent interference by the owner is not enough to allow
the contractor to avoid a no damage for delay clause. The contractor must show
interference was the result of willfulness, bad faith, or breach of a
fundamental term of the contract. See also Peter Kiewit Sons’ Co. v.
Iowa Southern Utilities Co., 355 F.Supp. 376 (S.D. Iowa 1973).
Other jurisdictions will negate a no damage for
delay clause if the contractor can show only negligent interference by the
owner. See, e.g., John E. Green Plumbing and Heating Co., Inc. v. Turner
Construction Co., 742 F.2d 965 (6th Cir. 1984)(exculpatory clauses strictly
construed under Michigan law); Newberry Square Development Corp. v. Southern
Landmark, Inc., 578 So.2d 750 (Fla.App. 1991)(owner’s negligent failure to
have the drawings available to commence work sufficient owner interference to
justify an award of damages notwithstanding a no damage for delay clause).
Some states have passed legislation effectively
voiding no damage for delay clauses where the owner attempts to absolve itself
of all liability for its own acts. Such a bill was passed in Washington in
response to the case of Nelse Mortensen & Co. v. Group Health Cooperative of
Puget Sound, 17 Wash.App. 703, 566 P.2d 560, aff'd 90 Wash.2d
843, 586 P.2d 469 (1978) wherein the court upheld a finding that the contractor
was forced to absorb delay costs arising from numerous substantial changes and
untimely specification changes because the owner had included a no damage for
delay clause. Because of the egregious facts of Nelse Mortensen, the
Washington legislature decided that no damage for delay clauses should not be
upheld. Wash.Rev.Code Ann. §§ 4.24.360-.380 (1988). California has also passed
similar legislation. See, e.g., California Public Contracts Code § 7102.
c. Denial of Site Access
Denial of site access is another widely
recognized exception to the operation of a no damage for delay clause. See,
e.g., U.S. Steel Corp. v. Missouri Pacific Railroad Co., 668 F.2d 435 (8th
Cir. 1982)(owner failed to have bridge substructure completed prior to
contractor’s work on superstructure; contractor allowed to recover for delay
notwithstanding no damage for delay clause). However, the Ohio Supreme Court has
held that denial of site access before the contractor mobilizes on site does not
negate a no damage for delay clause. Carrabine Construction Co. v. Chrysler
Realty Corp., 250 Ohio St.3d 222, 495 N.E.2d 952 (Ohio 1986). Therefore, the
contractor should be aware that an owner’s failure to provide site access does
not provide a guaranteed waiver of a no damage for delay clause or a guaranteed
recovery for delay. See, e.g., Appeal of Volpe-Head, Joint Venture, ENG
BCA No. 4726 (July 14, 1989)(government’s failure to provide site access for
several months concurrent with contractor’s failure to acquire approval of
excavation submittal; no recovery).
D. OWNERSHIP OF FLOAT
Defined simply, “float” is that period of time
within which any given activity may be performed before the activity impacts the
critical path. One court defined float as “the difference between the earliest
allowable completion date and the latest allowable completion date.” L.K.
Comstock & Co.. Inc. v. United Engineers & Constructors, Inc., 880 F.2d 219,
230 n. 19 (9th Cir. 1989). However float is defined, both owners and contractors
dispute who owns the float. That is, who is entitled to delay the project
without incurring liability for delay damages because the delayed activity did
not impact the critical path.
In their article, “How to Recognize, Preserve,
Present, and Prosecute Construction Contractors’ Delay Claims,” South
Carolina Law Review, Vol. 40, pg. 943, Summer 1989, authors Asselin and
Harris-Helms discuss the ownership of “float.” Contractors argue that they own
the float because they are responsible for and have control over the “means,
methods, techniques, sequences and procedures for coordinating all portions” of
construction. See, General Conditions of the Contract for Construction,
AIA Document A201 ¶ 3.3.1 (1987). According to this argument, contractors should
be entitled to whatever benefits flow from their shouldering the “means,
methods, techniques, sequences and procedures” responsibilities. All additional
time the contractor can incorporate into its schedule should be available to it
to compensate for schedule deficiencies or for delays which are due to the
contractor or its subcontractors. Of course, the contractor can always choose to
“front-end load” the beginning of the schedule with float so that the benefit of
the float time will not be denied it later in the project. The contractor can
provide this version of the schedule to the owner and, thus, can effectively
deny the owner the use of a real schedule for monitoring purposes.
The owner’s view is that, based upon contract
language, float belongs to it. Contracts often state in an indirect fashion that
the owner is entitled to the float. For example, a contract may indicate that
the contractor will be granted a time extension only if the project completion
date is extended as a result of delay. See, e.g., Rapp v. Mountain States
Tel. & Tel., 606 P.2d 1189 (Utah 1980). Another view is essentially one of
“first in time, first in right;” in other words, the float should be used by the
first party who needs to make up for delay, consistent with the overall best
interests of the project. Under this view, the contractor may be denied use of
the float if the owner, while using the float for the good of the project,
earlier makes up for an owner-responsible delay.
There is a surprising dearth of reported cases
regarding ownership of float. The majority of cases cited by Asselin and
Harris-Helms are Board of Contract Appeals decisions. Some decisions support the
contractor’s right to float time, See, e.g., Fischbach & Moore Int’l
Corp., 77-1 B.CA. (CCH) ¶ 12,300 (l977) (ASBCA No. 18146);
Ferguson-Crowley, Inc., 68-2 B.CA. (CCH) ¶ 7,194 (l968) (ASBCA Nos. 11124,
11307, 12088); Continental Consolidated Corp., 67-2 B.C.A. (CCH) ¶ 6,624
(l967) (ENG BCA Nos. 2743, 2766), aff'd in part, 200 Ct. Cl. 737
(l972); Heat Exchanges, Inc., 1963 B.CA. (CCH) ¶ 3881 (l963) (ASBCA No.
8705), while other cases support the owners’ entitlement. See, e.g.,
Ballenger Corp., 84-1 B.CA. (CCH) ¶ 16,973 (l983) (DOT CAB No. 74-32);
Arntz Bros., 79-2 B.C.A. (CCH) ¶ 14,038 (l979) (ASBCA Nos. 19183); Dawson
Construction Co., 75-2 B.CA. (CCH) ¶ 11,563 (l975) (GSBCA No. 3998). One
court has even held that for a contractor to recover in the event of concurrent
delay, the contractor must show that the owner’s delay affected a critical path
activity while its delay affected only float activities. Fischbach & Moore
Int’l Corp., 77-1 B.C.A. (CCH) ¶ 12,300 (l977) (ASBCA No. 18146).
Only a few federal district court and circuit
court decisions were found in which the court even mentioned float, let alone
discussed who owned it. See, e.g., Comstock, 880 F.2d at 230 n. 19,
supra. In Natkin & Co. v. George A. Fuller Co., 347 F. Supp. 17, 31
(W.D. Mo. 1972), the court discussed “float” in its findings of fact: “Total
float may be used to schedule jobs for all contractors; free float belongs to
one contractor for scheduling anyone activity. Neither total nor free float is
to be used for changes.” Finally, one court discussed float while defining
“critical path”:
The critical path is the longest
series of the work activities through the performance of a whole project. If
an activity on the critical path exceeds its scheduled duration, the
termination of the project will be delayed unless some other activity on the
critical path is performed in less than its scheduled time. A work activity
not on the critical path may be completed later than its scheduled time
without affecting the termination of the project unless the noncritical
activity exceeds its “float” and thereby becomes an activity on the critical
path.
United States Fidelity & Guaranty Co.
v. Orlando Utilities Comm’n, 564 F. Supp. 962,968 (M.D.Fla.1983).
The authors agree with the Comstock
definition of float as the time between contractor-scheduled completion and
owner-allowed completion. Many courts, without mentioning the word “float,” have
permitted the contractor to recover damages for interference with early
completion. See, e.g., Grow Construction Co. v. State, 56 A.D.2d 95, 391
N.Y.S.2d 726 (App. 1977); Housing Auth. of City of Texarkana v. E.W. Johnson
Construction Co., 264 Ark. 523, 573 S.W.2d 316 (1978); Weaver-Bailey
Contractors, Inc. v. U.S., 19 Cl.Ct. 474 (1990); Metropolitan Paving Co.
v. U.S., 163 Ct.Cl. 420, 352 F.2d 241 (Ct.Cl. 1963). These well-reasoned
cases, without explicitly referring to float; have in effect determined that the
float belongs to -the contractor.
E. LIQUIDATED DAMAGES AS SWORD AND SHIELD
1. Limitation on the Recoverability of
Liquidated Damages When a Project is Delayed.
It is well-settled that liquidated damage clauses
are valid and enforceable, as long as a particular clause does not operate as a
penalty. In determining whether a liquidated damages provision constitutes a
penalty, early courts applied many different tests. See, e.g., Keeble v.
Keeble, 5 So. 149 (Ala. 1888)(ten different criteria to measure whether
liquidated damages clause was a penalty). More recently, however, the following
two criteria are applied by most jurisdictions:
1. The actual damages caused by a breach will
be difficult or impossible to accurately estimate; and
2. The sum stipulated is a reasonable
pre-estimate of the probable loss.
See, e.g., Southeastern Land Fund,
Inc. v. Real Estate World, Inc., 237 Ga. 227, 227 S.E.2d 340 (1976).
Even if a contract remedy meets the two elements
set forth above, the contract may still be penal in nature if the stipulated sum
does not set the measure of the damages recoverable. Cheatham v. Kem
Manufacturing Corporation, 372 So.2d 1085 (Miss. 1979). For example, a
contract provision allowing the party to choose between liquidated or actual
damages did not provide for valid liquidated damages and instead acted as a
penalty. See, e.g., Pappas v. Deringer, 145 So.2d 770 (Fla. App.
1962)(“may at their-option” language, which allowed lesser to elect actual or
liquidated damages, made clause void as a penalty); Sheffield v. Paul T.
Stone, Inc., 98 F.2d 250 (D.C. Cir. 1938)(party cannot choose between
liquidated and actual damages after determining which is greater).
Both owners and contractors on private projects
should be aware that the easiest way to defeat a liquidated damages clause is to
show that the owner made no attempt to set a stipulated sum that approximated a
reasonable forecast of the actual damages. See, e.g., San-Ore Gardner v.
Missouri Pacific Railroad Co., 658 F.2d 562 (8th Cir. 1981). The same is not
true as to public projects, especially in states that have passed legislation
that liquidated damages are favored in public works projects and are prima facie
reasonable. See, e.g., California Public Contracts Code § 10226;
Westinghouse Electric Corp. v. City of Los Angeles, 129 Cal.App.3d 771, 181
Cal.Rptr. 332(l982)(damages for delay particularly difficult to ascertain in
public projects); Taos Construction Co. v. Penzel Construction Co., Inc.,
750 S.W.2d 522 (Mo. 1988)(public entity allowed to recover liquidated damages on
showing of breach alone; no need to show actual damages).
A number of Board of Contract Appeals decisions
have struck down liquidated damage clauses where the government entity reduced
the per diem charge. See, e.g., Appeal of Coliseum Construction Co.,
ASBCA No. 36642 (December 6, 1988)(liquidated damages clause lowered from
$1,820.00 per day to $220.00 was admission that no reasonable estimate had been
made at contract formation; clause struck down); Appeal of Dave’s
Excavation, ASBCA No. 36161 (June 8, 1988)(government guidelines called for
$50.00 per day, contract used $125.00 per day without reasonable explanation;
clause struck as unenforceable penalty).
As discussed previously, contractors often insert
incorporation or “flow clauses in their subcontracts, in an attempt to pass
through liquidated damages provisions to the subcontractors. However, to the
extent that a small subcontractor delays the project, resulting in an amount of
damages disproportionate to the amount of its subcontract, the subcontractor may
argue that enforcement of the clause results in a penalty. If the court holds
the incorporated liquidated damages clause void as a penalty, the contractor can
counter that is entitled to recover its actual damages: what was assessed
against it due to the delay, which is the liquidated damage amount.
Contractors that attempt to apportion liquidated
damages by proportioning the per diem amount rather than allocating the number
of days should be aware of the Board of Contract Appeals cases cited previously.
Take, for example, the scenario where a contractor is delayed for sixty days
because three subcontractors concurrently delayed the project. Assume a
liquidated damages provision of $600.00 per day in the prime contract and a
flow-down clause in each of the subcontracts. The contractor is assessed
$36,000.00 by the owner. The contractor may try to charge each subcontractor
$600.00 per day for a total recovery of $108,000.00, but will be unsuccessful
when the subcontractors learn of the contractor’s windfall at their expense. The
subcontractors will argue that assessing each of them the full amount, $600.00
per day, is a penalty.
However, under a strict liquidated damage
analysis, as to each subcontract the estimated amount of damage, if that
subcontractor delayed the contractor, is $600.00 per day. Therefore, the
contractor responds, the clause should be upheld. The subcontractor then must
argue that the flow-down clause is not a true liquidated damage provision
because damages were not difficult to ascertain at the time of contracting;
indeed, the parties knew the damages to the contractor would be $600.00 per day.
If the contractor attempts to apportion the
amount by enforcing liquidated damages at a reduced per diem of $200.00 per day
for each subcontractor, it merely provides more arguments to void the liquidated
damages clause. First, reducing the amount is tantamount to admitting it was
unreasonable; therefore, the clause is void as a penalty. See, e.g., Appeal
of Coliseum Construction Co. supra. Second, the jurisdiction the contractor
is in may not permit apportionment of liquidated damages. See, e.g., Gogo v.
Los Angeles County Flood Control District, 45 Cal.App.2d 334, 114 P.2d 65
(1941). Finally, the subcontractors will argue each of them are not liable for
an equal amount of delay and, therefore, the allocation is too speculative or
uncertain to support an award of damages against it.
A better approach would be for the contractor to
assess each subcontractor the best estimate of the number of days it actually
delayed the project and assess liquidated damages at the full rate of $600.00
per day. See, e.g., Mattingly Bridge Co., Inc. v. Holloway & Son Construction
Co., 694 S.W.2d 702 (Ky. 1985). In this way, the contractor is fully
reimbursed and each subcontractor is fairly required to pay for the delay it
caused.
Perhaps the best approach from the contractor’s
standpoint is to argue that it is not assessing liquidated damages but rather is
assessing actual damages. The flow-down clause merely put the subcontractors on
notice that liquidated damages assessed by the owner would be a component of the
actual damages assessed against the subcontractor if it delayed the project.
There are two advantages to this approach. First, the contractor does not have
to deal with the trappings of liquidated damage provisions and the arguments
outlined above. Second, and most important, the contractor can also assess its
own actual damages for the sixty additional days its employees were on the
project.
If the contractor attempts to assess both the
liquidated damages it paid plus the actual delay damages it incurred,
subcontractors may argue that the “flow-down” clause is really a liquidated
damage provision and that the contractor cannot claim
both liquidated and actual damage. For a good
discussion of liquidated damages in a similar fact situation, see Ely v.
Bottini, 179 Cal.App.2d 287, 3 Cal.Rptr. 756 (1960), where the court
specifically allowed the general contractor to allocate to a subcontractor the
liquidated damages assessed by the owner. In that case, the court answered the
subcontractor’s argument that damages were too speculative as follows:
While Civil Code section 3301,
provides that no damages can be recovered for a breach of contract which are
not clearly ascertainable in both their nature and origin, the fact that the
amount of damage may not be susceptible of exact proof or may be uncertain,
contingent or difficult of ascertainment does not bar recovery. ... One
whose wrongful conduct has rendered difficult the ascertainment of damages
cannot escape liability because the damages could not be measured with
exactness.
3 Cal.Rptr. at 761.
As to the subcontractor’s argument that the
contractor could not apportion liquidated damages citing Gogo v. Los Angeles
County Flood Control Dist., the court held it was inapplicable because there
was no contention that the owner, McCarthy, was responsible for any delay and
the damages assessed were actual damages and not liquidated damages “so that the
special rule with regard to penalties is not applicable.” 3 Cal.Rptr. at 762.
Finally, because the subcontractor offered
evidence that the contractor caused some of the delay, it argued Gogo should
still apply to prevent any apportionment. The court rejected that argument:
But a different rule is applicable
as between a contractor and subcontractor where the primary contract with
the owner provides a penalty for delay and the contractor and subcontractor
are each responsible for part of the delay. The rule in such case is ... ‘A
subcontractor is bound by a [liquidated damage] clause contained in the
original contract ... and if in such a case both the contractor and the
subcontractor are the cause of the delay, each should bear his respective
proportion of the damage resulting therefrom.
3 Cal.Rptr. at 763.
Although it would seem that subcontractors should
try to avoid flow-down clauses that incorporate a prime contract liquidated
damages clause, such a battle may not always be the best strategy. In
Industrial Indemnity Co. v. Wick Construction Co., 680 P.2d 1100 (Alaska
1984), a subcontractor sued the general contractor for payment. The contractor
counterclaimed and asserted the subcontractor had delayed the project 414 days.
On appeal, the Alaska Supreme Court held the subcontractor was liable for 264
days of delay but struck down the trial court’s award of $765,654.00 to the
contractor for delay damages. The court held that the subcontract had
incorporated by reference the liquidated damages clause from the prime contract:
$400.00 per -day. Therefore, the award should have been only $105,600.00 (264 x
$400.00), saving the subcontractor $660,000.00. For similar “flow-through”
cases, see McDaniel v. Ashton-Mardian Co., 357 F.2d 511 (9th Cir. 1966)
and Coast Sash and Door Co. v. Strom Construction Co., 65 Wash.2d 279,
396 P.2d 803 (1964).
Some courts hold that the party seeking to
enforce a liquidated damage clause need not show any injury. See, e.g.,
Mechanical Air Engineering Co. v. Totem Construction Co., 166 Ariz. 191, 801
P.2d 426 (App.1989)(other than proof that liquidated damage amount reasonably
related to actual damages, no proof of actual damages need be made; clause valid
against subcontractor although owner did not charge contractor for delay). The
reasoning behind this position was stated in Litton Industries Credit
Corporation v. Catanuto, 175 Conn. 69, 71,394 A.2d 191, 193 (1978): “The
very purpose for which such provisions are sustained is to obviate the
difficulties of proof of actual damage, once such a provision is found to be
valid, no proof of the true amount of injury is required.” See also Public
Health Trust of Dade County v. Romart Construction, Inc., 577 So.2d 636
(Fla.App. 1991)(if valid liquidated damages clause, actual damages need not be
proven).
Other jurisdictions have held that if no actual
damages are sustained, a liquidated damages clause will not be enforced. See,
e.g., Wehr Constructors, Inc. v. Steel Fabricators, Inc., 769 S.W. 2.d 51
(Ky. 1989); Norwalk Door Closer Co. v. Eagle Lock and Screw Co., 153
Conn. 681, 220 A.2d 263 (l966)(if no actual damages, liquidated damages clause
will not be enforced). If a liquidated damages provision is incorporated
into a subcontract by a “flow-down” clause, a court may hold that because the
clause was a pass-through obligation, if liquidated damages were not assessed by
the owner against the general contractor, none could be assessed against the
subcontractor. See, e.g., Pierce Associates, Inc. v. Nemours Foundations,
865 F.2d 530 (3d Cir. 1989).
As to concurrent delay and liquidated damages, in
the past courts refused recovery to either party. See, e.g., J.A. Jones
Construction Co. v. Greenbriar Shopping Center, 332 F. Supp. 1336 (N.D. Ga.
1971), aff'd, 461 F.2d 1269 (5th Cir. 1972); Medema Homes, Inc.
v. Lynn, 647 P.2d 664 (Colo. 1982). In effect, the owner could not enforce
the liquidated damages clause and the contractor was unable to recover delay
damages. With the advent of CPM or similar scheduling techniques, courts are
more willing to apportion delay. See, e.g., Pathman Construction Co. v.
Hi-Way Electric Co., 65 lll.App.3d 480, 382 N.E.2d 453 (1978); Keith v.
Burzynski, 621 P.2d 247 (Wyo. 1980); E.I.T. Constr. Co., 83-2 B.CA.
(CCH) ¶ 16,712 (1983) (ASBCA No. 22795). In such cases, the moving party has the
burden of showing entitlement to the damages. See, e.g., In re Blackhawk
Heating & Plumbing Co., 76-1 B.C.A. (CCH) ¶ 11,649 (1976)(GSBCA No. 2432).
The contractor must be able to show that the owner’s delay affected a critical
path activity while its delay affected only float activities. See, e.g.,
Fischbach & Moore Int’l Corp., 77-1 B.C.A. (CCH) ¶ 12,300 (1977)
(ASBCA No. 18146); c.f., Wilner v. United States, 23 Cl.Ct. 241
(1991)(concurrent delay off critical path does not prevent recovery for
owner-caused delay on critical path). If the contractor’s delay affected the
critical path, it may not be able to recover delay damages. See, e.g.,
Commerce Int’l Co. v. United States, 338 F.2d 81 (Ct. Cl. 1964). If,
however, the contractor can show that the owner’s delays which affected the
critical path exceeded those of the contractor, it may be able to recover its
apportioned delay damages. See, e.g., Blake Constr. Co., 82-1 B.C.A.
(CCH) ¶ 15,688 (1982) (ASBCA No. 24356).
2. Waiver of Liquidated Damages in Lieu of
Actual Damages
In general, the courts have held that, where a
contract contains a provision for liquidated damages, the contract will control.
See, e.g., Davis v. Tucson Arizona Boys Choir Society, 137 Ariz. 228,669
P.2d 1005 (App. 1983); Hall Construction Co. v. Beynon, 507 So.2d 1225
(Fla.App1987)(if a contract provides for liquidated damages for delay, the party
claiming damages will be entitled only to the liquidated damages). Where a
contract contains a provision for liquidated damages, actual damages are
immaterial, and the parties are bound to accept the amount set forth in the
contract. Brewer v. Nyers, 545 S.W.2d 235 (Tex. App. 1976); Siler v.
Marshall, 251 Md. 342, 247 A.2d 385 (App. 1968); see also Northern
Illinois Gas Co. v. Energy Cooperative Inc., 122 Ill. App. 3d 940, 461
N.E.2d 1049 (1984). Even if the actual damages far exceed those provided by a
liquidated damages clause, if the original estimate was a reasonable forecast,
the damaged party cannot abandon the clause in favor of actual damages. See,
e.g., Monsen Engineering Co. v. Tami-Githens, Inc., 219 N.J.Super. 241, 530
A.2d 313 (1987); X.L.O. Corp. v. John T. Brady & Co., 104 A.D.2d 181, 482
N.Y.S.2d 476 (1984), appeal granted, 110 A.D.2d 1094, 487 N.Y.S.2d 1021(1985),
order aff’d, 66 N.Y.2d 970,489 N.E.2d 768,498 N.Y.S.2d 799
(1985)(owner cannot sue contractor for amount of actual damages in excess of
liquidated damage amount).
The previous section demonstrated that liquidated
damage clauses are not ·enJfor4:eable if shown to be a penalty. If the
liquidated damage clause is held to be a penalty, it will not be enforced and
actual damages will be the measure of recovery. See, e.g., Larson-Hegstrom &
Associates, Inc. v. Jeffries, 145 Ariz. 329, 701 P.2d 587 (App.1985). The
party asserting that a liquidated damage clause operates as a penalty has burden
of proving what the actual damages are and must show that liquidated damages are
not an approximation of that sum. See, e.g., Commercial Union Insurance Co.
v. LaVilla Independent School District, 779 S.W.2d 102 (Tex. Civ. App.
1989).
Further, where the owner has contributed to the
delay, some courts have refused to enforce the liquidated damages provision and
have forced the owner to prove actual damages with the inherent problem of
apportioning the delay. See, e.g., Acme Process Equipment Co. v. U.S.,
347 F.2d 509, 171 Ct.CI. 324 (1965), rev’d on other grounds, 385
U.S. 138 (l966)(concurrent delay causes government to lose its right to insist
on artificial measure of damages applicable to situation where contractor alone
delayed project). The ability to apportion concurrent delay, and a court’s
willingness to allow apportionment, affects whether a liquidated damages clause
will be enforced or whether the owner must show actual damages.
Similar to that in other jurisdictions,
California law on apportionment of liquidated damages has followed a tortuous
path. In early decisions, California courts refused to apportion delay. Gogo
v. Los Angeles County Flood Control District, 45 Cal.App.2d 334, 114 P.2d 65
(Cal. 1941); see also Peter Kiewit Sons’ Co. v. Pasadena City Junior
College Dist., 59 Cal. 2d 241, 379 P.2d 18, 28 Cal. Rptr. 714 (l963)(owner
responsible for delay was not entitled to liquidated or actual damages). Delay
and liquidated damages were, however, apportioned in later California decisions.
See, e.g., Nomellini Construction Co. v. Dep’t of Water Resources,
19 Cal.App.3d 240, 96 Cal.Rptr. 682 (3rd Dist. 1971)(where delays in performance
of contract are occasioned by mutual fault and extension of time for delay
clause in contract, court must apportion delay between parties).
In Vrgora v. L.A. Unified School Dist.,
152 Cal.App.3d 1178, 200 Cal.Rptr. 130 (App. 1984), the contractor argued that
the liquidated damages clause should not be enforced because the owner had
beneficial occupancy of a major portion of the building. The court held that
liquidated damages continued to run until the building was fully complete. The
court reasoned that because liquidated damages presume the inability of the
parties to calculate actual damages, it could not apportion an unknown amount of
damages. The result was that although a major portion of the building was
occupied by the owner, the full amount of liquidated damages continued to run.
See also London Guarantee & Accident Co., Ltd. v. Las Lomitas School Dist.,
191 Cal.App.2d 423, 12 Cal.Rptr. 598 (App. 1961)(liquidated damages in public
contract run until “actual” completion, not “substantial” completion;
architect’s certification of completion conclusive as to date of actual
completion) accord Taos Construction Co. v. Penzel Construction Co., Inc.,
750 S.W.2d 522 (Mo. 1988)(although traffic was using bridge, where erosion
control not completed, liquidated damages continued to accrue); Ledbetter
Bros., Inc. v. North Carolina Department of Transportation, 68 N.C.App.
97,314 S.E.2d 761 (1984). Note that Illinois law holds the opposite. See,
e.g., Stone v. City of Arcola, 181 Ill.App.3d 513,536 N.E.2d 1329
(1989)(liquidated damages on public projects cease at substantial completion).
Federal courts also hold that liquidated damages stop on substantial completion.
See, e.g., Appeal of Mitchell Engineering & Construction Co., ENG BCA No.
3785 (April 4, 1989)(liquidated damages cease when project available for its
intended purpose).
Finally, some courts have held that liquidated
damages cannot be assessed if the contractor abandons the project. See, e.g.,
City of Elmira v. Larry Walter, Inc., 76 N.Y.2d 45, 564 N.E.2d 655, 563
N.Y.S.2d 45 (1990)(liquidated damages clause operates only to situation where
contractor fails to complete on schedule, not to abandonment). Therefore, in the
case of abandonment, the owner is entitled to recover actual damages. Other
jurisdictions are to the contrary. See, e.g., Pacific Employers Ins. Co. v.
City of Berkeley, 158 Cal.App.3d 145, 204 Cal.Rptr. 387 (l984)(performance
surety liable for. liquidated damages notwithstanding abandonment by principal).
F. RECOVERABILITY OF DELAY DAMAGES AND
LIQUIDATED DAMAGES UNDER PERFORMANCE AND PAYMENT BONDS
The general rule regarding sureties and their
principals is that the surety’s liability is coextensive with that of its
principal, at least up to the penal sum of the bond. See, e.g., Arbor Club of
Boca Raton, Inc. v. Omega Construction Co., 565 So.2d 357 (Fla.App. 1990)review dismissed, Transamerica Ins. Co. v. Arbor Club of Boca Raton, Inc.,
576 So.2d 294 (Fla. 1990). Although there is a strong opposite view, the
majority rule is that if a default by the principal delays the project, the
performance surety can be held-liable for liquidated damages stipulated in the
contract. See, e.g., Riva Ridge Apts. v. Robert G. Fisher Co., 745 P.2d
1034 (Colo.App 1987); c.f., American Home Assurance Co. v. Larkin General
Hospital, Ltd., 593 So.2d 195 (Fla. 1992)(performance bond required
surety to complete project only, not liable for delay damages); Asphalt
Paving Co. v. United States Fidelity and Guaranty Co., 671 P.2d 1013
(Colo.App. 1983)(surety liable for actual labor and equipment costs in excess of
subcontract balance only).
A surety’s liability for delay damages or
liquidated damages is almost certain if the performance bond includes an
incorporation clause that places the requirements of the contract on the surety.
See, e.g., Pacific Employers Ins. Co. v. City of Berkeley, 158 Cal.App.3d
145, 204 Cal.Rptr. 387 (App. 1984)(although performance bond does not
necessarily encompass liability for liquidated damages, if bond incorporates
contract which expressly calls for liquidated damages, surety is liable).
However, if the owner makes final payment to the contractor, it loses the right
to recover liquidated damages against the performance surety. County of
Dauphin v. Fidelity and Deposit Co. of Maryland, 770 F.Supp. 248 (M.D.Pa.
1991).
The language of the performance bond on a private
project can be determinative of the scope of the bond. See, e.g., Bossier
Medical Properties v. Abbott and Williams Construction Co., 557 Sc.2d 1131
(La.App. 1990)(language that surety shall indemnify and hold owner harmless from
all costs or damage resulting from principal’s default held to cover lost rent).
As to public works performance bonds, however, the statute is often read into
the bond and controls its scope. See, e.g., State Highway Administration v.
Transamerica Insurance Co., 278 Md. 690, 367 A.2d 509 (1976).
On multiple-prime projects, one contractor may
not have any right to make a against another contractor’s performance bond
because it is not usually named as an obligee. See, e.g., M.G.M. Construction
Corp. v. New Jersey Educational Facilities Authority, 220 N.J.Super. 483,
532 A.2d 764 (N.J.Super. 1987); c.f. Aetna Casualty & Surety Co. v. Doleac
Electric Co., 471 So.2d 325 (Miss. 1985)(performance surety can be held
liable to other prime contractors due to delay by its principal via third-party
beneficiary principles). At least one court has held that a subcontractor could
make a claim against a joint venture’s payment bond although it had a contract
only with one of the joint venturers. Seaboard Surety Co. v. Richard F.
Kline, Inc., 91 Md.App. 236,603 A.2d 1357 (Md.App. 1992).
A subcontractor with a delay damage claim should
consider making a claim against the contractor’s payment bond. The Miller Act,
40 U.S.CA. § 270(b), requires the issuance of payment bonds for all federal
public projects in excess of $25,000. The purpose of this statutory bond is to
protect those who furnish labor and materials on federal jobs. Early decisions
under the Miller Act held that delay damages are not recoverable against a
Miller Act payment bond. See, e.g., McDaniel v. Ashton-Mardian Co., 357
F.2d 511 (9th Cir. 1966); L.P. Friestedt v. U.S. Fireproofing Co., 125
F.2d 1010 (l0th Cir. 1942); U.S. v. Guy H. Tames Construction Co., 390 F.
Supp. 1193 (N.D. Tenn. 1972), aff'd 489 F.2d 756, (6th Cir. 1973);
U.S. v. Santa Fe Engineers, 515 F. Supp. 512 (D. Colo. 1981); and
W.S.A., Inc. v. Stratton, 680 F. Supp. 375 (S.D. Fla. 1988)(construing
Florida’s version of Miller Act).
The district court in the W.S.A., Inc.
case gave a good summary of the reasoning behind not allowing damages for delay
to be collected from a Miller Act payment bond:
There is no indication of any
intention to hold the surety liable for damages caused by delay. The clear
language of the payment bond states the surety is liable for only labor,
materials and supplies. The same holds true for the statute itself. Because
there is no intention in either the statute or this bond in particular, to
the contrary, the surety should not be liable for the damages caused by the
negligence of the principal in causing the delay. “Labor” and “material”
should not encompass damages for breach of contract.
W.S.A., Inc., 680 F. Supp. at
377.
More recently, however, courts are holding that
delay damages are recoverable from a Miller Act payment bond. The trend started
in the District of Columbia, U.S. ex rel. Otis Elevator Co. v. Piracci
Construction Co., Inc., 405 F. Supp. 908 (D. D.C. 1975); U.S. ex rel.
Mariana v. Piracci Construction Co., Inc., 405 F. Supp. 904 (D.D.C. 1975);
adopted by the Circuit court of the District of Columbia, U.S. v. William S.
Klingensmith, Inc., 670 F.2d 1227 (D.C. Cir. 1982); and began to branch out
to the other circuits such as in U.S. ex rel. Pertun Construction v.
Harvestor’s Group, Inc., 918 F.2d 915 (11th Cir. 1990). These
decisions have been based on the broad purpose of the Miller Act which is to be
liberally construed and applied. F.D. Rich, Co., Inc. v. U.S. ex rel.
Industrial Lumber Co., Inc., 417 U.S. 116 (1974). Further, the language of
the Miller Act itself states that the bond is liable for any “sum or sums justly
due.” 40 U.S.C. § 270 (B)(a).
The language of the 11th Circuit in the Pertun
Construction Co. case summarizes the reasoning of allowing recovery for
delay damages:
Surety liability for out-of-pocket
costs of delay is consistent with both the language and -the purpose of the
Miller Act. The statute provides for recovery of the costs of labor and
materials furnished or used by the subcontractor in performing contractual
obligations. Only by allowing a full recovery of these costs, including
those portions caused by delay, can the purpose of the statute --to afford
the subcontractor the financial protection of an action against the surety
--be achieved. If the surety is not liable for the portion of costs caused
by delay, the subcontractor will either have to bear the burden himself or
rely on his remedy for breach of contract against the prime contractor. And
it was Congress’s view of the inadequacy of these very alternatives to
assure full payment for labor and materials actually supplied to a federal
project that prompted the enactment of the Miller Act.
Id. 918 F.2d at 918. See, also, General
Federal Construction, Inc. v. D. R. Thomas, Inc., 52 Md.App. 700, 451 A.2d
1250 (1982). Subsequently, the Fifth Circuit Court of Appeals has followed the
Eleventh Circuit. U.S. ex rel. Lochridge-Priest, Inc. v. Con-Real Support
Group, Inc., 950 F.2d 284 (5th Cir. 1992). In Lochridge, the Fifth
Circuit held that the subcontractor can recover if it can show the damages
represented the actual increased cost of labor and materials due to the delay.
The Ninth Circuit recently joined the Fifth and
Eleventh Circuits in allowing recovery for delay against a Miller Act payment
bond. MAI Steel Service, Inc. v. Blake Construction Co., 981 F.2d 414
(9th Or. 1992). The Ninth Circuit distinguished its earlier holding in
McDaniel on its facts and held that a subcontractor could recover from the
Miller Act surety “all ... increased labor and material costs resulting from
construction delays for which it is not responsible, even if those delays are
caused by someone other than the general contractor.” MAI Steel, 981 F.2d
at 420. Note, however, the court specifically listed the recoverable items -
labor and material costs - and did not include indirect delay damages such as
increased home office overhead, interest on retention, claimed lost profits,
etc. See also U.S. ex rel. T.M.S. Mechanical Contractors, Inc. v. Miller
Mutual Fire Ins. Co. of Texas, 942 F.2d 946 (5th Cir. 1991)(payment bond not
liable for termination for convenience costs).
Other courts distinguish delay damages and
damages stemming from the general contractor’s breach of contract. In U.S. ex
rel. Moran Towing Corp, v. Hartford Accident & Indemnity Co., 204 F. Supp.
353 (D.R.I. 1962), the district court stated:
It is generally held that bonds
furnished under the Miller Act are to be liberally construed . . . In
accordance with this rule, the courts have construed said Act liberally to
allow recovery upon bonds provided thereunder . . . . But despite this
liberal construction, it is generally held that a subcontractor has no
remedy against the surety on a Miller Act bond for the recovery of damages
caused by the negligence of the prime contractor, the principal on such
bond. . . . Similarly, while a subcontractor may undoubtedly maintain an
action against the prime contractor for loss of profits caused by the
latter’s breach of contract, the courts hold that he may not maintain such
an action against a surety on the prime contractor’s bond furnished under
the Miller Act ....
However, there is a distinction
between a claim for the value of labor and materials furnished by a
subcontractor in the prosecution of the work as a result of the breach or
default in the performance of his contract by the prime contractor, and a
claim for damages for the breach of such a contract. Where the claim
asserted is for the value of labor and materials furnished, the
subcontractor may maintain an action against the surety on such a bond.
Id. at 355-356.
It has been argued that because state public
works payment bonds guarantee “payment,” not performance, and are a substitute
for the state’s mechanic’s lien laws, the payment bond surety should not be
liable for full performance of every subcontract obligation but only for labor
and materials provided to the project. To the extent that a subcontractor wishes
to recover delay damages on a state public works payment bond, the language of
the statute often plays a key role. See, e.g., Salvino Steel & Iron Works,
Inc. v. Fletcher & Sons, Inc., 398 Pa.Super. 86,580 A.2d 853 (Pa.Super.
1990)(statutory language covered materials furnished or labor performed, not
storage costs due to delay of prime). The scope of a statutory payment bond is
measured by the statute under which it is issued. See, e.g., Wichita Sheet
Metal Supply, Inc. v. Dahlstrom & Ferrel Construction Co., 246 Kan. 557,
Ms.792 P.2d 1043 (1990)(statute read into the bond; missing provisions included
and restrictive provisions that conflict with the statute are read out). At
least one state has allowed a subcontractor to recover delay damages against a
statutory payment bond. See, e.g., General Federal Construction, Inc. v. D.R.
Thomas, Inc., 52 451 A.2d 1250 (Md.App. 1982)(Maryland’s Little Miller Act
payment bond construed similar to federal Miller Act bond; recovery for delay
damages allowed).
In conclusion, the authors suggest that owners,
contractors, subcontractors, design professionals and all others involved with
the construction process should be prepared for delay claims which will
inevitably arise. In today’s construction industry, even the smallest mistakes’
can ripple into big delays in project completion. The axiom “time is money” is
particularly true in construction --delay is costly and ultimately someone must
bear that cost. Hopefully, this paper has shed some light on the nature and
extent of damages that are recoverable when a construction project is delayed.
u
This article was co-authored by Edward Rubacha. |