Jay M. Mann, Esq. and Patrick F. Welch, Esq.
Problems and
Pitfalls Handling AIA Bond Claims
While
the A312-2010 bond forms have many good qualities and are a big improvement over
predecessor AIA bonds and many other bond forms in use today, the potential for
liability exceeding the penal sum is a serious problem for the surety under the
A312-2010 Performance Bond.
This article was
prepared in conjunction with a 2011 continuing
education presentation for surety
claims departments.
I. Introduction
In 1970, The
American Institute of Architects (“AIA”) released its landmark AIA Document A311
bonds – Performance Bond and Labor and Material Payment Bond (“A311-1970
Performance Bond” and “A311-1970 Payment Bond”). Thereafter, in 1984, the AIA
released its AIA Document A312 bonds – Performance Bond and Payment Bond
(“A312-1984 Performance Bond” and “A312-1984 Payment Bond”). The most recent
version of AIA bonds, released in 2010, are the A310-2010 Bid Bond and the
A312-2010 Bonds – Performance Bond and Payment Bond (“A312-2010 Performance
Bond” and “A312-2010 Payment Bond”). Since these bond forms are, by far, the
most commonly used bonds in the surety industry, surety claims professionals
closely track how courts have interpreted the bond coverage provisions
(including conditions precedent to coverage, limitations upon coverage, notice
provisions and recoverable damages). Trends have emerged from these court
decisions, in some cases correct interpretations and in other cases clearly
wrong interpretations of the bonds. More troubling for sureties, there is yet
another category of conflicting court decisions leading to uncertainty as to
surety liability exposure under particular AIA bonds.
The need for
clarity, and even more important for consistency in court rulings interpreting
the bonds, is what led the AIA to undertake the major project of updating its
A312 bond forms. Revision of the A312 bond forms began in April 2009 and was the
collaboration of many leading construction industry organizations, including the
American Bar Association Forum Committee on the Construction Industry, the
Associated Builders & Contractors, the American Subcontractors Association, the
Associated General Contractors of America, the Associated Specialty Contractors,
the Construction Owners Association of America, the National Association of
Surety Bond Producers, the Surety & Fidelity Association of America, the
National Society of Professional Engineers, the American Council of Engineering
Companies, the American Insurance Association, the Engineers Joint Contract
Documents Committee, and the American College of Construction Lawyers. The long
wait for the new bond forms ended on June 10, 2010 when the AIA released the
A310-2010 Bid Bond and A312-2010 Performance and Payment Bonds.
Issuance of the
A312-2010 bond forms does not mean the end to use of the earlier A311-1970 and
A312-1984 bonds. Although the A311 is no longer an official bond form of the
AIA, and the A312-1984 is being phased out at the end of 2011 by the AIA (an 18
month long transition to the A312-2010 bond forms), all sureties who are members
of the Surety & Fidelity Association of America (“SFAA”) may use current and
prior bond forms (and even put the bond forms on their own letterhead) under a
license agreement with the AIA. But the real reason for continued use of the
older bond forms is that owners and their design professionals continue to
specify these bond forms and, as a consequence, sureties continue to issue the
older bond forms. It is thus important for surety claims professionals to
understand the nuances of coverage under all three sets of AIA bond forms.
Attached as
exhibits are the bond forms which will be discussed in this article:
-
The
A311-1970 Performance Bond and Payment Bond are Exhibit “1.”
-
The A312-1984
Performance Bond and Payment Bond are Exhibit “2.”
-
The AIA Amendment to
A312-1984 Payment Bond (May 2008) is Exhibit “3.”
-
The A310-2010 Bid Bond is
Exhibit “4.”
-
The A312-2010 Performance Bond and Payment Bond are Exhibit
“5.”
-
Also attached as Exhibit “6” is a document entitled “AIA Bond Form
Commentary and Comparison,” a paper published by the AIA to explain the 2010
bond forms to the construction industry.
This article will
examine coverage under each of the bonds, however this article will not be an
in-depth discussion of all coverage issues which may arise under these bonds.
Rather, this article will focus upon those bond provisions which have led to
conflicting and sometimes erroneous court decisions – in other words, those
provisions that cause the most problems for the surety’s handling of bond
claims. Because the A312-2010 bonds are so new, there are no reported cases on
these bonds as of date of this article. But this article will examine how the
AIA resolved, in its new bonds, coverage issues that had arisen under its prior
bonds. As stated above, the A312-2010 bonds are the product of a massive
collaborative effort by many construction industry organizations; the result is
a series of bond forms which are clearer and contain less ambiguities then the
AIA predecessor bonds. The hope, of course, is that improved drafting of the new
bonds will lead to less coverage misinterpretations by the courts. The negative
from the surety’s perspective, also to be discussed below, is that important
surety rights and defenses were sacrificed in negotiations with other trade
groups which resulted in the new bonds. Bottom line, in the authors' opinion,
is that the surety industry lost ground in exchange for clarity (or at least
better clarity) as to coverage under the A312-2010 bonds.
II. A311-1970 BONDS
Not so long ago, the
A311-1970 Performance Bond was the workhorse of the surety industry. However,
with the introduction of the longer form A312-1984 Performance Bond, the surety
industry chose to less frequently use the A311-1970 Performance Bond.
Notwithstanding its decreased popularity, the A311-1970 Performance and Payment
Bonds are still often issued on current projects by owners and their design
professionals, and so sureties must still adjust claims made against these
bonds.
The A311-1970
Performance Bond is an old fashioned bond form which is short, skimpy on details
and relies upon common law and/or case law to determine rights and obligations
of the parties thereto. The A311-1970 Payment Bond has a few more details than
its Performance Bond counterpart. But both bonds are written in archaic language
and coverage under both bonds is described in the negative (“If Contractor shall
promptly and faithfully perform said Contract, then this obligation shall be
null and void.”). As a practical matter, the reader has to know what the
intended coverage is and then work backwards to determine the extent of the
surety’s obligations under these bonds.
Whether the operative
language of the A311-1970 Performance Bond creates a condition precedent to the
surety’s performance has been a critical issue as courts have struggled to
construe this bond form. The particular language in this bond, which has been
the subject of hotly debated court decisions, is as follows:
KNOW ALL MEN BY THESE PRESENTS, that
(A) _______________, as Principal,
hereinafter called Contractor, and _________________, as Surety, hereinafter
called Surety, are held and firmly bound unto ___________, as Obligee,
hereinafter called Owner, in the amount of $__________ . . .
(B) WHEREAS, Contractor has…entered
into a contract with Owner . . ., which Contract is by reference made a part
hereof, . . .
NOW THEREFORE, THE CONDITION OF THIS
OBLIGATION IS SUCH THAT, if Contractor shall promptly and faithfully perform
said Contract, then this obligation shall be null and void; otherwise it shall
remain in full force and effect.
* * *
(C) Whenever Contractor shall be, and
declared by Owner to be in default under the Contract, the Owner having
performed Owner’s obligations thereunder, the Surety may promptly remedy the
default, or shall promptly
(1) Complete the
Contract in accordance with its terms and conditions, or
(2) Obtain a bid
or bids for completing the Contract…and make available as Work progresses . . .
sufficient funds to pay the cost of completion less the balance of the Contract
price…
Conditions
precedent to bond coverage, such as the declaration of default condition quoted
above, are extremely important to the surety’s handling of a performance bond
claim. Until a bond’s conditions precedent are satisfied, the surety’s
obligations have not been triggered and so the surety does not have the right to
take over the bonded project or even discuss project issues with subcontractors
and other project participants. Indeed, the surety can face liability for
tortious interference with the contractor’s business relations if it acts too
early. U.S. Fid. & Guar. Co. v. Braspectro Oil Servs. Co., 369 F.2d 34, 51 (2nd Cir.
2004). On the other hand, if the surety waits too long to act, it may face
significantly higher liability exposure due to worsening conditions at the
bonded project.
Unfortunately,
the case law has been conflicting as to what is meant by the above-quoted
default language of the A311-1970 Performance Bond – therefore, there is
uncertainty as to when the default condition precedent of the bond has been
satisfied. The leading case decision for the surety, construing the default
condition of the A311-1970 Performance Bond, is L&A Contracting Co. v. S.
Concrete Serv., Inc., 17 F.3d 106, 111 (5th Cir. 1994). In L&A
Contracting, the Fifth Circuit Court of Appeals observed that “the bond in
this case imposes liability on [the surety] for [its bond principal’s] breach
only if two conditions exist. First, [the bond principal] must have been in
default of its performance obligation under the subcontract. Second, [the
bond obligee] must have declared [the bond principal] to be in default.”
As to what
constitutes a sufficient declaration of default to invoke the surety’s
obligation under the A311-1970 Performance Bond, the L&A Contracting
Court provided a bright-line rule of coverage. In clear and unequivocal
language, “the declaration must inform the surety that the principal has
committed a material breach or a series of material breaches of the subcontract,
that the obligee regards the subcontract as terminated, and that the
surety must immediately commence performing under the terms of the bond.” L&A
Contracting, 17 F.3d at 111 (emphasis added).
In the years
since the Fifth Circuit handed down its decision in L&A Contracting, many
courts have embraced the Fifth Circuit’s reasoning and likewise held that the
operative language of the A311-1970 Performance Bond creates condition
precedents to a surety’s performance obligations. See N. Am. Specialty Ins.
Co. v. Ames Corp., No. 08-80966-CIV, 2010 WL 1027866, at *6-8 (S.D. Fla. May
18, 2010) (granting summary judgment in favor of surety where bond obligee’s
letters to surety failed to declare bond principal in default, which is a
condition precedent to the surety’s performance bond obligation); Hunt
Constr. Group, Inc. v. Nat’l Wrecking Corp., 587 F.3d 1119, 1122 (D.C. Cir.
2009) (affirming district court’s grant of summary judgment in favor of surety
on the ground that “the requirements listed in Paragraph C are properly read as
true conditions precedent, in the absence of which the surety has no liability
on the bond”); CC-Aventura, Inc. v. Weitz Co., LLC, No. 06-21598-CIV,
2008 WL 2937856, at *3-4 (S.D. Fla. July 14, 2008) (no dispute that bond obligee
was required to provide notice of bond principal’s default in order to recover
performance bond); Current Builders of Florida, Inc. v. First Sealord Sur.,
Inc., 984 So.2d 526, 529-31 (Fla. Dist. Ct. App. 2008) (affirming trial
court’s denial of motion for new trial on the ground that bond obligee failed to
provide notice of bond principal’s default to surety); Elm Haven Constr. Ltd.
P’ship v. Neri Constr. LLC, 376 F.3d 96 (2d Cir. 2004) (affirming summary
judgment in favor of surety and recognizing that “[in] order to trigger
[surety’s] liability under the performance bond, two conditions had to be met.
First, [the bond principal] had to be ‘in default’ under the subcontract
agreement, and second, [the bond obligee] has to ‘declare [the principal] to be
in default under the’ subcontract agreement”); Balfour Beatty Constr., Inc.
v. Colonial Ornamental Iron Works, Inc., 986 F. Supp. 82, 85-86 (D. Conn.
1997) (“[p]erformance bond requirements for notice of default and demand that
surety step in and perform under the bond must be met before an obligee can
recover under the performance bond); Ins. Co. of N. Am. v. Metro. Dade County,
705 So.2d 33, 35 (Fla. Dist. Ct. App. 1998) (holding that bond obligee’s
“failure to comply with [the] bond’s notice provisions stripped the surety of
its bargained for right and relieved the surety of its liability”); Dragon
Constr., Inc. v. Parkway Bank & Trust, 287 Ill.App.3d 29, 33-34, 678 N.E.
55, 57-58, 222 Ill.Dec. 648,650-51 (Ill. Ct. App. 1997) (holding that the
“[obligee’s] failure to provide adequate notice of [bond principal’s]
termination and their hiring of a successor contractor before [surety] received
the late notice stripped [surety] of its right to limit its liability and
constituted a material breach of contract which rendered the surety bonds null
and void”). All of these cases share a common holding: unless and until the bond
obligee declares a default in clear and unequivocal language and terminates the
bonded contract, the surety is not obligated to perform under the A311
Performance Bond.
On the opposite
end of the spectrum are those case decisions that expressly reject the reasoning
of L&A Contracting and its progeny and hold that the operative language
of the A311-1970 Performance Bond does not create conditions precedent to a
surety’s performance obligations. The leading case against the surety is
Colorado Structures, 161 Wash.2d 577, 167 P.3d at 1125 (Wash. 2007), in
which the Washington Supreme Court expressly rejected the reasoning of the Fifth
Circuit in L&A Contracting and held that the bond obligee was not
required to formally declare the bond principal in default before the surety’s
liability on its A311-1970 Performance bond was triggered. The Colorado
Structures Court went so far as to state that L&A Contracting was
“wrongly decided” declaring that “[t]he linchpin of the L&A court’s
conclusion is its assertion . . . . that the events described in the preamble to
Paragraph C condition not just the use of the remedies described in Paragraph C,
but also the liability described in Paragraph A. To do so, however,
plainly violates the language of the bond.” (167 P.3d at 1128, emphasis in
original).
In Colorado
Structures, the bond obligee/general contractor chose to supplement a bond
principal/subcontractor in order to minimize financial penalties for late
performance. The obligee informed the surety of the subcontractor’s untimely
work, but never terminated the subcontract. At the conclusion of the project, it
was determined that the cost of supplementation exceeded the subcontract
balance, and so the obligee sought recovery under the A311-1970 Performance
Bond. According to the Court, the obligee did not have to meet any condition
precedent for surety liability under Paragraph A of the bond; Paragraph A is
subject to only a single condition subsequent, i.e., the principal’s prompt and
faithful performance. Although the obligee did not sufficiently declare a
default for Paragraph C purposes, the principal was in fact in material default
and so the obligee was entitled to recover from the surety under the Paragraph A
bond coverage.
In the authors'
opinion, the Colorado Structures, case was wrongly decided – to the
extent that it makes use of the A311-1970 Performance Bond potentially dangerous
for a surety. The bond was never intended to provide two alternative paragraphs
of coverage to the bond obligee; this is a fiction, or at best a misreading, by
the Colorado Structures court. The effect of this ruling is that the
surety is deprived of any opportunity to minimize damages caused by a
misperforming principal – the surety cannot take over the project until the
principal is terminated by the obligee, so it must wait while the principal
continues to misperform and thus build upon the damages for which the surety
will ultimately be liable to the obligee. This is not the risk which the surety
assumed when the Performance Bond was written, and greatly increases the
surety’s liability exposure. Fortunately, this very serious coverage
interpretation problem was corrected by the AIA in the A312 bonds.
Notwithstanding that
Colorado Structures was wrongly decided, a number of courts in various
jurisdictions have chosen to follow the Colorado Structures holding and
rule against the surety (although not always following the extreme
surety-adverse dicta of the Colorado Structures opinion). Nova
Casualty Co. v. Turner Construction Co., No. 14-09-00733-CV, 2011 WL 480599
at *4-5 (Tex. Ct. App. Feb. 10, 2011) (obligee entitled by subcontract to
supplement principal subcontractor and charge surety with excess cost, without
termination of subcontract or notice to surety); RLI Ins. Co. v. St.
Patrick’s Home for the Infirm and Aged, 452 F. Supp.2d 484, 488 (S.D.N.Y.
2006) (distinguishing Elm Haven on the ground that “unlike the bonds at
issue in [Elm City and like cases], the performance bond in this case
does not include an explicit notice requirement”); Walter Concrete Constr.
Corp. v. Lederle Lab., 99 N.Y.2d 603, 605, 788 N.E. 2d 609, 610, 758
N.Y.S.2d 260, 261 (N.Y 2003) (holding that “[u]nlike the AIA-312 bond …. an
action on the AIA-311 bond is not tied to a declaration of default, the
principal’s cessation of work or the surety’s refusal to perform under the bond
…. Had the parties to the contract desired notice as a precursor to liability
under the bond, they would have elected to issue a more specific AIA-312 ….”);
DCC Constructors, Inc. v. Randall Mech., Inc., 791 So.2d 575, 576-77
(Fla. Dist. Ct. App. 2001) (holding that “[t]here is no language in the
performance bond …. which requires termination of the subcontract as a condition
precedent to [the surety’s] obligations”); Menorah Nursing Home, Inc. v.
Zukov, 153 A.D.2d 13, 21-22, 548 N.Y.2d 702, 708 (N.Y. App. Div. 1989)
(rejecting surety’s argument that action against surety should be dismissed
because the bond obligee failed to declare principal in default under the
subcontract on the ground that “the bond contains no provision which expressly
requires a notice of default as a condition precedent to any legal action on the
bond”); Dooley and Mack Constructors, Inc. v. Developers Sur. And Indemn. Co.,
972 So. 2d 893 (Fla. Dist. Ct. 2007) (obligee has option to complete the bonded
work and hold the surety liable for all damages and expenses, without notifying
surety because notice not required under the bonded subcontract).
There is a clear split
of authority around the country on this very important point of coverage, and it
is difficult to predict whether L&A Contracting or Colorado Structures
will be the prevailing view in a jurisdiction which has not yet addressed
this issue in a reported decision.
A related, but
distinctly different, issue is the surety’s defense when the obligee fails to
give prompt notice to the surety or otherwise fails to promptly act upon default
by the principal contractor. Blackhawk Heating and Plumbing Co. v. Seaboard
Surety Company, 534 F. Supp. 309 (N.D. Ill. 1982) involved a performance
bond similar to the A311-1970 bond form. The principal/subcontractor’s work was
untimely, yet the obligee/general contractor did not declare a default and call
upon the bond for what the surety contended was an unreasonably long period of
time. The court agreed with the surety and allowed a defense to the performance
bond claim – to the extent that the surety could prove delay in notice by the
obligee prejudiced the surety and added to the surety’s costs of completion.
Other courts have also ruled that the surety has a pro tanto defense,
i.e., to the extent of prejudice, for late notice by the obligee. Plowden and
Roberts, Inc. v. Conway, 192 So.2d 528 (Fla. Ct. App. 1966); Bayer and
Mingolla Construction Co. v. Deschenes, 348 Mass. 594, 205 NE.2d 208 (Mass.
1965). This defense due to the obligee’s failure to give prompt notice (really a
mitigation of damages defense) is in sharp contrast to the defense due to the
obligee’s failure to meet bond conditions precedent. The former is to the extent
of defense and places the burden of proving prejudice (sometimes a highly
difficult burden to meet) on the surety; the latter is a full defense for the
surety regardless of the extent (or even the absence) of prejudice.
Turning to other
coverage issues under the A311-1970 Performance Bond, the bond does not
explicitly address whether delay damages/liquidated damages are recoverable and
again there is a split in the cases interpreting this bond. In the leading
surety-favorable case, American Home Assurance Co. v. Larkin General
Hospital, Ltd., 593 So.2d 195, 196 (Fla. 1992), the court held that “a
surety cannot be held liable for delay damages due to the contractor’s default
unless the bond specifically provides coverage for delay damages.” See
Downington Area School District v. International Fidelity Insurance Co., 769
A.2d 560, 565-66 (Pa. 2001). On the other hand, the court in Cates
Construction, Inc. v. Talbot Partners, 980 P.2d 407 (Cal. 1999) held a
surety liable for delay damages under the A311-1970 Performance Bond due to the
bond language “…including other costs and damages for which the Surety may be
liable.” There is no clear answer as to whether actual delay damages or
liquidated damages are recoverable against an A311-1970 Performance Bond in a
jurisdiction which has not addressed this issue – a problem of lack of clarity
in the bond form which was corrected (although not in the surety’s favor) in the
A312 bond forms.
Another troubling
issue in the A311-1970 bond form is when the bond limitations period has
expired. The limitations period of the A311-1970 Performance Bond provides as
follows:
Any suit under this bond must be
instituted before the expiration of two (2) years from the date on which final
payment under the Contract falls due.
While no case law was
found directly addressing the limitations clause of the A311-1970 Performance
Bond, there have been quite a few cases which considered similar clauses in
other bond forms setting limitations deadlines triggered by when final payment
to the bond principal became due. As examples are a series of New York opinions
which have reached inconsistent holdings. In Clyde-Savannah Cent. Sch. Dist.
v. Naitzker, Thorsell & Dove, 73 AD 2d 810 (NY App. Ct. 1979), a subcontract
bond stated suit could be filed no later than two years from the date final
payment became due. The court turned to the subcontract and determined final
payment required acceptance of subcontractor’s work by the owner and/or the
architect. Despite the fact that payment was actually made more than two years
before suit on the bond was filed, the surety’s limitations defense was rejected
because there was no evidence of acceptance of subcontractor’s work by the owner
or architect. On the other hand, in a more recently decided New York case
involving similar facts, Yeshava Uni v. Fid. and Deposit Co. of Maryland,
116 AD 2d 49, 500 NYS 2d 241 (NY App. Ct. 1986), the court accepted the surety’s
limitations defense because the subcontractor had been paid and the
owner/architect’s acceptance was implied by taking occupancy of the building.
Both of the above New
York cases involved claims for latent defects in performance discovered after
the project was completed. In yet a third New York latent defect case, Town
of Esopus v. Brinnier and Larios, 135 AD 2d 935, 522 NYS 2d 337 (NY App. Ct.
1987), the court approved the surety’s limitations defense and dismissed the
surety, notwithstanding the obligee/ owner’s position that principal/contractor
had covered up its defective sewer work and so final payment was fraudulently
induced. The Yeshava opinion was cited approvingly, and it is fair to say
that Yeshava is now the prevailing view in New York.
In BDI Const. Co.
v. Hartford Fire Ins. Co., 995 So.2d 576 (Fla. Dist. Ct. App. 2008), the
applicable Florida five-year limitations period ran from when final payment was
due to the principal/subcontractor. Rejecting the general contractor’s argument
that final payment never really became due to the subcontractor because of its
defective stucco and drywall work, the court ruled that the limitations period
ran from when final payment to the subcontractor was actually made. In agreement
with BDI are Fed. Ins. Co. v. Southwest Florida Retirement Center,
Inc., 707 So.2d 1119 (Fla. 1988) (Florida Supreme Court ruled bond
limitations period ran from date of acceptance of construction) and La
Liberti, LLC v. Keating Building Corp., 2007 WL 4323687 (E.D. Pa. Dec. 11,
2007) (bond limitations period ran from date of final payment to principal
subcontractor). On the other hand, for a case which follows the
Clyde-Savannah reasoning, see Hagerstown Elderly Assoc. Ltd. P’ship v.
Hagerstown Elderly Building Assoc. Ltd. P’ship, 368 Md. 351, 793 A.2d 579
(Md. Ct. App. 2002) (court looked to bonded contract and determined final
payment did not become due until a loan closing had occurred). Although these
cases are irreconcilable as to the event which triggers the running of the bond
limitations period, there is consensus on one important point: no distinction is
made between patent and latent claims and courts do not apply a discovery
exception to the time limitations requirement of the A311-1970 or similar form
performance bonds.
As another point of
discussion regarding bond limitations clauses, it must be remembered that many
states have statutorily prescribed the minimum period for suits to be filed on
insurance claims (including surety bond claims) and attempts to shorten the
minimum time period are invalid. See, e.g., Conn. Gen. Stat. § 38a-290
(2010) (minimum time limit to bring suit on performance bond in Connecticut is
three years from date principal last performed work); 8 V.S.A. § 3663 (2010)
(limitations period of less than twelve months to file suit on performance bond
from date of default is null and void as against public policy in Vermont;
A.R.S. § 20-1115(A)(3) (in Arizona, time within which an action must be brought
on an insurance claim, including a bond claim, cannot be less than two years
after cause of action accrues); S.D. Codified Laws § 53-9-6 (2010) (for
time to enforce surety contract to be valid in Texas, the time period cannot be
less than two years after the cause of action has accrued). The point is that it
is not sufficient for the surety claims handler to simply apply the limitations
clause found in the A311-1970 Performance Bond or any other bond form – the law
of the jurisdiction in which the bond is issued must be reviewed to determine if
the bond limitations clause is enforceable.
Finally, regarding
limitations clauses contained in bonds, the rogue case of City of Santa Fe v.
Travelers Casualty & Surety Company, 228 P.3d 483 (N.Mex. S. Ct. 2010) must
be discussed. This case involved an A312-1984 Performance Bond, but its holding
is equally applicable to the A311-1970 Performance Bond. In this case, an
A312-1984 Performance Bond was issued on behalf of a general contractor for a
City of Santa Fe public project. Although the bonded contract was silent as to
time to sue and so was subject to a six-year statute of limitations, the bond
contained a two-year limitations clause. The New Mexico Supreme Court ruled that
the two year limitations clause in the bond was not binding on Santa Fe, because
Santa Fe had not “agreed” to the shorter time period of the bond. Although it
would not have violated public policy for Santa Fe to make this agreement, the
Court held such agreement could not be implied from Santa Fe’s acceptance of the
bond prior to commencement of construction. Thus the surety Travelers was bound
to a six-year, not a two-year, time period to sue on the performance bond. No
authority was cited by the Court for its bizarre holding. While unprecedented,
this case is the law in New Mexico. Accordingly, sureties issuing bonds in New
Mexico are advised (if feasible) to get public and private obligees to actually
sign issued bonds indicating their approval of the terms and conditions therein;
otherwise there will be uncertainty as to enforceability of limitations clauses
and perhaps other bond provisions.
III. A312-1984 BONDS
Since its release by
the AIA, the A312-1984 Performance Bond has been the surety industry’s
preeminent performance bond form. In contrast to the A311-1970 Performance Bond,
the A312-1984 Performance Bond is a long bond form which provides obligees,
principals and sureties with a “roadmap” explicitly detailing each parties’
rights and obligations under the bond (including important condition precedents
that must occur before the surety’s performance bond obligations are triggered).
The A311-1970 bond is a short form bond and the A312-1984 is a long form bond.
When the AIA undertook its update project in 2009, it expressly decided not to
include a short form performance bond in its revised series and instead opted to
only update its long form A312-1984 bond.
A. Conditions Precedent to Surety’s Obligations
The pertinent
condition precedent language of the A312-1984 Performance Bond is as follows:
3. If
there is no Owner Default, the Surety’s obligation under this Bond shall arise
after:
3.1
The
Owner has notified the Contractor and the Surety at its address described in
Paragraph 10 below that the Owner is considering declaring a Contractor Default
and has requested and attempted to arrange a conference with the Contractor and
the Surety to be held not later than fifteen days after receipt of such notice
to discuss the methods of performing the Construction Contract. If the Owner,
the Contactor and the Surety agree, the Contractor shall be allowed a reasonable
time to perform the Construction Contract, but such an agreement shall not waive
the Owner’s right, if any, subsequently to declare a Contractor Default; and
3.2
The
Owner has declared a Contractor Default and formally terminated the Contractor’s
right to complete the Contract. Such Contractor Default shall not be declared
earlier than twenty days after the Contactor and Surety have received notice as
provided for in Sub-paragraph 3.1; and
3.3
The
Owner has agreed to pay the Balance of the Contract Price to the Surety in
accordance with the terms of the Construction Contract or to a contractor
selected to perform the Construction Contract in accordance with the terms of
the contract with the Owner.
Notably, consistent with the A312
philosophy of eliminating archaic language previously used in other bond forms,
the parties are referred to in the A312 bonds as “Owner,” “Contractor” and
“Surety.”
As a threshold matter,
it should be noted that there should not be a Colorado Structures
misinterpretation of the A312 bond form. There are not two surety obligation
paragraphs in the A312-1984 Performance Bond, and so there is simply no way to
logically read alternative coverages (one subject to conditions precedent, the
other not subject to conditions precedent) into this bond.
The above-quoted
Paragraph 3 of the A312-1984 Performance Bond requires that the Owner must be in
compliance with its obligations under the bonded contract as a condition to the
Surety’s liability under the bond. Moreover the bond, in Paragraphs 3.1 through
3.3, explicitly provides for three conditions precedent to the Surety’s
liability. Consistent with the express language of Paragraph 3, a majority of
courts from around the country have concluded that Paragraph 3 creates three
condition precedents. See Travelers Cas. And Sur. Co. of Am. v. Crystal
Towers, LLC, No. 08-0518-KD-C, 2009 WL 5068823, at *14-15 (S.D. Ala. Dec.
17, 2009) (granting surety’s motion for summary judgment on breach of contract
claim, recognizing that surety’s duties under Paragraph 4 of the A312
Performance Bond are not triggered until after the conditions precedent in
Paragraph 3 are met); Stonington Water Street Assoc. v. Hodess Building Co.
Inc., 2011 WL 861688 (D. Conn. March 9, 2011) (surety dismissed on summary
judgment because owner failed to follow Paragraph 3 of A312 Performance Bond,
and thus deprived surety of opportunity to mitigate its damages); Klewin
Building Co., Inc. v. Heritage Plumbing & Heating, Inc., 42 A.D.3d 559, 560,
840 N.Y.S.2d 144, 145 (N.Y. 2007) (denying surety’s motion for summary judgment
on the ground that it failed to establish that any of the condition precedents
set forth in Paragraph 3 of the performance bond were not satisfied by the bond
obligee); U.S. Fid. and Guar. Co. v. Braspetro Oil Ser. Co., 369 F.3d 34,
57-61 (2d Cir. 2004) (recognizing that Paragraph 3 of the A312 Performance Bond
contains a number of conditions precedent to the surety’s obligations and
concluding that contrary to the surety’s assertion, the bond obligee did comply
with Paragraphs 3.2 and 3.3); Enter. Capital, Inc. v. San-Gra Corp., 284
F. Supp.2d 166, 179-81 (D. Mass. 2003) (noting that the language of Paragraph 3
does in fact create conditions precedent and concluding that various letters
from bond obligee to surety failed to satisfy the requirements of Paragraph 3.2
that the declaration of default and notice of termination of the bond principal
be clear, direct, and unequivocal); but see Commercial Cas. Ins. Co.
of Georgia v. Mar. Trade Ctr. Builders, 257 Ga.App. 779, 783, 572 S.E.2d
319,322 (Ga. Ct. App. 2002) (rejecting surety’s argument that notice to the
surety of the bond principal’s default was a condition precedent to recovery
under the A312 Performance Bond on the ground that “[t]he plain language of the
executed documents leads to only one reasonable interpretation, that the
contractor was not required to give the surety notice before supplementing the
subcontractor’s labor and material to collect under the performance bond”).
B. Paragraph
3.1 – Notice to Surety and Request for Conference
The first
condition under Paragraph 3.1 requires the Owner to notify the Contractor and
the Surety that the Owner is considering a Contactor Default (a defined term of
the bond), and the Owner requests a conference within 15 days to discuss methods
of performing the construction contract. A majority of case decisions have
strictly enforced the requirements of Paragraph 3.1. See Breath of Life
Christian Church v. Travelers Ins. Co., No. W2009-00284-COA-R3-CV, 2010 WL
1172080, (Tenn. Ct. App. 2010) (affirming trial court award of summary judgment
in favor of surety on action against performance bond and rejecting bond
obligee’s argument that “section three of the bond is merely a notice provision
that should be dispensed with where [surety] had some indication of the
difficulties between [the owner and bond principal]”); Podsiadlo v. W. Ins.
Co., No. C056936 (Super.Ct.No. SC20050080), 2009 WL 2901950, (Cal. Ct. App.
2009) (unpublished opinion) (letter sent by bond obligee to surety advising
surety of the earlier termination of bond principal, which also stated that bond
obligee was willing to meet and confer, did not satisfy the condition precedent
found in Paragraph 3.1); U.S. for Use of Platinum Mech., LLC v. U.S. Sur. Co.,
No. 07 Cv. 3318 (CLB), 2007 WL 4547849, (S.D.N.Y. 2007) (concluding that bond
obligee failed to comply with Paragraph 3.1 where bond obligee did not provide
any evidence in its papers filed in opposition to surety’s motion for summary
judgment that it mailed the notice of default letter to the address provided for
in Paragraph 10 of the bond). However, courts do not require the Owner’s notice
to the Surety to track the precise terminology of Paragraph 3.1. See
CC-Aventura, Inc. v. Weitz Co., LLC, No. 06-21598-CIV, 2008 WL 2557434,
(S.D. Fla. 2008) (concluding that although a letter from bond obligee to surety
“did not use the precise terminology of Paragraph 3.1 in stating it was
‘considering’ declaring a default,” the letter nonetheless created an issue as
to whether the bond obligee fulfilled the condition precedent in Paragraph 3.1);
Developers Sur. and Ind. Co. v. Dismal River Club, LLC, No 4:07CV3178,
2008 WL 2223872, (D.Neb. 2008) (concluding that letter from the surety which did
not use the terminology of Paragraph 3.1, but nonetheless indicated that there
was a Contractor Default, created a jury issue as to whether the bond obligee
effectively fulfilled the conditions of Paragraph 3.1).
Also note that
the United States District Court in RLI Ins. Co. v. Indian River Sch. Dist.,
EDis, 566 F. Supp.2d 356 (D. Del. 2008), applying Delaware state law,
refused to find Paragraph 3.1 of the A312-1984 Performance Bond to be a
condition precedent to the Surety’s obligations on the ground that it
contradicted the Delaware Procurement Act; thus, the Surety’s defense based on
failure of a bond condition precedent was rejected. Another case ruling against
the surety is Carnell Construction Corp. v. Danville Redevelopment & Housing
Authority, Case No. 4:10-cv-7 (W.D. Va. Jan. 27, 2011), in which the owner
prevailed despite not giving required notices under the A312-1984 Performance
Bond because the bonded contract’s HUD General Conditions controlled over the
bond.
C. Paragraph
3.2 – Declaration of Default and Termination
The second
condition precedent under Paragraph 3.2 to the Surety’s performance bond
obligations is that the Owner has “declared the Contractor in default and
formally terminated the Contractor’s right to complete the contract.”
Furthermore, Paragraph 3.2 requires the Owner to wait at least twenty days after
the Contractor and Surety have received notice of the pre-default conference
before declaring such contractor default. Generally, the reported case decisions
construing Paragraph 3.2 of the A312-1984 Performance Bond have applied the
L&A Contracting standard and required that an owner’s declaration of default
must be made in clear, direct, and unequivocal language. Those case decisions
finding the owner’s notice to be insufficient include instances where the notice
merely included threats about declaring a Contractor default, or the owner
actually affirmed the bonded contract. See CC-Aventura, Inc. v. Weitz Co.,
LLC, No. 06-21598-CIV, 2008 WL 2557434 (S.D. Fla. 2008) (concluding that
letter from obligee to surety which reiterated earlier notice of bond
principal’s deficiencies, requested a conference as provided for by Paragraph
3.1, and stated the obligee was willing to consider any proposed resolution
“could not reasonably be interpreted to declare bond principal in default in
clear, direct, and unequivocal language”); Developers Sur. and Ind. Co. v.
Dismal River Club, LLC, No 4:07CV3178, 2008 WL 2223872 (D.Neb. 2008)
(finding that bond obligee failed to comply with Paragraph 3.2 where bond
obligee’s letters to the bond principal and its surety never formally terminated
the bond principal’s right to complete the project); CC-Aventura, Inc. v.
Weitz Co., LLC, 2007 WL 2986371 (S.D. Fla. 2007) (finding that letter from
bond obligee addressed to contactor and surety, which affirmed the contract with
the bonded contractor and indicated that it still looked to the contractor to
perform the contract, did not meet the requirements of Paragraph 3.2); Bank
of Brewton, Inc. v. Int’l Fid. Ins. Co., 827 So.2d 747, 754 (S. Ct. Ala.
2002) (concluding that bond obligee’s notices to surety, which detailed many
threats to declare a contractor default, were insufficient under Paragraph 3.2
because “a mere threat is not sufficient to trigger the obligations of a
surety”). On the other hand are those cases which found the owner’s notice to
have complied with the condition precedent requirement in Paragraph 3.2 and
rejected a surety’s overly technical notice argument. Mid-State Sur. Corp. v.
Thrasher Engineering, Inc., 575 F. Supp.2d 731, 740-43 (S.D. Va. 2008)
(rejecting surety’s overly technical argument that bond obligee’s letter, which
did not expressly state that the bond principal’s right under the contract had
been terminated, failed to meet Paragraph 3.2 requirement to declare the bond
principal to be in default); U.S. Fid. and Guar. Co. v. Braspetro Oil Ser.
Co., 369 F.3d 34, 57-58 (2nd Cir. 2004) (rejecting surety’s argument that
allowing the principal to remain on the project under new financial arrangements
independent of the bonded contracts negated the obligee’s termination of the
principal, and holding that obligee’s notices to surety which stated the
principal’s rights had been cancelled were sufficient to expressly and
unequivocally terminate the principal’s rights under the contract). See also
Travelers Cas. And Sur. Co. of Am. v. Crystal Towers, LLC, No. 08-0518-KD-C,
2009 WL 5068823, at *14-15 (S.D. Ala. Dec. 17, 2009) (rejecting obligee’s
argument that surety waived the condition precedent in Paragraph 3.2 because
“the fact that some of the action taken by [the surety] may have been the same
as it would taken had the duty to perform arose is not sufficient evidence from
which a reasonable jury could find that [the surety] waived its contractual
right”).
D. Paragraph
3.3 – Agreement to Pay Contract Balance
The third condition
precedent under Paragraph 3.3 to the Surety’s performance bond obligations is
that the Owner agrees to pay the balance of the contract price to the Surety or
to the Surety’s replacement contractor. A majority of case decisions recognize
Paragraph 3.3 as a condition precedent to the Surety’s performance obligations;
however, some courts have refused to require strict compliance with the duty to
agree to turn over the remaining contract balance where no such balance exists.
See Mid-State Sur. Corp. v. Thrasher Engineering, Inc., 575 F.
Supp.2d 731, 743 (S.D. Va. 2008) (concluding that “since there was no balance to
be paid to [surety] on the Completion Agreement at the time of [bond
principal’s] breach, it was not possible for [bond obligee] to comply with
Paragraph 3.3 of the Performance Bond and it was excused from doing so”);
U.S. Fid. and Guar. Co. v. Braspetro Oil Ser. Co., 369 F.3d 34, 58-59 (2d
Cir. 2004) (observing that with respect to compliance with Paragraph 3.3., “the
relevant inquiry is whether the Obligees actually agreed to pay the Balance of
the Contract Price – not, as the Sureties urge, whether the Obligees agreed with
the Sureties’ assessment of what the respective Balances were at the time of the
declarations of default,” and holding that Obligees’ letters stating that they
agreed to pay the balance of the contract price to the Sureties, but
unfortunately there is no balance remaining, complied with Paragraph 3.3). Other
courts have likewise dispensed with a formalistic reading of Paragraph 3.3 and
rejected the Surety’s argument that the Owner’s notice must track the language
of Paragraph 3.3 verbatim. See Sleeper Village, LLC v. NGM Ins. Co., No.
09-cv-44-PB, 2010 WL 1434306 (D.N.H. 2010) (not for publication) (rejecting
surety’s argument that bond obligee’s notice did not comply with Paragraph 3.3
because it never explicitly agreed to pay the balance of the contract price to
the new contractor, and alternatively, it failed to specifically identify the
balance of the contract price that was available to fund the completion
contract, on the grounds that surety’s letter in response to declaration of
default acknowledged that the bond obligee had agreed to tender the contract
balance, and moreover, the language of the performance bond does not require the
obligee to disclosure the exact contract balance in its notice); LBL
Skysystems (USA), Inc. v. APG-Am., Inc., Civil Action No. 02-5379, 2006 WL
2590497 (E.D. Pa. 2006) (concluding that bond obligee had complied with the
condition precedent found in Paragraph 3.3 of the A312 Performance Bond where
the obligee’s letter stated that it would pay the balance of the contract price
to the surety in accordance with the terms of the construction contract or to a
contractor selected to perform the construction contract in accordance with the
terms of the contract with the obligee and agrees to comply with all other
provisions of the performance bond required to be performed by obligee).
However, courts have rejected arguments by owners that compliance with Paragraph
3.3 was not required because the surety did not specifically request an owner
pay the contract balance. See Solai & Cameron, Inc. v. Plainfield Cnty
Consol. Sch. Dist. No. 202, 374 Ill.App.3d 825, 871 N.E.2d 944 (Ill. Ct.
App. 2007) (rejecting bond obligee’s argument that it was not obligated under
the A312 Performance Bond to agree to pay the surety the balance of the contract
because the surety did not specifically request the bond obligee to pay the
surety the balance due on the contract ), or because the owner otherwise did not
state in its notice to the surety that it agreed to pay the contract balance.
See Developers Sur. and Ind. Co. v. Dismal River Club, LLC, No
4:07CV3178, 2008 WL 2223872 (D.Neb. 2008) (finding that bond obligee failed to
comply with Paragraphs 3.2 and 3.3 where obligee’s letters to the principal and
its surety never formally terminated the bond principal’s right to complete the
project nor agreed to pay the balance of the contract price to complete the
project); Bank of Brewton, Inc. v. Int’l Fid. Ins. Co., 827 So.2d 747,
752-54 (S. Ct. Ala. 2002) (holding that obligee/bank’s letter to surety failed
to state that the obligee agreed to the balance of the contract to price to the
surety or to a contractor selected to complete the original contract; thus the
bank did not substantially comply with the performance bond).
E. Paragraph 4 – Surety’s
Performance Options
The A312-1984
Performance Bond sets forth Surety’s performance options in the event the Owner
satisfies the condition precedents provided for under Paragraph 3. Under
Paragraph 4, a Surety has the right to elect one of four options. Paragraph 4 of
the bond provides as follows:
4. When the
Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly and
at the Surety’s expense take one of the following actions:
4.1 Arrange
for the Contractor, with consent of the Owner; to perform and complete the
Construction Contract; or
4.2
Undertake to perform and complete the Construction Contract itself, through its
agents or through independent contractors; or
4.3 Obtain
bids or negotiated proposals from qualified contractors acceptable to the Owner
for a contract for performance and completion of the Construction Contract,
arrange for a contract to be prepared for execution by the Owner and the
contractor selected with the Owner’s concurrence, to be secured with performance
and payment bonds executed by a qualified surety equivalent to the bonds issued
on the Construction Contract, and pay to the Owner the amount of damages as
described in Paragraph 6 in excess of the Balance of the Contract Price incurred
by the Owner resulting from the Contractor’s default; or
4.4 Waive
its right to perform and complete, arrange for completion, or obtain new
contractor and with reasonable promptness under the circumstances:
1.
After investigation, determine the amount for which it may be liable to the
Owner and, as soon as practicable after the amount is determined; tender payment
therefore to the Owner; or
2. Deny liability in whole or in part and
notify the Owner citing reasons therefore.
Like Paragraph 3
cases, most reported cases addressing an obligee’s failure to permit the surety
to exercise its performance options, under Paragraph 4, have discharged the
surety without a showing of prejudice. See St. Paul Fire & Marine Ins. Co. v.
VDE Corp., 603 F.3d 119, 123-24 (1st Cir. 2010) (affirming district
court’s finding that obligee materially breached the bond by insisting that
surety could not employ the bond principal as completion contractor under
Paragraph 4.2, which entitled surety to discharge of its obligations to perform
under the bond); Fidelity & Deposit Company of Maryland v. Jefferson County
Commission, 2010 WL 48 79115 (N.D. Ala. Nov. 17, 2010) (same holding);
Solai & Cameron, Inc. v. Plainfield Cnty. Consol. Sch. Dist. No. 202, 374
Ill.App.3d, 825, 871 N.E.2d 944 (Ill. Ct. App. 2007) (holding that
obligee exceeded its authority under the Performance Bond by hiring its own
replacement contractor first and thereafter declaring a subcontractor default
and termination, which negated the surety’s options under Paragraphs 4.1, 4.2
and 4.3 of the Performance Bond and thereby nullified the surety’s duty to
perform); Seaboard Sur. Co. v. Town of Greenfield, 370 F.3d 215 (1st Cir.
2004) (owner’s refusal to allow completion by surety pursuant to Paragraph 4.2
and failure to issue 15 day notice of alleged surety default prior to
undertaking owner completion constituted a material breach of the bond
discharging the surety); Enter. Capital, Inc. v. San-Gra Corp., 284 F.
Supp.2d 166, 179-81 (D. Mass. 2003) (concluding that obligee’s failure to comply
with notice requirement of Paragraph 3 of the A312-1984 Performance Bond was a
material breach that precluded surety from exercising its completion options
under Paragraph 4 of the bond, resulting in the bond being null and void).
The leading and
most influential case in this field is St. Paul Fire & Marine Ins. Co. v.
City of Green River, 93 F.Supp.2d 1170 (D. Wyo. 2000), aff’d 6 Fed. Appx.
828 (10th Cir. 2001). At issue in Green River were Paragraph 4.1 (which
allows Surety to arrange for Contractor, with the consent of Owner, to complete
the project) and Paragraph 4.2 (which gives Surety the right to complete
through its agents or through independent contractors). The Surety opted under
Paragraph 4.2 to complete by using its bond principal, but Owner objected under
Paragraph 4.1 to completion by the Contractor without Owner’s consent, refused
Contractor access to the jobsite, and ultimately terminated Surety’s right to
perform and completed with its own forces. The Green River court ruled
for the Surety and discharged the bond. Its analysis was that Paragraph 4.2
contains no limitation on who the Surety may utilize to complete, and Paragraph
4.1 (which requires Owner consent) is fundamentally distinct from Paragraph 4.2
(which does not require Owner consent). Under Paragraph 4.1 where Surety
arranges for completion by its principal, Surety does not assume primary
responsibility for completing the contract. In contrast, under Paragraph 4.2,
Surety assumes primary responsibility to complete the contract, and with that
“the freedom to assemble the project team of its choosing.” Based on this
premise, the Green River court reasoned as follows:
While it makes sense that the owner would have the right to object to such a
“shotgun wedding” to the contractor it just terminated, it does not follow that
the [owner] would have this right when the surety assumes primary contractual
responsibility. In fact, the surety performance options contained in the
performance bond are standard in the industry, and it is common practice for a
surety that elects to perform the project itself hire the principal’s employees
under the direction of a consultant, just as St. Paul did here.
93 F.Supp.2d at 1177-78.
Accordingly, the
court held that St. Paul’s proposed use of its principal’s personnel did not
constitute an anticipatory breach, and owner, City, did not have the right to
terminate St. Paul. Having determined that the City did not have the right to
terminate St. Paul, the court then evaluated the implications of the City’s
wrongful termination. The court started from the premise that “[i]f the [City’s]
action constituted a material breach, St. Paul is excused from further
performance under the contract.” The court went on to note that “[c]ourts have
consistently held that an obligee’s action that deprives a surety of its ability
to protect itself pursuant to performance options granted under a performance
bond constitutes a material breach, which renders the bond null and void.” Based
on this, the court concluded that because St. Paul would not have entered into
the performance bond in the absence of its performance options under Paragraph
4, the City’s action depriving St. Paul of those options was a material breach
which discharged St. Paul from any further duty under the bond. Accordingly, the
court granted judgment in favor of St. Paul.
F. Paragraph 6 – Recoverable Damages
In the discussion
of the A311 Performance Bond, page 12 above, it was explained that courts
interpreting the A311 Performance Bond have disagreed as to whether actual delay
damages or liquidated damages are recoverable by the obligee against the surety.
This debate was resolved against the surety in the A312-1984 Performance Bond,
Paragraph 6, which reads as follows:
6. After the Owner has terminated the Contractor’s right to complete the
Construction Contract, and if the Surety elects to act under Subparagraph 4.1,
4.2, or 4.3 above, then the responsibilities of the Surety to the Owner shall
not be greater than those of the Contractor under the Construction Contract, and
the responsibilities of the Owner to the Surety shall not be greater than those
of the Owner under the Construction Contract. To the limit of the amount of this
Bond, but subject to commitment by the Owner of the Balance of the Contract
Price to mitigation of costs and damages on the Construction Contract, the
Surety is obligated without duplication for:
* * *
6.3 Liquidated
damages, or if no liquidated damages are specified in the Construction Contract,
actual damages caused by delayed performance or non-performance of the
Contractor.
Clearly the
surety is responsible, under this bond form for actual delay damages or
liquidated damages to the same extent as the principal and to the limit of the
bond. Notably this provision was not changed in the A312-2010 Performance Bond
(although the numbering was changed to Paragraph 7).
G. Paragraph 9 – Limitations Period
Paragraph 9 of
the A312-1984 Performance Bond imposes a limitation period, different than the
A311-1970 Performance Bond, upon which a suit may be commenced upon the bond.
Paragraph 9 provides in pertinent part that:
Any proceeding, legal or equitable,
under this Bond may be instituted in any court of competent jurisdiction in the
location in which the work or part of the work is located and shall be
instituted within two years after Contractor Default or within two years after
the Contractor has ceased working or within two years after the Surety refuses
or fails to perform its obligation under this Bond, whichever occurs first. If
the provisions of this Paragraph are void or prohibited by law, the minimum
period of limitation available to sureties as a defense in the jurisdiction of
the suit shall be applicable.
A number of courts
have recently handed down decisions construing the two year limitation period in
the A312 Performance Bond with mixed results for sureties. In ADP Marshall,
Inc. v. Noresco, LLC, C.A. No. 07-129ML, 2010 WL 1753585 (Dist.R.I. Apr. 30, 2010), the Rhode
Island District Court enforced the two year limitation period found in the
A312-1984 Performance Bond, and rejected the bond obligee’s argument that the
limitation period tolled based upon the obligee’s having filed cross-claims in a
state court lawsuit which solely involved payment bond claims. On the other
hand, see City of Santa Fe v. Travelers Cas. & Sur. Co., 228
P.3d 483 (N.M. 2010), already discussed in the prior A311-1970 section of this
article addressing bond limitations clauses. The City of Santa Fe court’s
problem with the surety’s position had nothing to do with how the A312 bond was
drafted, rather the court rejected the surety’s argument that the obligee had
agreed to the bond limitations clause when it accepted the bond. To say the
least this was an outcome-driven decision, and to reach that decision the court
had to employ questionable legal analysis.
Another case
wrongly decided against the surety is Millsboro Fire Co. v. Constr. Mgmt.
Serv., Inc., C.A. No. 05C-06-137-MMJ, 2009 WL 846614 (Del. Super. Ct. 2009)
(unpublished opinion). In this case, the date of Contractor Default and the date
Contractor ceased working were both considerably more than two years before suit
by Owner was filed against Surety Fidelity and Deposit Company of Maryland
(“F&D”). The only date in Paragraph 9 of the A312-1984 Performance Bond, which
was within two years of filing suit, was F&D’s denial of the claim. But the
court could not bring itself to dismiss F&D on its bond limitations defense.
According to the court, the limitations period of the bond does not begin to run
until the insurer denies coverage and notifies the insured of the rejection of
any claim for such benefits (“Until denial of coverage, there is no justiciable
controversy”). Thus, F&D’s limitations defense was rejected by the Millsboro
Court. Further, the Millsboro Court also reasoned that “[g]enuine issues
of material fact exist as to whether F&D, as surety, dealt fairly with MFC in
responding to MFC’s requests for F&D’s position on payment of claim, thereby
creating [a] triable issue of estoppel.”
In this article’s
A311-1970 Performance Bond discussion of its limitations period, pages 14-15
above, the reader was cautioned that if the bond limitations period is shorter
than the minimum time prescribed by statute in a particular jurisdiction, the
clause will be invalidated. One important difference in the A312-1984
Performance Bond is that the bond limitations clause, Paragraph 9, has a savings
provision as follows: “If the provisions of this Paragraph are void or
prohibited by law, the minimum period of limitation available to sureties as a
defense in the jurisdiction of the suit shall be applicable.” By changing from
an invalidated limitations clause (found in the A311-1970 Performance Bond) to a
minimally permitted limitations clause (found in the A312-1984 Performance
Bond), the AIA significantly reduced “late” bond claims which may be filed
against sureties. Savings clauses in bonds are generally upheld by courts.
See e.g., City of Santa Fe v. Travelers Cas. Sur. Co., 147 N.M. 699, 703,
228 P.3d 483, 487 (N.M. 2010).
H. A312-1984
– Payment Bond
The reader will
note that there has been no discussion thus far in this article about AIA
payment bonds. The reason is that the A311-1970 Payment Bond is straightforward
and non-controversial. The same cannot be said, however, of the A312-1984
Payment Bond.
The controversial
clause of the A312-1984 Payment Bond is Paragraph 6, which reads as follows:
6. When the Claimant has
satisfied the conditions of Paragraph 4, the Surety shall promptly and at the
Surety’s expense take the following actions:
6.1 Send an answer to the
Claimant, with a copy to the Owner, within 45 days after receipt of the claim,
stating the amounts that are undisputed and the basis for challenging any
amounts that are disputed.
6.2 Pay or arrange for
payment of any undisputed amounts.
Paragraph 6 refers to
the Claimant satisfying the conditions of Paragraph 4, which reads as follows:
4. The Surety
shall have no obligation to Claimants under this Bond until:
4.1 Claimants who are
employed by or have a direct contract with the Contractor have given notice to
the Surety (at the address described in Paragraph 12) and sent a copy, or notice
thereof, to the Owner, stating that a claim is being made under this Bond and,
with substantial accuracy, the amount of the claim.
4.2 Claimants who do not have
a direct contract with the Contractor:
1. Have
furnished written notice to the Contractor and sent a copy, or notice thereof,
to the Owner, within 90 days after having last performed labor or last furnished
materials or equipment included in the claim stating, with substantial accuracy,
the amount of the claim and the name of the party to whom the materials were
furnished or supplied or for whom the labor was done or performed; and
2. Have
either received a rejection in whole or in part from the Contractor, or not
received within 30 days of furnishing the above notice any communication from
the Contractor by which the Contractor has indicated the claim will be paid
directly or indirectly; and
3. Not
having been paid within the above 30 days, have sent a written notice to the
Surety (at the address described in Paragraph 12) and sent a copy, or notice
thereof, to the Owner, stating that a claim is being made under this Bond and
enclosing a copy of the previous written notice furnished to the Contractor.
Essentially, these two clauses
require that when a proper payment bond claim is submitted to the Surety, the
Surety must respond to the claim within 45 days: if the response is a denial, in
whole or in part, within that 45 day time period the Surety must state the
amount of the claim that is undisputed and the basis for such dispute of the
claim. Although no time period is expressly stated, within a reasonable time
thereafter the Surety must pay the undisputed amount to the Claimant.
But, in reality, some
payment bond claims are complicated and require more than 45 days to determine.
What happens under the A312-1984 Payment Bond if the Surety does not timely
respond to the Claimant? Unfortunately under the case law interpreting Paragraph
6, the answer is that the Surety has waived its right to dispute the claim.
See National Union Fire Insurance Co. v. Bramble, 388 Md. 195, 213 879 A.2d
101 (Md. Ct. App. 2005) (“Therefore, the effect of the provisions in Paragraph 6
is that the entirety of the claim is undisputed and the sureties are required to
promptly pay the claims submitted by Wadsworth and Bramble”); Casey v.
Seaboard Surety Co., 2006 WL 3299932 (E.D. Va. 2006); Gibson Plastering
Co. v. XL Specialty Insurance Company, 521 F.Supp.2d 1326 (M.D. Fla. 2007).
These cases were
extremely troubling for the surety industry, as the belief of most surety claim
professionals was that these cases were not only wrongly decided but, as a
practical matter, made it unreasonably difficult for the surety to avoid waiver
of defenses. In response to Bramble and other cases following
Bramble’s holding, in May, 2008 the AIA (at the SFAA’s urging) issued a
stopgap Amendment to the A312-1984 Payment Bond as follows:
The AIA recommends amending
Section 6 of A312-1984 as follows:
§ 6 When the Claimant has satisfied the conditions of Section 4, the Surety
shall promptly and at the Surety’s expense take the following actions:
§ 6.1 Send an answer to the Claimant, with a copy to the Owner, within
4560
days after receipt of the claim, stating the amounts that are undisputed and the
basis for challenging any amounts that are disputed.
§ 6.2 Pay or arrange for payment of any undisputed amounts.
§ 6.3 The Surety’s failure to discharge its obligations under this Section 6
shall not be deemed to constitute a waiver of defenses the Surety or Contractor
may have or acquire as to a claim. However, if the Surety fails to discharge its
obligations under this Section 6, the Surety shall indemnify the Claimant for
the reasonable attorneys’ fees the Claimant incurs to recover any sums found to
be due and owing to the Claimant.
The complete AIA Amendment (really
a Rider to the A312-1984 Payment Bond), with AIA explanation for the Amendment,
is attached hereto as Exhibit “3.”
The Amendment
expressly stated that the Surety’s failure to timely respond to a payment bond
claim was not to be deemed a waiver of defenses (although the Surety was then
exposed to liability for the Claimant’s reasonable attorneys’ fees). The authors
believe the Amendment was a fair and reasonable approach to correct Bramble
and other mistaken court rulings. However in the negotiations leading to the
revised A312-2010 Payment Bond, this was a hot topic of debate. The surety
industry won this point in the new bond form, as will be discussed below, but
gave up other points in the negotiations which will clearly hurt sureties in the
long run when addressing A312-2010 Performance Bond claims.
IV.A312-2010 BONDS
A. Penal Sum of Performance Bond
By far the most
controversial aspect of the A312-2010 Performance Bond is its explicit
provisions which make the penal sum inapplicable under certain circumstances.
Paragraph 5 of the
Performance Bond gives the Surety four options upon the Owner’s satisfaction of
conditions precedent, as follows:
5. When the Owner has
satisfied the conditions of Section 3, the Surety shall promptly and at the
Surety’s expense take one of the following actions:
5.1 Arrange
for the Contractor, with the consent of the Owner, to perform and complete the
Construction Contract;
5.2 Undertake to perform and complete the Construction Contract itself, through its
agents or independent contractors;
5.3 Obtain
bids or negotiated proposals from qualified contractors acceptable to the Owner
for a contract for performance and completion of the Construction Contract,
arrange for a contract to be prepared for execution by the Owner and a
contractor sel3ected with Owner’s concurrence, to be secured with performance
and payment bonds executed by a qualified surety equivalent to the bonds issued
on the Construction Contract, and pay to the Owner the amount of damages as
described in Section 7 in excess of the Balance of the Contract Price incurred
by the Owner as a result of the Contractor Default; or
5.4 Waive
its right to perform and complete, arrange for completion, or obtain a new
contractor and with reasonable promptness under the circumstances:
1. After
investigation, determine the amount for which it may be liable to the Owner and,
as soon as practicable after the amount is determined, make payment to the
Owner; or
2. Deny
liability in whole or in part and notify the Owner, citing the reasons for
denial.
Paragraph 8 of the
Performance Bond limits the Surety’s liability to the amount of the bond if the
Surety acts under 5.1 (arranges for the Contractor to complete, with consent of
the Owner), 5.2 (tenders new contractor to Owner and pays Owner for any
deficiency), and 5.4 (either makes payment to Owner or denies liability to
Owner). What is missing from Paragraph 8 is option 5.2 (Surety takes over and
completes bonded project). Thus, when the Surety elects to proceed with a
takeover under option 5.2, the Surety’s liability is clearly not limited to the
penal sum unless the Surety’s takeover agreement with the Owner contains a penal
sum limitation clause.
Proponents of the
A312-2010 Performance Bond will point out certain case law which holds that a
surety’s liability is not limited to the penal sum in a takeover situation
unless a penal sum limit is written into the takeover agreement with the owner.
See Int’l Fid. Ins. Co. v. City of Rockland, 98 F.Supp.2d 400, 428
(S.D.N.Y. 2000); U.S. Fid. and Guar. Co. v. Braspetro Oil Serv. Co., 369
F.3d 34 (2d. Cir. 2004); Employers Mut. Cas. Co. v. United Fire Cas. Co.,
682 N.W. 2d 452, 457 (Iowa Ct. App. 2004). In other words, according to the
A312-2010 proponents, Paragraphs 5 and 8 of the Performance Bond are nothing
more than a recitation of existing law. Also see page 3 of the AIA Bond Form
Commentary and Comparison, Exhibit “6” to this article, which explains the
policy reason for not making the bond penal sum applicable to a surety takeover
(“this limitation could leave the owner with an unfinished project once the
surety has expended the amount of the bond”) unless the owner expressly agrees
to the bond penal sum limit in a takeover agreement with the surety. Most surety
professionals would disagree with this policy argument; their counter would be
that the surety only received consideration for, and assumed risk, to the bond
limit and so the owner should bear the costs of project completion in excess of
the bond penal sum.
In reality the
practical problem, based on the authors' experience, is that the A312-2010
Performance Bond diminishes the surety’s bargaining leverage with the owner and
makes it more difficult to negotiate a penal sum limitation in the takeover
agreement. Previously the surety’s attorney could effectively argue, for example
under Paragraph 6 of the A312-1984 Performance Bond, that the surety’s liability
under any option was “the limit of the amount of this Bond.” Now under the
A312-2010 Performance Bond that argument is gone and, further, the owner’s
attorney can effectively argue that the bond was not intended to give the surety
a penal sum limitation in a takeover situation. Unfortunately, it is expected
that owners will now be more stubborn on this penal sum issue, forcing the
surety dealing with an A312-2010 Performance Bond claim to either elect a
takeover without a penal sum limitation or go for another Paragraph 5 option.
Another, less obvious,
way that the A312-2010 Performance Bond penal sum can be blown is based on
Paragraph 6, which reads as follows:
6. If the Surety does not
proceed as provided in Section 5 with reasonable promptness, the Surety shall be
deemed to be in default on this Bond seven days after receipt of an additional
written notice form the Owner to the Surety demanding that the Surety perform
its obligations under this Bond, and the Owner shall be entitled to enforce any
remedy available to the Owner. . . .
The above-quoted
clause is not substantively different from Paragraph 5 of the A312-1984
Performance Bond, except that the period of time for the Surety to act has been
shortened from fifteen days to seven days after receipt of the Owner’s cure
notice. If the Surety does respond and exercises one of its Paragraph 5 options,
then Paragraph 6 of the A312-2010 Performance Bond states that “the Surety shall
be deemed to be in default on this Bond.”
What is the effect of
the Surety being deemed in default on the Bond? In Continental Realty v.
Crevolin, 380 F.Supp. 246 (S.D. W.Va. 1974), involving a non-AIA performance
bond, it was held that if the surety fails to perform in accordance with its
bond options, then the surety is in default of the bond and its liability is not
limited to the bond penal sum. Notably there are non-AIA bond cases which
disagree with Crevolin and hold that a surety’s failure to perform does
not expose the surety to bond liability in excess of the penal sum. In re
Tech for Energy Corp., 123 B.R. 979 (Bktrcy Ct. E.D. Tenn. 1991);
Employers Mut. Cas. Co. v. United Fire and Cas. Co., 682 NW 2d 452 (Iowa Ct.
App. 2004). There are no cases directly addressing Paragraph 6 of the A312-2010
Performance Bond or its predecessor Paragraph 5 of the A312-1984 Performance
Bond. Thus it is impossible to accurately predict, in most jurisdictions, how
courts will treat the liability of a surety who fails to timely respond to an
obligee’s cure notice and thus is in default of the A312-1984 or A312-2010
Performance Bond.
B. Notice
and Request for Conference Pursuant to Performance Bond
In the above
discussion of the A312-1984 Performance Bond, it was pointed out that a number
of courts have strictly enforced the requirements of Paragraph 3.1 (Owner gives
pre-default notice to Contractor and Surety that Owner is considering declaring
a default, and Owner requests conference with Contractor and Surety), to the
point that failure of the Owner to comply with Paragraph 3.1 was a complete
defense for the Surety without a showing of prejudice.
This surety defense
was significantly reduced by Paragraph 3 of the A312-2010 Performance Bond,
which reads as follows:
3. If there is no Owner Default under the Construction Contract, the
Surety’s obligation under this Bond shall arise after
.1 the Owner first provides notice to the Contractor and the Surety that
the Owner is considering declaring a Contractor Default. Such notice shall
indicate whether the Owner is requesting a conference among the Owner,
Contractor and Surety to discuss the Contractor’s performance. If the Owner does
not request a conference, the Surety may, within five (5) business days after
receipt of the Owner’s notice, request such a conference. If the Surety timely
requests a conference, the Owner shall attend. Unless the Owner agrees
otherwise, any conference requested under this Section 3.1 shall be held within
ten (10) business days of the Surety’s receipt of the Owner’s notice. If the
Owner, the Contractor and the Surety agree, the Contractor shall be allowed a
reasonable time to perform the Construction Contract, but such an agreement
shall not waive the Owner’s right, if any, subsequently to declare a Contractor
Default;
.2 the Owner declares a Contractor Default, terminates the Construction
Contract and notifies the Surety; and
.3 the Owner has agreed to pay the Balance of the Contract Price in
accordance with the terms of the Construction Contract to the Surety or to a
contractor selected to perform the Construction
Contract.
The A312-1984 bond
form required the Owner to give notice and request a conference within 15 days,
and then declare a default not earlier than 20 days after the notice; the
A312-2010 bond form does not require the Owner to request a conference (a
conference may still be requested by the Surety) and does not limit when the
Owner may declare a Contractor Default. Thus the waiting time periods for the
Owner to act were streamlined in the 2010 bond form.
Unfortunately for the
surety industry, the case law which provided the Surety with a full defense for
the Owner’s non-compliance with Paragraph 3 was given up in the negotiation
process. Paragraph 4 of the A312-2010 Performance Bond states:
4. Failure on the part of the
Owner to comply with the notice requirement in Section 3.1 shall not constitute
a failure to comply with a condition precedent to the Surety’s obligations, or
release the Surety from its obligations, except to the extent the Surety
demonstrates actual prejudice.
Thus, the Surety now has a pro
tanto defense, to the extent of prejudice, due to the Owner’s non-compliance
with Paragraph 3.1. Presumably the Surety will still have a full defense due to
the Owner’s non-compliance with Paragraph 3.2 (Owner must declare a Contractor
Default and terminate Contractor) and Paragraph 3.3 (Owner must agree to pay
balance of bonded contract to Surety).
C. L&A
Contracting/Colorado Structures Issue Under Performance Bond
The discussion
in this article, page 6-11, regarding the A311-1970 Performance Bond was
extensive about the L&A Contracting/Colorado Structures debate as
to conditions precedent to bond coverage. In the discussion, pages 17-18,
regarding the A312-1984 Performance Bond, it was pointed out that no court
should reach a Colorado Structures misinterpretation of this bond form
because alternative coverage clauses cannot be read into this bond. The same is
true for the A312-2010 Performance Bond. Paragraphs 3 and 4 make clear that 3.1,
3.2 and 3.3 are acts of the Owner which are conditions precedent to coverage,
and an Owner’s failure to so act gives rise to either a full defense (3.2 and
3.3) or a pro tanto defense (to the extent of prejudice) for the Surety.
Significantly,
Paragraph 3 provides another potentially full condition precedent defense for
the Surety. The introductory clause to Paragraph 3 states that the Surety’s
obligation under the bond arises “if there is no Owner Default under the
Construction Contract.” The term “Owner Default” is defined in Paragraph 14.4 to
be “Failure of the Owner, which has not been remedied or waived, to pay the
Contractor as required under the Construction Contract or to perform and
complete or comply with the other material terms of the Construction Contract.”
The surety claims professional should carefully review the bonded contract and
applicable statutes (for example, a state’s Prompt Pay Act) to determine if the
Owner has failed to pay or otherwise materially breached its obligations to the
Contractor. If the answer is yes, then the Surety has no obligation to the Owner
under the A312-1984 or A312-2010 Performance Bond.
D. A312-2010
Payment Bond Issues
Notably, coverage was
broadened under the A312-2010 Payment Bond by expanding the definition of
“Claimant” under Paragraph 16.2. Previously, under the A312-1984 Payment Bond,
parties with standing to bring a payment bond claim were those in privity with
the Contractor or with a subcontractor to the Contractor. Now, under the new
A312-2010 Payment Bond, parties entitled to bring a bond claim also includes
“any individual or entity that has rightfully asserted a claim under an
applicable mechanic’s lien or similar statute against the real property upon
which the Project is located.” The rationale of this change is that because the
intent of a payment bond is to protect an owner from liens, the payment bond
should allow claims by all rightful lien claimants. This change is obviously not
applicable to public projects, as these are not lienable projects. With regard
to private projects, the surety claims handler will need to investigate local
laws to determine if a particular questionable party (for example, a third tier
subcontractor) has standing to file a mechanic’s lien and thereby has standing
to bring a bond claim under the A312-2010 Payment Bond.
There were other minor
changes to the A312-2010 Payment Bond which will not be discussed in this
article. The major change, and the topic of much debate within the AIA, was the
consequence of a Surety’s failure to timely respond to a payment bond claim.
Earlier in this article, when discussing the A312-1984 Payment Bond, it was
noted a number of courts have ruled that the Surety’s failure to respond to a
claim within 45 days (the time period required by the Payment Bond) resulted in
a waiver by the Surety of its bond defenses. These cases were clearly wrongly
decided and contrary to the intent of the AIA bond drafters, to the point that
in May 2008 the AIA itself recommended a stopgap Amendment to override these
cases. This Amendment or Bond Rider is
attached as Exhibit “3” to this
article.
The A312-2010 Payment
Bond adopts the May 2008 stopgap Amendment recommended by the AIA. In Paragraph
7, the Surety is given 60 days (increased from 45 days) to respond to a proper
payment bond claim. The Surety’s response must include a statement as to amount
of the claim that is undisputed, the Surety must pay the undisputed amount, and
the Surety must state in writing the basis for challenging any items of the
claim that are disputed. In a major concession to the surety industry, the
Surety’s failure to timely respond was expressly stated not to result in a
waiver of defenses to the claim. Paragraph 7.3 reads as follows:
7 When a Claimant has
satisfied the conditions of Section 5.1 or 5.2, whichever is applicable, the
Surety shall promptly and at the Surety’s expense take the following actions:
7.1 Send an answer to the Claimant, with a copy to the Owner, within sixty
(60) days after receipt of the Claim, stating the amounts that are undisputed
and the basis for challenging any amounts that are disputed; and
7.2 Pay or arrange for payment of any undisputed amounts.
7.3 The Surety’s failure to discharge its obligations under Section 7.1 or
Section 7.2 shall not be deemed to constitute a waiver of defenses the Surety or
Contractor may have or acquire as to a Claim, except as to undisputed amounts
for which the Surety and the Claimant have reached agreement. If, however, the
Surety fails to discharge its obligations under Section 7.1 or Section 7.2, the
Surety shall indemnify the Claimant for the reasonable attorney’s fees the
Claimant incurs thereafter to recover any sums found to be due and owing to the
Claimant.
Many in the surety
industry question whether this victory – i.e., that an untimely response to a
payment bond claim no longer results in a waiver of defenses – justifies the
other concessions made by the surety industry in the A312-2010 bond forms. This
author agrees with the critics of the new AIA bond forms; in the authors'
opinion, more was lost than gained by the surety industry in the transition from
A312-1984 to A312-2010 bonds.
V. A310-2010 Bid Bond
The A310-2010 Bid Bond
is a short and straightforward bond form. It is not a penalty bond, i.e., in the
event that the Contractor does not enter into a contract with the Owner, then
the Surety is responsible for the excess cost to the Owner of entering into a
contract with another party – not to exceed the penal sum of the bond. Among
other things, the Bid Bond provides that the time for Owner’s acceptance of bids
may be extended for 60 days beyond the bid documents without the Surety’s
consent.
Perhaps most striking
in the A310-2010 Bid Bond is its requirement that the bond be issued by a
“surety admitted in the jurisdiction of the Project and otherwise acceptable to
the Owner.” Prevalence of individual sureties and fraudulent bonds is a
significant problem in the surety industry. See E. Gallagher, “The Importance
of Surety Bond Verification”, 39 Pub. Cont. L.J. 269 (2010). There is no
question that the AIA intended to have only sureties, approved and licensed by
the local insurance departments, issuing A310-2010 Bid Bonds. See the following
passage from the AIA Bond Form Commentary and Comparison, page 2 (Exhibit “6” to
this article):
Performance and Payment Bond
Surety. A310-1970 required the Contractor, in satisfying its obligations
under the bid bond, to enter into the construction contract and provide a bond
or bonds as specified in the contract from a “good and sufficient” surety.
However, A310-1970 does not make clear what constitutes a “good and sufficient”
surety. A310-2010 has been modified to state that any bonds provided by the
contractor in fulfilling its obligations under the bidding or contract documents
will be issued by a surety admitted in the jurisdiction of the project and
otherwise acceptable to the owner. The drafters understand that “admitted” is a
term of art in the insurance industry meaning holding a certificate of authority
from the insurance commissioner allowing the admitted entity to issue surety
bonds in that state.
VI. CONCLUSION
There is no question
that the biggest problem with the A312-2010 bonds is that, under certain
circumstances, the surety may be obligated to pay beyond the penal sum of the
Performance Bond. Interestingly this is not a problem under the A312-2010
Payment Bond, because this bond form contains an absolute limitation clause as
follows:
8 The Surety’s total
obligation shall not exceed the amount of this Bond, plus the amount of
reasonable attorney’s fees provided under Section 7.3, and the amount of this
Bond shall be credited for any payments made in good faith by the Surety.
Liability beyond the bond penal
sum is also not a problem under the A310-2010 Bid Bond, because again the bond
form expressly states that the Surety’s liability may not “exceed the amount of
this Bond.”
Turning to the
A312-2010 Performance Bond, it is true that sureties issuing performance bonds
have become accustomed (in certain jurisdictions) to claims and lawsuits being
filed against them for alleged bad faith conduct. See, e.g., Dodge v.
Fidelity and Deposit Company of Maryland, 161 Ariz. 344, 778 P.2d 1240 (S.
Ct. AZ 1989) (en banc). Although bad faith claims are frequently abused,
it is understandable that a surety may be held liable for extra-contractual
damages under certain egregious circumstances. What is not understandable,
however, is that a surety may be liable beyond its bond limit if the surety has
not engaged in bad faith conduct. This is why the A312-2010 bond forms have been
subject to extensive criticism in the surety industry.
There is a solution to
the penal sum problem in the A312-2010 Performance Bond. When certain courts
misinterpreted the A312-1984 Payment Bond and held the surety to have waived
defenses by not timely responding to claims, the AIA acted by adopting its 2008
Amendment to A312-1984 Performance Bond. The AIA called this 2008 Amendment a
“stopgap measure” and recommended that a surety include the 2008 Amendment
whenever issuing the A312 Payment Bond.
In the authors'
opinion, a surety issuing the A312-2010 Performance Bond should consider
including the following simple modification to its bond:
Notwithstanding anything to the
contrary herein, the Surety’s total obligation under this Bond shall not exceed
the amount of this Bond.
This modification may
be added to Paragraph 16 of the bond form. The difference between the above
modification and the AIA’s 2008 Amendment to the A312-2010 Payment bond (which
may also be added to the bond form as a modification) is that the 2008 Amendment
was officially sanctioned by the AIA, while the above suggested modification to
the A312 Performance Bond is not officially sanctioned. Certainly an objection
to the modification may be made by an owner/obligee (perhaps contending that the
A312-2010 Performance Bond, with modification, is not the bond specified for the
project). But this same objection could be made by owners/obligees to the AIA’s
2008 Amendment, and to the best of the authors' knowledge there have been no
such issues arising from use of the AIA’s 2008 Amendment. If an objection is
raised to the suggested performance bond modification, then the surety can deal
with the objection on a case-by-case basis. Perhaps the surety may have to
concede this point on rare occasion, but in most situations the owner/obligee
will likely agree to the surety’s very reasonable request that its liability be
limited to the bond amount.
While the A312-2010 bond forms have many good
qualities and are a big improvement over predecessor AIA bonds and many other
bond forms in use today, the potential for liability exceeding the penal sum is
a serious problem for the surety under the A312-2010 Performance Bond. The
suggested modification is, in the authors' opinion, a reasonable solution to
this problem. u
|